2026 Regular Session                                       ENROLLED
    HOUSE BILL NO. 2
    BY REPRESENTATIVE BACALA                        ACT No. 4

1                             AN ACT

2   To provide with respect to the capital outlay budget and the capital outlay program for state

3          government, state institutions, and other public entities; to provide for the

4          designation of projects and improvements; to provide for the financing thereof

5          making appropriations from certain sources; and to provide for related matters.

6   Be it enacted by the Legislature of Louisiana:

7              Section 1.(A) The following sums or so much thereof as may be necessary are

8   hereby appropriated out of any monies in the state treasury from the sources specified, from

9   federal funds and self-generated revenues belonging to the state of Louisiana and/or

10  collected by boards, commissions, departments, and agencies thereof, all for making capital

11  outlay and for the purposes and in the amounts specified herein for the Fiscal Year

12  commencing July 1, 2026, and ending June 30, 2027, subject to the conditions thereafter

13  provided:

14             A project with funding payable from General Obligation Bonds Priority 1

15  indicates that the funding for the project includes the reauthorization of funding which was

16  previously granted as a line of credit by the State Bond Commission in Fiscal Year 2025-

17  2026. As used in this Section, the term "general obligation bonds" means state general

18  obligation bonds or other evidences of indebtedness payable from the Bond Security and

19  Redemption Fund. The amount set forth in this Section opposite each project, or so much

20  thereof as may be necessary, is hereby appropriated and payable from the source of funding

21  indicated; provided, however, amounts appropriated and payable from federal funds may be

22  encumbered or expended only to the extent such amounts shall have been committed or

23  received. Pursuant to the provisions of R.S. 39:82, funds for planning, acquisition,

24  construction, and major repair projects appropriated by this Act may be retained until

25  completion of the project, even if no bona fide liability exists on the last day of the fiscal

26  year.

               Page 1 of 174
    HB NO. 2                 ENROLLED

1             This Act shall constitute the comprehensive state capital outlay budget for the

2   2026-2027 Fiscal Year. Projects set forth which are payable from the proceeds available

3   from the sale of general obligation bonds shall have the priorities as indicated. The Request

4   for Line of Credit form used by the attorney general and Bond Counsel in evaluating

5   Louisiana Constitutional, Internal Revenue Code, and applicable income tax regulations

6   shall be filed with the commissioner of administration, State Bond Commission, and state

7   attorney general. No general obligation bond cash lines of credit shall be granted to fund

8   any lower priority project prior to the granting of general obligation bond cash lines of credit

9   to fund all higher priority projects (the "general rule"), except as hereinafter provided. This

10  prohibition against funding a lower priority project shall not apply upon a showing of an

11  impossibility or impracticality either to proceed with all unfunded higher priority projects

12  or to proceed with the funding of such projects or any part thereof through the issuance of

13  general obligation bonds for any reason. Such showing shall be stated in reasonable detail

14  in a certificate or certificates signed by the state agency responsible for administering the

15  funding, and filed with the commissioner of administration and the State Bond Commission

16  (hereinafter referred to as "the Commission"). Upon a determination by the Commission

17  that proceeding with such a project or the funding thereof through the issuance of general

18  obligation bonds is impractical or impossible, the Commission may then proceed with the

19  sale of general obligation bonds or the granting of cash lines of credit without regard to the

20  priority of the unfunded projects determined to be impossible or impractical.

21            Upon recommendation by the state agency responsible for administering the

22  funding, if it is determined at any time that proceeding with the project or with the funding

23  thereof is no longer impossible or impractical, the State Bond Commission may rescind the

24  certificate of impossibility or impracticality and may proceed with the project or with the

25  issuance of general obligation bonds or the granting of cash lines of credit to fund the

26  project. Alternatively, the Interim Emergency Board (hereinafter referred to as "the Board"),

27  upon reviewing certificates as described above and determining that proceeding with such

28  projects or the funding thereof through the issuance of general obligation bonds is

29  impossible or impractical, may designate a lower priority for such projects. The Board's

30  determination and lower priority designation shall be submitted to the members of the

31  legislature for their approval in accordance with the provisions of Chapter 3-B of Subtitle

              Page 2 of 174
    HB NO. 2                                                           ENROLLED

1   I of Title 39 of the Louisiana Revised Statutes of 1950. In accordance with the provisions

2   of Chapter 3-B of Subtitle I of Title 39 of the Louisiana Revised Statutes of 1950, whenever

3   at the written request of the appropriate legislators and agency, the Board determines that

4   an adjustment to a project description originally set forth in such capital budget adopted by

5   the legislature for a current fiscal year is necessary to correct a mistake in a project

6   description, clarify a description, change the scope of a description, or make any other

7   adjustment the Board deems necessary to implement the purpose of the project, such

8   adjustment shall become effective only upon the approval by majority vote of the elected

9   members of each house of the legislature in the manner provided for in Chapter 3-B of

10  Subtitle I of Title 39 of the Louisiana Revised Statutes of 1950.

11            If such approval is granted, notification by the chair or secretary of the Board of

12  the results of the balloting shall be transmitted to the State Bond Commission, which may

13  then proceed with the sale of general obligation bonds or the granting of cash lines of credit

14  for each change approved upon request of the commissioner of administration in accordance

15  with the general rule.

16            With respect to Priorities 1 through 5, a lower priority project may be moved to

17  a higher priority only upon a showing of an emergency or other cause not reasonably

18  anticipated by the legislature, which shall be stated in reasonable detail in a certificate signed

19  by the head of the appropriate department, political subdivision, or agency and filed with the

20  commissioner of administration and the Board. Upon a determination by the Board that such

21  project should be moved to a higher priority because of an emergency or other cause not

22  reasonably anticipated by the legislature, the Board shall designate a higher priority to the

23  project. The matter then shall be submitted to and be subject to the same approval by the

24  members of the legislature in the manner previously indicated in this Section. If such

25  approval is granted, notification by the chair or secretary of the Board of the change of

26  priority shall be transmitted to the State Bond Commission, which then upon request of the

27  commissioner of administration, may proceed with the sale of general obligation bonds or

28  the granting of cash lines of credit in accordance with the general rule. As to projects within

29  a priority, the State Bond Commission acting on requests submitted by the commissioner of

30  administration shall determine when such project, or phases thereof, shall be funded. In

31  making such determination, the State Bond Commission shall consider the amount of

                            Page 3 of 174
    HB NO. 2                                                     ENROLLED

1   proceeds of general obligation bonds to be made available in light of money and capital

2   market conditions; the expenditure requirements of the project; the time required for

3   architectural plans and drawings, public bidding, and site acquisition and preparation;

4   availability of receipt of federal monies; litigation affecting the undertaking or completion

5   of a project; federal tax laws and regulations regarding the sale of municipal bonds; and

6   other items of a similar nature bearing upon the possibility or the necessity to commence a

7   project or any particular phase thereof.

8             Any other provision of this Act to the contrary notwithstanding, projects

9   described in Priority 5 of this Act shall not be moved to a higher priority except upon one

10  of the following conditions: (1) Funding is necessary to complete or additionally fund a

11  project located elsewhere in the Capital Outlay Act. Determination of such condition shall

12  be made by the head of the appropriate department or agency by means of a certificate to

13  that effect filed with the Interim Emergency Board, who shall, by mail ballot, request

14  approval of such change and if approved by a majority of each house of the legislature it

15  shall be funded, or (2) unless required by an emergency or other cause not reasonably

16  anticipated by the legislature, to be in accordance with procedures set forth in this Section.

17  However, the State Bond Commission may authorize a non-cash line of credit for any

18  project in Priority 5 which represents that portion of construction contracts which were let

19  during a previous fiscal year, or construction contracts which will be let during the current

20  fiscal year, but which will not require cash expenditures during the year. Such non-cash

21  lines of credit, when combined with previously sold bonds or with higher priority bonds or

22  lines of credit, or with funds appropriated from other sources, will provide sufficient

23  appropriated funds to award equipment or construction contracts. Contracts shall not be

24  awarded without approval of the division of administration.

25            Upon approval by the State Bond Commission, and subject to compliance with

26  its policies and procedures and the procedures set forth herein, a line of credit providing for

27  the use of funds in anticipation of the sale of general obligation bonds may be granted to the

28  appropriate administering agency or department from the Comprehensive Capital Outlay

29  Escrow Account, or if there is not a sufficient amount available in such account, from other

30  available state cash in the state treasury, for capital improvement projects for which bond

31  proceeds are appropriated by a current capital budget, prior to the actual issuance of bonds

              Page 4 of 174
    HB NO. 2                                                                   ENROLLED

1   for such projects, unless the attorney general advises that an impediment exists to the valid

2   issuance of the bonds on the date such line of credit is granted.

3             All bonds that are to be repaid, in whole or in part, by revenues generated by the

4   project shall be designated as "Reimbursement Bonds." The State Bond Commission shall

5   enter into such agreements as are necessary to provide that the agency or subdivision, whose

6   project is reimbursable, shall pay the bond debt costs into the Bond Security and Redemption

7   Fund. Such costs may be paid annually or at the end of the term of the bonds issued as

8   determined by the State Bond Commission.

9             Priority 1 general obligation bond funding shall be limited to:

10            (1) Projects and amounts which were previously authorized by Act 2 of the 2025

11  Regular Session of the Legislature; and which were granted cash lines of credit by the State

12  Bond Commission. The bonds to fund these projects were not sold in Fiscal Year 2025-

13  2026.

14            (2) The reauthorization of the portion of the outstanding Fiscal Year 2025-2026

15  Priority 5 Non-Cash Lines of Credit for projects which will require cash expenditures in

16  Fiscal Year 2026-2027 and therefore must be converted to Cash Lines of Credit in Fiscal

17  Year 2026-2027.

18            (3) Commitments made in the Higher Education Desegregation Settlement

19  Agreement.

20            Priority 2 general obligation bond projects are for the completion of plans and

21  specifications, land acquisition, site preparation, or for construction which will begin during

22  the fiscal year. It is presently anticipated that the listed projects will require the sale of

23  bonds or extension of lines of credit during the fiscal year after adoption of this Act.

24            Priority 3 general obligation bond projects are for the preparation of plans and

25  specifications, land acquisition, site preparation, or for construction and shall be limited to

26  funding for the portion of construction contracts which will not require cash expenditures

27  during the fiscal year. The projects in this category shall be considered future year projects

28  in the state's five-year capital outlay plan. It is presently anticipated that the listed projects

29  will not require the sale of bonds or extension of lines of credit during the fiscal year.

30            Priority 4 general obligation bond projects are for the preparation of plans and

31  specifications, land acquisition, site preparation, or for construction and shall be limited to

                     Page 5 of 174
    HB NO. 2                                                              ENROLLED

1   funding for the portion of construction contracts which will not require cash expenditures

2   during the fiscal year. The projects in this category shall be considered future year projects

3   in the state's five-year capital outlay plan. It is presently anticipated that the listed projects

4   will not require the sale of bonds or extension of lines of credit during the fiscal year.

5             Priority 5 general obligation bond funding shall be limited to funding for the

6   portion of construction contracts which will not require cash expenditures during the fiscal

7   year. These funds, when combined with previously sold bonds or with higher priority bonds

8   on lines of credit, or with funds appropriated from other sources, will provide sufficient

9   appropriated funds to award contracts. Non-cash lines of credit shall be required prior to the

10  award of these contracts.

11            In accordance with the cash management plan adopted pursuant to R.S.

12  48:251(D) and the provisions of Act 161 of the 1998 First Extraordinary Session, the

13  Department of Transportation and Development is authorized to enter into contracts or

14  agreements for projects approved pursuant to the Highway Priority Program, Airport

15  Construction and Development Priority Program, Port Construction and Development

16  Priority Program, and Statewide Flood Control Program for projects bid and awarded,

17  authorized, or commenced during the fiscal year which do not require cash expenditures for

18  the full contract or agreement amount.

19                             EXECUTIVE DEPARTMENT

20  01/107 DIVISION OF ADMINISTRATION

21  (576744) State Office Buildings Major Repairs, Equipment

22            Replacement, and Renovations, Planning and Construction

23            (Statewide)

24            Payable from General Obligation Bonds

25            Priority 1                                               $ 5,000,000

26            Priority 5                                               $ 7,110,000

27            Payable from Federal Funds via Interagency Transfers     $ 10,000,000

28            Total                                                    $ 22,110,000

29  (576969) Shreveport Storage Facility, Planning and Construction

30            (Caddo)

31            Payable from State General Fund (Direct) Non-Recurring

32            Revenues                                                 $ 1,440,000

33  (576970) Storage Building Renovation and Paved Catering Pad,

34            Louisiana Governor's Mansion, Planning and Construction

35            (East Baton Rouge)

36            Payable from State General Fund (Direct) Non-Recurring

37            Revenues                                                 $  798,000

                                  Page 6 of 174
    HB NO. 2                                                                ENROLLED

1   (576981) Pentagon Barracks Repair Brick Walls/Mitigate Rising

2             Damp, Planning and Construction

3             (East Baton Rouge)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $ 33,900,000

6   (576983) Exterior Waterproofing and Repairs, Chief Justice

7             Pascal F. Calogero, Jr. Courthouse, Planning and

8             Construction

9             (Orleans)

10            Payable from General Obligation Bonds

11            Priority 1                                                 $ 4,080,818
                                                                         $ 22,300,000
12            Priority 5                                                 $ 26,380,818

13            Total

14  (576986) Exterior Waterproofing at State Capitol Building, Planning

15            and Construction

16            (East Baton Rouge)

17            Payable from General Obligation Bonds

18            Priority 1                                                 $ 28,890,540

19            Priority 5                                                 $ 60,200,000

20            Total                                                      $ 89,090,540

21  (576989) Renovations and Additions, Louisiana Governor's

22            Mansion, Planning and Construction

23            (East Baton Rouge)

24            Payable from General Obligation Bonds

25            Priority 5                                                 $ 2,000,000

26            Payable from State General Fund (Direct) Non-Recurring

27            Revenues                                                   $  225,000

28            Total                                                      $ 2,225,000

29  (578157) Community Water Enrichment Program

30            (Statewide)

31            Payable from General Obligation Bonds

32            Priority 5                                                 $ 11,000,000

33            Payable from State General Fund (Direct) Non-Recurring

34            Revenues                                                   $ 5,000,000

35            Total                                                      $ 16,000,000

36  (578163) Local Government Assistance Program

37            (Statewide)

38            Payable from General Obligation Bonds

39            Priority 5                                                 $ 10,000,000

40            Payable from State General Fund (Direct) Non-Recurring

41            Revenues                                                   $ 3,000,000

42            Payable from the balance of State General Funds (Direct)

43            previously allocated under the authority of Act 485 of

44            2021 for Abbeville Harbor and Terminal District, Port of

45            Vermillion South Slip Entrance Emergency Dredging,

46            Planning and Construction (Vermilion), Act 29 of 2018

47            for Madison Parish Port, Harbor and Terminal District,

48            Improvements to Madison Parish Port former Northrop

49            Grumman Shipbuilding Expansion (Madison), Act 485 of

50            2021 for Acadia Parish, Street Improvements on Hains

51            Road, Planning and Construction (Acadia), Act 2 of 2004

52            for Bossier Parish, Drainage Improvements Mimosa

53            Gardens Subdivision, Planning and Construction

54            (Bossier), Act 2 of 2020 for Jefferson Parish, Brown

55            Avenue Roadway Reconstruction Between the Westbank

56            Expressway and 36th Street, Planning and Construction

                                  Page 7 of 174
    HB NO. 2                                                                 ENROLLED

1             (Jefferson), Act 465 of 2023 for St. Mary Parish, Facility

2             and Infrastructure Improvements at Kemper Williams

3             Park Near Patterson, Planning and Construction (St.

4             Mary), Act 29 of 2018 for Abita Springs, Water Lines and

5             Sewer Lines, Extensions and Upgrades, Planning and

6             Construction (Cash and/or In-Kind Match Required) (St.

7             Tammany), Act 29 of 2018 for Arcadia, Drainage

8             Improvement Louisiana Highway 151 and Gap Farm

9             Road, Planning and Construction (Bienville), Act 117 of

10            2022 for Haughton, Additional Water Supply Wells and

11            Elevated Tank, Planning and Construction (Bossier), Act

12            20 of 2019 for Lake Arthur, Repair and Upgrades to City

13            Hall, Planning and Construction (Jefferson Davis), Act 29

14            of 2018 for Opelousas, Opelousas Infrastructure

15            Renovation Program, Planning and Construction (St.

16            Landry), Act 465 of 2023 IEB for Thibodaux, Andolsek

17            Park, Planning and Construction (Lafourche), Act 485 of

18            2021 for Capitol City Family Health Center, Inc. Care

19            South Medical and Dental Expansion, Planning and

20            Construction (East Baton Rouge), Act 2 of 2025 for

21            Capitol City Family Health Center, Inc., Care South

22            Medical and Dental Expansion, Planning and

23            Construction (East Baton Rouge), Act 20 of 2019 for East

24            Baton Rouge Sheriffs Office, Renovation of Special

25            Operations/Detectives Building, Planning and

26            Construction (East Baton Rouge), Act 485 of 2021 for

27            Monroe Downtown Economic Development District for

28            Monroe Riverwalk, Planning and Construction

29            (Ouachita), Act 21 of 2010 for West Feliciana School

30            Board, Julius Freyhan Cultural/Conference Center,

31            Planning and Construction

32            (West Feliciana)                                            $ 2,103,730

33            Total                                                       $ 15,103,730

34  (578882) Major Repairs, Equipment Replacement and Renovations

35            for State Buildings to Address Deferred Maintenance

36            Backlog and Infrastructure, Planning and Construction

37            (Statewide)

38            Payable from General Obligation Bonds

39            Priority 1                                                  $ 5,000,000

40            Priority 5                                                  $ 25,000,000

41            Payable from the balance of Interest Earnings previously

42            allocated under the authority of Act 52 of 2011 for

43            Division of Administration, Supplemental Funding, New

44            Orleans State Office Facility (Orleans), Act 26 of 2005

45            for Division of Administration, Emergency Major

46            Repairs, Planning and Construction (Statewide), Act 54

47            of 2013 for Nunez Community College, Replace

48            Administration Building at Nunez Community College,

49            Chalmette (Supplemental Funding) (St. Bernard), Act 485

50            of 2021 for Office of Wildlife, Region 5/Lake Charles

51            Office

52            (Calcasieu)                                                 $  349,354

53            Payable from the balance of State General Funds (Direct)

54            previously allocated under the authority of Act 21 of 2000

55            for Division of Administration, Technical College

56            Campus Buildings Major Repairs, Equipment

57            Replacement and Site Work, Planning and Construction

58            (Statewide), Act 29 of 1998 for Division of

59            Administration, Technical College Campus Buildings

                                Page 8 of 174
    HB NO. 2                                                             ENROLLED

1             Major Repairs, Equipment Replacement and Site Work,

2             Planning and Construction (Statewide), Act 485 of 2021

3             for Department of Veterans Affairs, Northwest LA

4             Veterans Cemetery Expansion (Caddo), Act 5 of 2024 for

5             Office of Behavioral Health, Center Building and Fire

6             Alarm System Renovation and Restoration, East

7             Louisiana State Hospital, Planning and Construction (East

8             Feliciana), Act 20 of 2019 for Office of Secretary,

9             Atchafalaya Basin Protection and Enhancement (Federal

10            Match and Local/Sponsor Match) (Assumption,

11            Avoyelles, Iberia, Iberville, Pointe Coupee, St. Landry,

12            St. Martin, St. Mary), Act 465 of 2023 for Louisiana Tech

13            University, Carson-Taylor Hall Renovation, Planning and

14            Construction (Lincoln), Act 2 of 2020 for McNeese State

15            University, ADA Upgrades Campus-Wide, Planning and

16            Construction

17            (Calcasieu)                                                $ 1,467,673

18            Total                                                      $ 31,817,027

19  (578883) Repair, Restoration and Replacement for Declared

20            Disasters, Planning, Construction, Renovation, and

21            Acquisition

22            (Statewide)

23            Payable from General Obligation Bonds

24            Priority 1                                                 $ 58,874,753

25            Priority 5                                                 $ 53,000,000

26            Payable from Federal Funds via Interagency Transfers       $ 70,000,000

27            Total                                                      $ 181,874,753

28  (578884) Outstanding Percent for Arts Projects

29            (Statewide)

30            Payable from General Obligation Bonds

31            Priority 1                                                 $ 5,233,845
                                                                         $ 5,000,000
32            Priority 5                                                 $ 10,233,845

33            Total

34  (578971) Statewide Roofing Asset Management Program and

35            Waterproofing, Related Repairs and Equipment

36            Replacement Program

37            (Statewide)

38            Payable from General Obligation Bonds

39            Priority 5                                                 $ 5,000,000

40            Payable from State General Fund (Direct) Non-Recurring

41            Revenues                                                   $ 4,335,000

42            Total                                                      $ 9,335,000

43  (578975) Deferred Maintenance and Capital Improvements on

44            Public Postsecondary Educational Institutions, Planning

45            and Construction

46            (Statewide)

47            Payable from General Obligation Bonds

48            Priority 5                                                 $ 100,000,000

49            Payable from the balance of State General Funds (Direct)

50            previously allocated under the authority of Act 776 of

51            2024 for the Office of Wildlife, Region 5/Lake Charles

52            Office (Calcasieu), Act 2 of 2025 for Southern University

53            - Baton Rouge, A.O. Williams Hall Renovations,

54            Planning and Construction (East Baton Rouge), Act 2 of

55            2025 for Mcneese State University, Contraband Bayou

56            Erosion Retaining Wall, Phase II, Planning and

57            Construction (Calcasieu), Act 2 of 2025 for University of

                                   Page 9 of 174
    HB NO. 2                                                                ENROLLED

1             Louisiana - Lafayette, Madison Hall Renovation,

2             Planning and Construction (Lafayette), Payable from the

3             balance of State General Fund (Direct) Non-Recurring

4             Revenues from Act 5 of 2024 for Fletcher Technical

5             Community College, Precision Agriculture Training

6             Facility, Planning and Construction

7             (Terrebonne)                                               $ 14,000,000

8             Payable from Interest Earnings                             $ 5,000,000

9             Total                                                      $ 119,000,000

10  01/109 COASTAL PROTECTION AND RESTORATION AUTHORITY

11  (577890) Atchafalaya Basin Protection and Enhancement (Federal

12            Match and Local/Sponsor Match)

13            (Assumption, Avoyelles, Iberia, Iberville, Pointe Coupee,

14            St. Landry, St. Martin, St. Mary)

15            Payable from General Obligation Bonds

16            Priority 1                                                 $ 4,000,000

17            Priority 5                                                 $ 7,000,000

18            Total                                                      $ 11,000,000

19  (577891) Union Diversion Project, Planning and Construction

20            (Ascension, Livingston, St. James, St. John the Baptist)

21            Payable from General Obligation Bonds

22            Priority 1                                                 $ 2,010,212

23            Priority 5                                                 $ 22,350,000

24            Total                                                      $ 24,360,212

25  (577892) Coastal Protection Projects, Planning and Construction

26            (Statewide)

27            Payable from General Obligation Bonds

28            Priority 1                                                 $ 25,500,000

29            Priority 5                                                 $ 197,000,000

30            Payable from State General Fund (Direct) Non-Recurring

31            Revenues                                                   $ 20,000,000

32            Payable from Interagency Transfers                         $ 6,275,000

33            Total                                                      $ 248,775,000

34  (577893) Larose to Golden Meadow Hurricane Protection Project,

35            Planning and Construction

36            (Lafourche)

37            Payable from General Obligation Bonds

38            Priority 5                                                 $ 37,000,000

39  (577909) Morganza to the Gulf of Mexico Hurricane Protection

40            Project

41            (Ascension, Assumption, Iberia, Iberville, Lafourche,

42            Pointe Coupee, St. Martin, St. Mary, Terrebonne,

43            West Baton Rouge)

44            Payable from General Obligation Bonds

45            Priority 5                                                 $ 131,500,000

46  (577910) Eden Isle Flood Risk Reduction and Coastal Resilience

47            Project

48            (St. Tammany)

49            Payable from General Obligation Bonds

50            Priority 1                                                 $  621,766

51            Priority 5                                                 $ 104,000,000

52            Total                                                      $ 104,621,766

                                 Page 10 of 174
    HB NO. 2                                                                    ENROLLED

1   (578397) Construction of the Pumping Capacity Improvements,

2             Phase I Project

3             (Ascension, Assumption, Lafourche, Terrebonne)

4             Payable from General Obligation Bonds

5             Priority 5                                                     $ 11,000,000

6   (578398) Military Road Flood Risk Reduction and Coastal

7             Resilience Project

8             (St. Tammany)

9             Payable from General Obligation Bonds

10            Priority 5                                                     $ 3,000,000

11  (578399) St. Tammany Parish Coastal Storm and Flood Risk

12            Management Project

13            (St. Tammany)

14            Payable from General Obligation Bonds

15            Priority 1                                                     $  207,756

16            Priority 5                                                     $ 4,500,000

17            Total                                                          $ 4,707,756

18  01/112 DEPARTMENT OF MILITARY AFFAIRS

19  (576550) At-Risk Youth Education Center of Excellence - Gillis

20            W. Long Center

21            (Iberville)

22            Payable from General Obligation Bonds

23            Priority 1                                                     $ 1,700,000

24            Priority 5                                                     $ 8,300,000

25            Total                                                          $ 10,000,000

26  (576555) Renovate-Upgrade Cadet Barracks Building 131, 132,

27            and 133, Youth Challenge Program, Camp Minden,

28            Minden, Louisiana

29            (Webster)

30            Payable from General Obligation Bonds

31            Priority 1                                                     $  700,000

32  (576559) Plaquemine Readiness Center Modernization

33            (Iberville)

34            Payable from General Obligation Bonds

35            Priority 1                                                     $  676,000

36  (576560) Renovate-Upgrade Cadet Barracks Buildings 18, 21, 22,

37            23, and 24, Youth Challenge Program (YCP), Carville,

38            Louisiana

39            (Iberville)

40            Payable from General Obligation Bonds

41            Priority 1                                                     $  8,426

42  (576561) Gillis W. Long Center, Water, Fire, and Sewage Line

43            Upgrades, Carville, Louisiana

44            (Iberville)

45            Payable from General Obligation Bonds

46            Priority 1                                                     $  573,605

47  (576563) Statewide Backlog of Maintenance and Repair (BMAR),

48            Phase 3, and Statewide Infrastructure Rehabilitation, Phase 3

49            (Statewide)

50            Payable from General Obligation Bonds

51            Priority 5                                                     $ 40,235,000

                                  Page 11 of 174
    HB NO. 2                                                                ENROLLED

1             Payable from State General Fund (Direct) Non-Recurring

2             Revenues                                                   $ 8,235,000

3             Payable from the balance of general obligation bond

4             proceeds previously allocated under the authority of Act

5             117 of 2022 for the Department of Military Affairs, Camp

6             Minden, Infrastructure, Rehabilitation, Phase 2, Planning

7             and Construction

8             (Webster)                                                  $  4,115

9             Payable from Federal Funds                                 $ 91,000,000

10            Payable from the balance of State

11            General Funds (Direct) previously

12            allocated under the authority of

13            Act 2 of 2025 for the Department

14            of Military Affairs, Coushatta Readiness

15            Center Modernization

16            (Red River)                                                $  735,000

17            Total                                                      $ 140,209,115

18  (576564) Louisiana Military Department Conference Center at

19            Jackson Barracks

20            (Orleans)

21            Payable from the balance of State General Funds (Direct)

22            previously allocated under the authority of Act 2 of 2025

23            for the Department of Military Affairs, Coushatta

24            Readiness

25            Center Modernization (Red River)                           $  500,000

26  (576565) Historical Garrison Preservation - Jackson Barracks

27            (Orleans)

28            Payable from General Obligation Bonds

29            Priority 1                                                 $  950,000

30            Priority 5                                                 $ 2,590,000

31            Total                                                      $ 3,540,000

32  (576567) Louisiana National Guard Readiness Center Complex,

33            Abbeville LA, Planning and Construction

34            (Vermilion)

35            Payable from General Obligation Bonds

36            Priority 1                                                 $ 5,411,041

37  (576568) Multi-Purpose Machine Gun (MPMG) Range -

38            Training Center Pineville

39            (Rapides)

40            Payable from General Obligation Bonds

41            Priority 1                                                 $ 7,875,000

42  (576573) Louisiana National Guard Readiness Center Replacement,

43            Lafayette LA, Planning and Construction

44            (Lafayette)

45            Payable from General Obligation Bonds

46            Priority 1                                                 $ 5,906,956

47            Payable from the balance of State General Funds (Direct)

48            previously allocated under the authority of Act 2 of 2025

49            for the Department of Military Affairs, Coushatta

50            Readiness Center Modernization

51            (Red River)                                                $  765,000

52            Total                                                      $ 6,671,956

                                    Page 12 of 174
    HB NO. 2                                                               ENROLLED

1   (577361) Hammond Readiness Center, Planning and Construction

2             (Tangipahoa)

3             Payable from State General Fund (Direct) Non-Recurring

4             Revenues                                                  $ 10,400,000

5             Payable from Federal Funds                                $ 30,000,000

6             Total                                                     $ 40,400,000

7   (578805) Convert Building 2033 to 122nd Cyber Squadron

8             (Orleans)

9             Payable from Federal Funds                                $ 8,000,000

10  (578885) Louisiana National Guard Training Center Pineville Road

11            Network Rehabilitation

12            (Rapides)

13            Payable from General Obligation Bonds

14            Priority 1                                                $  802,979

15  01/120 OFFICE OF LOUISIANA HIGHWAY CONSTRUCTION

16  (578967) Louisiana Bridge Program

17            (Statewide)

18            Payable from General Obligation Bonds

19            Priority 5                                                $ 40,000,000

20  (578968) Louisiana Highway Road Program

21            (Statewide)

22            Payable from General Obligation Bonds

23            Priority 5                                                $ 158,000,000

24            Payable from the Louisiana Transportation Infrastructure

25            Fund                                                      $ 55,000,000

26            Total                                                     $ 213,000,000

27  Provided, however, that of the funds appropriated herein for the Office of Louisiana

28  Highway Construction, the amount of $25,000,000 from the Louisiana Transportation

29  Infrastructure Fund shall be expended solely on costs associated with the Division of

30  Administration Box Culvert Program.

31  (578969) LA 91: Bayou Plaquemine Brule Bridge Replacement,

32            Planning and Construction

33            (Acadia)

34            Payable from General Obligation Bonds

35            Priority 2                                                $ 1,000,000

36            Priority 5                                                $ 1,000,000

37            Total                                                     $ 2,000,000

38  (578970) Mills Avenue and Champagne Boulevard Extensions

39            (St. Martin)

40            Payable from General Obligation Bonds

41            Priority 5                                                $ 8,000,000

42  (578985) Non-Federal Aid Eligible Highway Program,

43            Planning and Construction

44            (Statewide)

45            Payable from the State Highway Improvement

46            Fund                                                      $ 79,000,000

                            Page 13 of 174
    HB NO. 2                                                                 ENROLLED

1   01/124 LOUISIANA STADIUM AND EXPOSITION DISTRICT

2   (578516) Zephyr Field Improvements, Planning and Construction

3             (Jefferson)

4             Payable from General Obligation Bonds

5             Priority 1                                                  $ 13,676,176

6             Priority 5                                                  $ 1,000,000

7             Total                                                       $ 14,676,176

8   (578886) Bayou Segnette Recreation Complex, Land Acquisition,

9             Planning and Construction

10            (Jefferson)

11            Payable from General Obligation Bonds

12            Priority 1                                                  $  198,688

13            Priority 5                                                  $ 9,000,000

14            Total                                                       $ 9,198,688

15                      DEPARTMENT OF VETERANS AFFAIRS

16  03/130 DEPARTMENT OF VETERANS AFFAIRS

17  (578732) Northeast Louisiana Veterans Cemetery - In-Ground

18            Cremation and Above-Ground Cremation Spaces, Planning

19            and Construction

20            (Richland)

21            Payable from Federal Funds                                  $ 1,500,000

22  03/135 NORTHWEST LOUISIANA WAR VETERANS HOME

23  (578510) Roof Replacement, Planning and Construction

24            (Richland)

25            Payable from Federal Funds via Interagency Transfers        $  570,000

26                                ELECTED OFFICIALS

27  04/139 SECRETARY OF STATE

28  (578786) Old State Capitol Exterior Repairs, Planning and

29            Construction

30            (East Baton Rouge)

31            Payable from General Obligation Bonds

32            Priority 1                                                  $ 5,992,420
                                                                          $ 5,200,000
33            Priority 5                                                  $ 11,192,420

34            Total

35                   LOUISIANA ECONOMIC DEVELOPMENT

36  05/250 OFFICE OF ECONOMIC DEVELOPMENT

37  (577235) Donaldsonville Training Facility, Planning and Construction

38            (Ascension)

39            Payable from General Obligation Bonds

40            Priority 5                                                  $ 5,600,000

41            Payable from State General Fund (Direct) Non-Recurring

42            Revenues                                                    $ 16,000,000

43            Total                                                       $ 21,600,000

                                  Page 14 of 174
    HB NO. 2                                                               ENROLLED

1   (577561) Economic Development Award Program for Infrastructure

2             Assistance

3             (Statewide)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $ 5,000,000

6   (577606) NIRC BSL-3 Lab and Animal Housing, Planning and

7             Construction

8             (Iberia)

9             Payable from General Obligation Bonds

10            Priority 1                                                 $ 20,600,000

11  (577607) NIRC Iberia BioInnovation Accelerator GMP CDMO

12            Planning and Construction

13            (Iberia)

14            Payable from General Obligation Bonds

15            Priority 1                                                 $ 8,000,000

16            Priority 5                                                 $ 45,400,000

17            Total                                                      $ 53,400,000

18  (577612) LA 1 Overpass Rail Improvements Phase 4

19            (Ascension)

20            Payable from General Obligation Bonds

21            Priority 5                                                 $ 132,520,250

22  (577614) ETP Parkway Road Project within the RiverPlex MegaPark

23            Phases 1 and 3

24            (Ascension)

25            Payable from General Obligation Bonds

26            Priority 5                                                 $ 31,162,500

27            Payable from State General Fund (Direct) Non-Recurring

28            Revenues                                                   $ 6,650,000

29            Payable from the Louisiana Economic Development

30            Initiatives Fund previously allocated under the authority

31            of Act 2 of 2025 for the Office of Economic Development,

32            Energy Transition Parkway, Phase II and Extension,

33            Planning and Construction

34            (Ascension)                                                $ 7,750,000

35            Total                                                      $ 45,562,500

36  ()        Louisiana Economic Development Capital Projects,

37            Planning and Construction

38            (Statewide)

39            Payable from General Obligation Bonds

40            Priority 5                                                 $ 169,282,750

41  Provided, however, that the funds appropriated herein shall be expended solely on the

42  following projects:

43  Donaldsonville Training Facility, Planning and Construction

44  LA 1 Overpass Rail Improvements Phase 4

45  ETP Parkway Road Project within the Riverplex Megapark Phases 1 and 3

46  Energy Transition Parkway, Phase II and Extension, Planning and Construction

47  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

48  Joint Legislative Committee on the Budget, the secretary of Louisiana Economic

49  Development is authorized to combine the specific projects listed within this appropriation

50  into the single project entitled Louisiana Economic Development Capital Projects.

51  Furthermore, all appropriations for the specific projects combined into the single project

52  entitled Louisiana Economic Development Capital Projects, including cash appropriations,

53  appropriations of fees and self-generated revenues, interagency transfers, statutory

                              Page 15 of 174
    HB NO. 2                                                               ENROLLED

1   dedications, general obligation bond appropriations, and appropriations from any other

2   means of finance, contained in this Act and any prior Capital Outlay Act, and all previously

3   approved cash and noncash lines of credit approved by the State Bond Commission for the

4   specific projects included within this appropriation shall transfer to and be included within

5   the Louisiana Economic Development Capital Projects appropriation when the projects are

6   combined by the secretary of Louisiana Economic Development.

7   DEPARTMENT OF CULTURE, RECREATION AND TOURISM

8   06/263 OFFICE OF STATE MUSEUM

9   (577180) Madame Johns Legacy Restoration ADA and Safety

10            Upgrades/Fire Suppression, Planning and Construction

11            (Orleans)

12            Payable from General Obligation Bonds

13            Priority 5                                                $ 3,275,000

14            Payable from State General Fund (Direct) Non-Recurring

15            Revenues                                                  $    325,000

16            Total                                                     $ 3,600,000

17  (577500) New Orleans Jazz Museum - Old U.S. Mint Emergency

18            Waterproofing, Structural Repair, Renovations, and Other

19            Development

20            (Orleans)

21            Payable from General Obligation Bonds

22            Priority 5                                                $ 23,000,000

23            Payable from State General Fund (Direct) Non-Recurring

24            Revenues                                                  $    225,000

25            Total                                                     $ 23,225,000

26  (578887) Construction of Civil Rights Museum, Planning and Construction

27            (Orleans)

28            Payable from General Obligation Bonds

29            Priority 1                                                $    48,992

30            Priority 5                                                $ 25,000,000

31            Total                                                     $ 25,048,992

32  06/264 OFFICE OF STATE PARKS

33  (577176) Bogue Chitto State Park - Trail Design, Construction,

34            Acquisition and Other Development

35            (Washington)

36            Payable from General Obligation Bonds

37            Priority 1                                                $ 3,000,000

38            Priority 5                                                $ 1,500,000

39            Total                                                     $ 4,500,000

40  (577177) Poverty Point State Historic Site - Land Acquisition,

41            Design, Museum/Interpretive Center and Expansion

42            (West Carroll)

43            Payable from General Obligation Bonds

44            Priority 1                                                $ 6,160,587
                                                                        $ 17,500,000
45            Priority 5                                                $ 23,660,587

46            Total

                              Page 16 of 174
    HB NO. 2                                                               ENROLLED

1   (577178) Tunica Hills State Preservation Area, Construction,

2             Development and Acquisition

3             (West Feliciana)

4             Payable from General Obligation Bonds

5             Priority 1                                                $ 4,500,000
                                                                        $ 15,500,000
6             Priority 5                                                $ 20,000,000

7             Total

8   (577179) Preventive Maintenance/Major Repairs and Improvements

9             (Statewide)

10            Payable from General Obligation Bonds

11            Priority 1                                                $ 3,457,963

12            Priority 5                                                $ 1,339,649

13            Payable from State General Fund (Direct) Non-Recurring

14            Revenues                                                  $ 4,339,649

15            Payable from Interagency Transfers                        $ 20,000,000

16            Total                                                     $ 29,137,261

17  (578889) Bogue Chitto State Park Emergency Erosion, Planning,

18            Design, Construction and Other Development

19            (Washington)

20            Payable from General Obligation Bonds

21            Priority 5                                                $ 1,200,000

22            Payable from State General Fund (Direct) Non-Recurring

23            Revenues                                                  $  840,013

24            Total                                                     $ 2,040,013

25  (578890) Bayou Segnette State Park, Land Acquisition, Additional

26            Cabins, Planning and Construction

27            (Jefferson)

28            Payable from General Obligation Bonds

29            Priority 1                                                $  2,198

30  06/A20 NEW ORLEANS CITY PARK

31  (577337) City Park Practice Track, Design, Renovation, and

32            Enhancements

33            (Orleans)

34            Payable from State General Fund (Direct) Non-Recurring

35            Revenues                                                  $ 3,400,000

36  (577338) Bayou Oaks Driving Range Planning, Design, and

37            Construction

38            (Orleans)

39            Payable from the Capital Outlay Savings Fund              $ 3,100,000

40  (577343) Repairs to Historic Structures, Planning and Construction

41            (Orleans)

42            Payable from General Obligation Bonds

43            Priority 1                                                $ 2,089,307

44  06/A98 LOUISIANA NAVAL WAR MEMORIAL COMMISSION

45  (577174) USS KIDD Veterans Museum Ship/Cradle and

46            Building/Campus/Memorial Repair & Renovation,

47            HVAC Replacement, Education Classroom, Security,

48            Artifact Restoration Equipment, Parking Expansion,

49            Planning and Construction

50            (East Baton Rouge)

                                  Page 17 of 174
    HB NO. 2                                                              ENROLLED

1             Payable from General Obligation Bonds

2             Priority 5                                               $ 1,200,000

3             Payable from State General Fund (Direct) Non-Recurring

4             Revenues                                                 $  125,000

5             Total                                                    $ 1,325,000

6                    DEPARTMENT OF TRANSPORTATION AND

7                                   DEVELOPMENT

8   07/270 ADMINISTRATION

9   (576769) Jimmie Davis Bridge Rehabilitation and Lighting, or

10            Design, Engineering, Planning and Construction

11            (Bossier)

12            Payable from General Obligation Bonds

13            Priority 1                                               $ 56,364,853

14            Priority 5                                               $ 36,000,000

15            Payable from State General Fund (Direct) Non-Recurring

16            Revenues                                                 $ 50,000,000

17            Total                                                    $ 142,364,853

18  (576770) LA 1 Improvements, Phase 2, Planning, Engineering,

19            Right-of-Way, Utilities and Construction

20            (Lafourche)

21            Payable from General Obligation Bonds

22            Priority 1                                               $ 46,905,593

23            Payable from State General Fund (Direct) Non-Recurring

24            Revenues                                                 $ 28,000,000

25            Total                                                    $ 74,905,593

26  (576771) LA 3241 (I-12 to Bush), Planning, Engineering,

27            Right-of-Way, Utilities and Construction

28            (St. Tammany)

29            Payable from General Obligation Bonds

30            Priority 5                                               $ 28,000,000

31  (576772) I-10 Calcasieu River Bridge, Environmental, Planning,

32            Engineering, Right-of-Way, Utilities, Demolition and

33            Construction

34            (Calcasieu)

35            Payable from General Obligation Bonds

36            Priority 1                                               $ 49,385,563

37            Priority 5                                               $ 50,000,000

38            Total                                                    $ 99,385,563

39  (576776) LA 964 (Groom Road - US 61) Highway Lighting

40            (East Baton Rouge)

41            Payable from General Obligation Bonds

42            Priority 1                                               $  450,000

43            Priority 5                                               $ 2,400,000

44            Total                                                    $ 2,850,000

45  (576777) Loyola/I-10 Interchange Improvements, Feasibility Study,

46            Interchange Modification Report, Environmental

47            Assessment, Engineering, Right-of-Ways, Utilities and

48            Construction

49            (Jefferson, Orleans)

50            Payable from General Obligation Bonds

51            Priority 1                                               $ 1,350,548

                                    Page 18 of 174
    HB NO. 2                                                             ENROLLED

1   (576778) Improvements on LA 3038, Including Patching,

2             Repairing and Overlaying of the Highway, Planning

3             and Construction

4             (Ascension)

5             Payable from General Obligation Bonds

6             Priority 1                                              $  47,139

7   (576779) Florida Avenue Bridge, Planning and Construction

8             (Orleans)

9             Payable from General Obligation Bonds

10            Priority 5                                              $ 7,200,000

11  (576780) Claiborne Corridor Rehabilitation

12            (Orleans)

13            Payable from General Obligation Bonds

14            Priority 5                                              $ 20,000,000

15  (576781) Pecue Lane/I-10 Interchange and I-10, Planning, Design,

16            Rights-of-Way, Utilities and Construction

17            (East Baton Rouge)

18            Payable from General Obligation Bonds

19            Priority 1                                              $ 1,355,887

20  (576789) LA 335: LA 35 - LA 14, Planning and Construction

21            (Vermilion)

22            Payable from General Obligation Bonds

23            Priority 2                                              $ 7,500,000
                                                                      $ 17,100,000
24            Priority 5                                              $ 24,600,000

25            Total

26  (576790) LA 35: Lafayette Parish Line - US 90

27            (Acadia)

28            Payable from General Obligation Bonds

29            Priority 2                                              $ 6,800,000
                                                                      $ 7,300,000
30            Priority 5                                              $ 14,100,000

31            Total

32  (576791) LA 29 Improvements (LA 13 - LA 758)

33            (Evangeline, St. Landry)

34            Payable from General Obligation Bonds

35            Priority 1                                              $ 5,009,987

36  (576792) LA 86: LA 320 - LA 3242, Planning and Construction

37            (Iberia)

38            Payable from General Obligation Bonds

39            Priority 1                                              $ 1,500,000

40            Priority 5                                              $ 7,200,000

41            Total                                                   $ 8,700,000

42  (576793) LA 117: Improvements from LA 8 to LA 118

43            (Natchitoches, Vernon)

44            Payable from General Obligation Bonds

45            Priority 1                                              $ 5,904,380

46            Priority 5                                              $ 13,500,000

47            Payable from State General Fund (Direct) Non-Recurring

48            Revenues                                                $ 16,500,000

49            Total                                                   $ 35,904,380

                                  Page 19 of 174
    HB NO. 2                                                              ENROLLED

1   (576794) Highway 397 in Calcasieu Parish, North and South Turning

2             Lanes

3             (Calcasieu)

4             Payable from General Obligation Bonds

5             Priority 1                                               $ 1,980,430

6             Priority 5                                               $ 3,800,000

7             Total                                                    $ 5,780,430

8   (576795) City of Gonzales - GO Program LA Highway 30 Corridor,

9             Planning and Construction

10            (Ascension)

11            Payable from General Obligation Bonds

12            Priority 1                                               $ 5,655,302

13            Priority 5                                               $ 2,500,000

14            Total                                                    $ 8,155,302

15  (576796) LA 156: LA 479 - LA 501, Planning and Construction

16            (Natchitoches, Winn)

17            Payable from General Obligation Bonds

18            Priority 5                                               $ 8,000,000

19  (576797) LA 182 Resurfacing

20            (St. Mary)

21            Payable from General Obligation Bonds

22            Priority 5                                               $ 8,000,000

23  (576809) LA 70 Resurfacing and Drainage Repairs

24            (St. Mary)

25            Payable from General Obligation Bonds

26            Priority 5                                               $ 6,460,000

27  (576810) US 190 (Vine Street) Reconstruction

28            (St. Landry)

29            Payable from General Obligation Bonds

30            Priority 1                                               $  182,710

31            Priority 5                                               $ 19,200,000

32            Total                                                    $ 19,382,710

33  (576811) Roundabout on LA 447 and LA 1025, Planning and

34            Construction

35            (Livingston)

36            Payable from General Obligation Bonds

37            Priority 1                                               $  35,205

38            Priority 2                                               $ 3,000,000

39            Priority 5                                               $ 5,000,000

40            Total                                                    $ 8,035,205

41  (576812) Roundabout at Intersection of LA 3125 and LA 3274

42            (St. James)

43            Payable from General Obligation Bonds

44            Priority 1                                               $ 1,999,807
                                                                       $ 4,400,000
45            Priority 5                                               $ 6,399,807

46            Total

47  (576813) LA 92: LA 91 - LA 13

48            (Acadia)

49            Payable from General Obligation Bonds

50            Priority 5                                               $ 15,100,000

                                    Page 20 of 174
    HB NO. 2                                                             ENROLLED

1   (576814) LA 28 Widening (LA 3128 - LA 116)

2             (Rapides)

3             Payable from General Obligation Bonds

4             Priority 1                                              $  204,706

5             Priority 5                                              $ 40,000,000

6             Total                                                   $ 40,204,706

7   (576815) Widening of Highway 447 and I-12 Overpass

8             Improvements, Environmental Phase Commencement,

9             Planning and Construction

10            (Livingston)

11            Payable from General Obligation Bonds

12            Priority 1                                              $ 3,739,209

13            Priority 5                                              $ 28,152,600

14            Payable from State General Fund (Direct) Non-Recurring

15            Revenues                                                $ 6,000,000

16            Total                                                   $ 37,891,809

17  (576820) LA 14: Zwan Road - LA 91

18            (Vermilion)

19            Payable from General Obligation Bonds

20            Priority 1                                              $ 9,000,000

21  (576821) LA 384 (Big Lake Rd. to McNeese St.), Planning and

22            Construction

23            (Calcasieu)

24            Payable from General Obligation Bonds

25            Priority 5                                              $ 10,000,000

26  (576822) LA 29:US 167-LA 182, Planning and Construction

27            (Evangeline, St. Landry)

28            Payable from General Obligation Bonds

29            Priority 2                                              $ 15,400,000
                                                                      $ 15,400,000
30            Priority 5                                              $ 30,800,000

31            Total

32  (576823) LA 363: St. Landry Parish Line - LA 1169, Planning and

33            Construction

34            (Evangeline)

35            Payable from General Obligation Bonds

36            Priority 2                                              $ 2,000,000

37            Priority 5                                              $ 5,300,000

38            Total                                                   $ 7,300,000

39  (576824) LA 621 Realignment and Other LA 73 Corridor

40            Improvements, Planning and Construction

41            (Ascension)

42            Payable from General Obligation Bonds

43            Priority 1                                              $ 3,797,761
                                                                      $ 8,100,000
44            Priority 5                                              $ 11,897,761

45            Total

46  (576826) US 190 Widening: LA 25 - US 190 Bus

47            (St. Tammany)

48            Payable from General Obligation Bonds

49            Priority 1                                              $ 2,000,000
                                                                      $ 3,100,000
50            Priority 5                                              $ 5,100,000

51            Total

                             Page 21 of 174
    HB NO. 2                                                             ENROLLED

1   (576827) LA 22: North Hoover Road - Dunson Road

2             (Tangipahoa)

3             Payable from General Obligation Bonds

4             Priority 5                                              $ 12,600,000

5   (576829) Roundabout at LA 3211 and Yokley Road

6             (St. Mary)

7             Payable from General Obligation Bonds

8             Priority 1                                              $ 3,500,000
                                                                      $ 3,800,000
9             Priority 5                                              $ 7,300,000

10            Total

11  (576830) LA 31: LA 341 - LA 355, Planning and Construction

12            (St. Martin)

13            Payable from General Obligation Bonds

14            Priority 5                                              $ 6,000,000

15  (576831) LA 330: LA 82 - Old LA 690, Planning and Construction

16            (Vermilion)

17            Payable from General Obligation Bonds

18            Priority 5                                              $ 10,400,000

19            Payable from State General Fund (Direct) Non-Recurring

20            Revenues                                                $  500,000

21            Payable from State General Fund (Direct)                $  300,000

22            Total                                                   $ 11,200,000

23  (576832) LA 13: Court Circle - Sherwood Lane, Planning and

24            Construction

25            (Acadia)

26            Payable from General Obligation Bonds

27            Priority 5                                              $ 14,750,000

28  (576833) US 90 in Acadia Parish, Planning and Construction

29            (Acadia)

30            Payable from General Obligation Bonds

31            Priority 5                                              $ 6,350,000

32  (576834) LA 182/LA 92-1 Intersection Improvements, Planning and

33            Construction

34            (St. Martin)

35            Payable from General Obligation Bonds

36            Priority 2                                              $ 1,000,000

37            Priority 5                                              $ 5,400,000

38            Total                                                   $ 6,400,000

39  (576835) LA 182/LA 88 Intersection Improvements, Planning

40            and Construction

41            (Iberia)

42            Payable from General Obligation Bonds

43            Priority 2                                              $ 1,000,000
                                                                      $ 8,800,000
44            Priority 5                                              $ 9,800,000

45            Total

46  (576836) US 167 J-Turns, Planning and Construction

47            (Vermilion)

48            Payable from General Obligation Bonds

49            Priority 2                                              $ 1,250,000
                                                                      $ 1,250,000
50            Priority 5                                              $ 2,500,000

51            Total

                                Page 22 of 174
    HB NO. 2                                                               ENROLLED

1   (576839) LA 3127: St. James Canal Bridge - LA 20, Planning

2             and Construction

3             (St. James)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 17,220,000

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                  $  400,000

8             Total                                                     $ 17,620,000

9   (576844) US 90: Lafayette Regional Airport - Assumption Parish

10            Line, Planning and Construction

11            (Iberia, Lafayette, St. Martin, St. Mary)

12            Payable from General Obligation Bonds

13            Priority 5                                                $ 40,000,000

14  (576845) LA 409 (Liberty Road): LA 64 - East Feliciana Parish Line

15            Planning and Construction

16            (East Baton Rouge)

17            Payable from General Obligation Bonds

18            Priority 1                                                $ 1,000,000

19  (576846) LA 74/I-10 Interchange, Planning and Construction

20            (Ascension)

21            Payable from General Obligation Bonds

22            Priority 5                                                $ 5,000,000

23  (576847) LA 347: LA 351 - LA 328

24            (St. Martin)

25            Payable from General Obligation Bonds

26            Priority 5                                                $ 2,000,000

27  (576850) Relocate Hickory Avenue (LA Hwy. 48-11th Street)

28            (Mounes) (LA Hwy. 3154) Construction, Right of Way,

29            and Utilities

30            (Jefferson)

31            Payable from General Obligation Bonds

32            Priority 1                                                $ 1,000,000

33            Priority 5                                                $ 1,000,000

34            Total                                                     $ 2,000,000

35  (576851) LA 699: LA 35 - LA 343, Planning and Construction

36            (Vermilion)

37            Payable from General Obligation Bonds

38            Priority 1                                                $ 2,929,357

39  (576852) Intersection Improvements (Roundabouts), Planning and

40            Construction

41            (Lafayette)

42            Payable from General Obligation Bonds

43            Priority 1                                                $ 5,000,000

44            Priority 5                                                $ 5,000,000

45            Total                                                     $ 10,000,000

46  (576853) Hooper Road Extension and Widening, Environmental,

47            Planning, Engineering, Right-of-Way, Utilities and

48            Construction

49            (East Baton Rouge, Livingston)

50            Payable from General Obligation Bonds

51            Priority 1                                                $ 7,597,091

52            Priority 5                                                $ 27,000,000

53            Total                                                     $ 34,597,091

                                  Page 23 of 174
    HB NO. 2                                                             ENROLLED

1   (576855) LA 31: LA 182 - 0.15 Mi N of N LA 96

2             (Iberia, St. Martin)

3             Payable from General Obligation Bonds

4             Priority 1                                              $ 6,694,539

5   (576857) LA 343 (Bosco Hwy) LA 98 - LA 356, Planning and

6             Construction

7             (St. Landry)

8             Payable from General Obligation Bonds

9             Priority 1                                              $ 6,229,762

10  (576858) LA 3211: Yokley Road to LA 182, Planning and

11            Construction

12            (St. Mary)

13            Payable from General Obligation Bonds

14            Priority 5                                              $ 15,000,000

15  (576859) LA 44 Widening, I-10 to LA 22, Planning, Utilities,

16            Right-of-Way and Construction

17            (Ascension)

18            Payable from General Obligation Bonds

19            Priority 1                                              $ 7,544,409
                                                                      $ 17,000,000
20            Priority 5                                              $ 24,544,409

21            Total

22  (576860) LA 42 (US 61 to LA 44) Widening, including a Roundabout

23            at Joe Sevario Road, Planning and Construction

24            (Ascension)

25            Payable from General Obligation Bonds

26            Priority 1                                              $  173,885

27  (576861) I-49 South from Lafayette to Westbank Expressway,

28            Planning, Engineering, Right-of-Way, Utilities and

29            Construction

30            (Iberia, Jefferson, Lafayette, Lafourche, St. Charles,

31            St. Martin, St. Mary, Terrebonne)

32            Payable from General Obligation Bonds

33            Priority 1                                              $  64,981

34            Priority 5                                              $ 188,000,000

35            Total                                                   $ 188,064,981

36  (576862) LA 91: Bayou Plaquemine Brule Bridge Replacement,

37            Planning and Construction

38            (Acadia)

39            Payable from General Obligation Bonds

40            Priority 1                                              $ 1,000,000

41            Priority 5                                              $ 5,200,000

42            Total                                                   $ 6,200,000

43  (576863) Louisiana Highway 64 and Louisiana Highway 1019

44            Roundabout, Planning and Construction

45            (Livingston)

46            Payable from General Obligation Bonds

47            Priority 1                                              $  175,000

48            Priority 5                                              $ 2,000,000

49            Total                                                   $ 2,175,000

                                    Page 24 of 174
    HB NO. 2                                                              ENROLLED

1   (576864) Roundabout at LA 3233 and I-49 Northbound Service

2             Road, Planning and Construction

3             (St. Landry)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 9,600,000

6   (576865) LA 429/I-10 Interchange, Planning and Construction

7             (Ascension)

8             Payable from General Obligation Bonds

9             Priority 5                                              $ 5,000,000

10  (576866) Peters Road Bridge and Extension, Planning and Construction

11            (Jefferson, Plaquemines)

12            Payable from General Obligation Bonds

13            Priority 1                                              $ 16,957,402

14            Payable from State General Fund (Direct) Non-Recurring

15            Revenues                                                $ 7,000,000

16            Total                                                   $ 23,957,402

17  (576867) Earhart/Causeway Interchange, Planning, Engineering,

18            Right-of-Way, Utilities and Construction

19            (Jefferson)

20            Payable from General Obligation Bonds

21            Priority 1                                              $ 4,731,751

22            Priority 5                                              $ 48,800,000

23            Total                                                   $ 53,531,751

24  (576869) Livingston Roundabout at Corner of LA 16 and LA 42,

25            Planning and Construction

26            (Livingston)

27            Payable from General Obligation Bonds

28            Priority 5                                              $ 3,600,000

29  (576870) LA 22 Extension and Improvements, LA 22 Roundabout,

30            Design, Engineering, Planning and Construction

31            (St. Tammany)

32            Payable from General Obligation Bonds

33            Priority 1                                              $   614,570

34            Priority 5                                              $ 3,240,000

35            Total                                                   $ 3,854,570

36  (576871) LA 3034 Improvements

37            (East Baton Rouge)

38            Payable from General Obligation Bonds

39            Priority 1                                              $ 10,538,487
                                                                      $ 22,000,000
40            Priority 5                                              $ 32,538,487

41            Total

42  (576872) New Mississippi River Bridge

43            (Ascension, East Baton Rouge, Iberville, St. James,

44            West Baton Rouge)

45            Payable from General Obligation Bonds

46            Priority 1                                              $   538,082

47            Priority 5                                              $ 3,000,000

48            Total                                                   $ 3,538,082

49  (576873) Verot School Road, State Hwy. 339 Widening, Planning

50            and Construction

51            (Lafayette)

52            Payable from General Obligation Bonds

53            Priority 5                                              $ 60,500,000

                                  Page 25 of 174
    HB NO. 2                                                                 ENROLLED

1   (576874) Hooper Road Widening and Sewer Improvements

2             (Blackwater Bayou to Sullivan Road) Planning,

3             Engineering, Utilities and Construction

4             (East Baton Rouge)

5             Payable from General Obligation Bonds

6             Priority 1                                                  $ 11,057,818
                                                                          $ 5,000,000
7             Priority 5                                                  $ 16,057,818

8             Total

9   (576875) US 371 Widening

10            (Webster)

11            Payable from General Obligation Bonds

12            Priority 5                                                  $ 3,600,000

13  (576876) Interchange Improvements on La. Highways (current or

14            former) in Lafayette Parish, Planning and Construction

15            (Lafayette)

16            Payable from General Obligation Bonds

17            Priority 5                                                  $ 15,000,000

18  (576877) New Orleans International Airport Landside Access

19            Improvements

20            (Jefferson)

21            Payable from General Obligation Bonds

22            Priority 1                                                  $ 5,892,521

23  (577318) LA 3227 - LA 157 Intersection Realignment, Planning and

24            Construction

25            (Bossier)

26            Payable from General Obligation Bonds

27            Priority 1                                                  $  12,287

28  (577415) Highway Program (Up to $4,000,000 for Secretary's

29            Emergency Fund)

30            (Statewide)

31            Payable from General Obligation Bonds

32            Priority 1                                                  $ 53,404,621

33            Priority 2                                                  $ 56,450,000

34            Priority 5                                                  $ 374,850,000

35            Payable from the balance of general obligation bond

36            proceeds previously allocated under the authority of Act

37            485 of 2021 for Department of Transportation and

38            Development - Administration, LA 182 Overlay (LA

39            3069 - LA 317) (St. Mary), Act 117 of 2022 for

40            Department of Transportation and Development -

41            Administration, LA 35 Overlay (LA 98 - LA 365)

42            (Acadia)                                                    $  839,253

43            Payable from the balance of State General Funds (Direct)

44            previously allocated under the authority of Act 73 of 1998

45            for Department of Transportation and Development -

46            Administration, State Parks Road Overlay, Construction

47            (Statewide), Act 23 of 2002 for Department of

48            Transportation and Development - Administration, Ridge

49            Road (LA 342) at West Broussard Road, Turn Lane,

50            Planning and Construction (Lafayette), Act 27 of 2006 for

51            Department of Transportation and Development -

52            Administration, LA Hwy. 6 Turn Lanes in Many at Many

53            Jr. and Sr. High Schools, Planning and Construction

54            (Sabine), Act 28 of 2007 for Department of

55            Transportation and Development - Administration, Turn

                                  Page 26 of 174
    HB NO. 2                                                            ENROLLED

1             Lane on LA Hwy. 171 in front of Mount Bethal Church

2             in Keithville, Planning and Construction (Caddo), Act

3             511 of 2008 for Department of Transportation and

4             Development - Administration, Bridge Replacement at

5             La. Hwy. 77 and La. Hwy. 78/411 (Pointe Coupee), Act

6             511 of 2008 for Department of Transportation and

7             Development - Administration, Leesville Route 171

8             Study (Vernon), Act 28 of 1997 for Evangeline Parish,

9             LA 29 and US 167, Improvements, Engineering,

10            Construction, Right of Way and Utilities (Evangeline),

11            Act 28 of 1997 for Jefferson Parish, Barataria Blvd.

12            Drainage Improvements Barataria Blvd./Patriot Street To

13            Ames Blvd. (Jefferson), Act 29 of 1998 for Jefferson

14            Parish, Lead Street Access, Planning and Construction

15            (Jefferson), Act 45 of 1996 for Lafourche Parish,

16            Thibodaux-Raceland-Savoie Flood Protection

17            (Lafourche), Act 26 of 2005 for Sabine Parish, Blue Lake

18            Road Improvements /North Toledo Bend State Park Road

19            (LA 3229 to North Toledo Bend State Park), Planning

20            and Construction (Sabine), Act 45 of 1996 for St. Mary

21            Parish, Sewer Improvements and Repairs at Kemper-

22            Williams Park (St. Mary), Act 479 of 1997 for Vidalia,

23            Comprehensive Traffic Improvements For Industrial Park

24            Areas, Planning and Construction

25            (Concordia)                                               $ 1,889,243

26            Payable from Transportation Trust Fund - Construction

27            Subfund                                                   $ 4,300,000

28            Payable from Transportation Trust Fund - Regular          $ 20,400,000

29            Payable from Transportation Trust Fund - Federal

30            Receipts                                                  $ 1,500,000,000

31            Payable from State General Fund (Direct) Non-Recurring

32            Revenues                                                  $ 8,115,000

33            Payable from Federal Funds                                $ 25,000,000

34            Payable from the Louisiana Transportation Infrastructure

35            Fund                                                      $ 260,000,000

36            Total                                                     $ 2,305,248,117

37  Provided, however, that the funds appropriated herein for the Highway Program, the amount

38  of $35,000,000 from the Louisiana Transportation Infrastructure Fund shall be expended

39  solely on costs associated with Box Culverts.

40  (577692) LA 1/LA 415 Connector

41            (West Baton Rouge)

42            Payable from General Obligation Bonds

43            Priority 5                                                $ 50,000,000

44            Payable from the balance of State General Funds (Direct)

45            previously allocated under the authority of Act 20 of

46            2009 for West Baton Rouge Parish, LA 415 Bridge at

47            Intracoastal Canal, Planning and Construction

48            (West Baton Rouge)                                        $ 1,610,990

49            Total                                                     $ 51,610,990

50  (577736) LA 3127: LA 70 - St. James Canal Bridge

51            (Ascension, St. James)

52            Payable from General Obligation Bonds

53            Priority 2                                                $ 9,500,000
                                                                        $ 6,000,000
54            Priority 5                                                $ 15,500,000

55            Total

                                  Page 27 of 174
    HB NO. 2                                                             ENROLLED

1   (577739) LA 641: LA 44-LA 3125

2             (St. James)

3             Payable from General Obligation Bonds

4             Priority 5                                              $ 5,000,000

5             Payable from State General Fund (Direct) Non-Recurring

6             Revenues                                                $  400,000

7             Total                                                   $ 5,400,000

8   (578083) Secretary's Emergency Fund for Bridge Damages, Other

9             Reimbursements, Local Matching Dollars, Federal Funds,

10            and Opportunity Grants Subject to the Provisions of

11            R.S. 48:232

12            (Statewide)

13            Payable from Interagency Transfers                      $ 25,000,000

14            Payable from Fees and Self-Generated Revenues           $ 45,000,000

15            Payable from Transportation Trust Fund - Federal

16            Receipts                                                $ 25,000,000

17            Payable from Federal Funds                              $ 2,500,000

18            Total                                                   $ 97,500,000

19  (578119) I-49 N: Inner City Connector

20            (Caddo)

21            Payable from General Obligation Bonds

22            Priority 5                                              $ 50,000,000
                                                                      $ 20,000,000
23            Payable from Megaproject Leverage Fund                  $ 70,000,000

24            Total

25  (578724) LA 45 Roadway Raising

26            (Jefferson)

27            Payable from General Obligation Bonds

28            Priority 5                                              $ 3,000,000

29  (578777) US 165: Roundabout at Pinecrest

30            (Rapides)

31            Payable from General Obligation Bonds

32            Priority 5                                              $ 12,500,000

33            Payable from State General Fund (Direct) Non-Recurring

34            Revenues                                                $ 5,500,000

35            Total                                                   $ 18,000,000

36  (578784) LA 13 (Crowley to Vermilion Parish Line)

37            (Acadia)

38            Payable from General Obligation Bonds

39            Priority 1                                              $  28,516

40  (578997) LA 8: Richard Thompson Bridge to Colfax,

41            Planning and Construction

42            (Grant, Rapides)

43            Payable from General Obligation Bonds

44            Priority 5                                              $ 18,000,000

45  (579010) LA10: LA 106- LA 13

46            (Evangeline)

47            Payable from General Obligation Bonds

48            Priority 5                                              $ 19,000,000

49            Payable from the Capital Outlay Savings Fund            $  500,000

50            Total                                                   $ 19,500,000

                                Page 28 of 174
    HB NO. 2                                                                 ENROLLED

1   07/274 PUBLIC IMPROVEMENTS

2   (576766) Mississippi River Deepening, Phase 3, Planning, Design,

3             Construction, Rights-of-Way, Relocations and Utilities

4             (Ascension, East Baton Rouge, Jefferson, Orleans,

5             Plaquemines, St. Bernard, St. Charles, St. James, St. John

6             the Baptist, West Baton Rouge)

7             Payable from General Obligation Bonds

8             Priority 1                                                  $ 55,500,000

9             Priority 5                                                  $ 25,000,000

10            Total                                                       $ 80,500,000

11  (576767) Houma Navigational Canal Deepening Project, Planning,

12            Design, Construction, Rights-of-Ways, Relocations and

13            Utilities

14            (Terrebonne)

15            Payable from General Obligation Bonds

16            Priority 1                                                  $ 9,650,000

17            Priority 5                                                  $ 37,150,000

18            Total                                                       $ 46,800,000

19  (576768) Acadiana Gulf of Mexico Access Channel (AGMAC),

20            Port of Iberia, Planning, Design, Construction,

21            Rights-of-Way, Relocations and Utilities

22            (Iberia, Vermilion)

23            Payable from General Obligation Bonds

24            Priority 1                                                  $ 2,840,987

25  (576773) J. Bennett Johnston (Red River) Deepening

26            (Avoyelles, Bossier, Caddo, Grant, Natchitoches, Rapides,

27            Red River)

28            Payable from General Obligation Bonds

29            Priority 1                                                  $  400,000

30  (576816) Bayou Dechene Reservoir, Planning, Land Acquisition

31            and Construction

32            (Caldwell)

33            Payable from General Obligation Bonds

34            Priority 1                                                  $ 2,885,096

35            Priority 5                                                  $ 18,300,000

36            Total                                                       $ 21,185,096

37  (576817) Ouachita River and Tributaries Bank Stabilization and

38            Levee Repairs

39            (Caldwell, Catahoula, Franklin, LaSalle, Ouachita)

40            Payable from General Obligation Bonds

41            Priority 1                                                  $ 2,742,599

42            Priority 5                                                  $ 14,650,000

43            Total                                                       $ 17,392,599

44  (576818) West of Atchafalaya Basin Feasibility Study

45            (Statewide)

46            Payable from General Obligation Bonds

47            Priority 5                                                  $  750,000

48  (576819) Short Line Railroad Upgrades

49            (Statewide)

50            Payable from General Obligation Bonds

51            Priority 1                                                  $ 7,088,146
                                                                          $ 14,720,000
52            Priority 5                                                  $ 21,808,146

53            Total

                                   Page 29 of 174
    HB NO. 2                                                              ENROLLED

1   (576840) Rehabilitation and Repair of State-Maintained Reservoirs

2             and Dams

3             (Statewide)

4             Payable from General Obligation Bonds

5             Priority 1                                               $ 5,082,788

6             Priority 2                                               $ 2,000,000

7             Priority 5                                               $ 19,130,000

8             Total                                                    $ 26,212,788

9   (576841) New Orleans Rail Gateway Program

10            (Jefferson, Orleans)

11            Payable from General Obligation Bonds

12            Priority 1                                               $ 1,272,606
                                                                       $ 10,600,000
13            Priority 5                                               $ 11,872,606

14            Total

15  (576842) Bundick Lake Level Control Structure, Planning and

16            Construction

17            (Beauregard)

18            Payable from General Obligation Bonds

19            Priority 1                                               $ 1,691,918
                                                                       $ 3,180,000
20            Priority 5                                               $ 4,871,918

21            Total

22  (576843) Turkey Creek Lake Repairs, Planning and Construction

23            (Franklin)

24            Payable from General Obligation Bonds

25            Priority 1                                               $ 5,355,289

26  (576878) Flood Control Reservoirs in the Amite River Basin

27            Watershed

28            (Ascension, East Baton Rouge, East Feliciana,

29            Livingston, St. Helena)

30            Payable from General Obligation Bonds

31            Priority 5                                               $ 2,000,000

32  (576879) Mississippi River Levee Raising, Arkansas to Old River,

33            Planning and Construction

34            (Avoyelles, Concordia, East Carroll, Madison, Pointe

35            Coupee, Tensas)

36            Payable from General Obligation Bonds

37            Priority 1                                               $ 10,642,245

38            Priority 5                                               $ 36,820,000

39            Total                                                    $ 47,462,245

40  (576880) Comite River Diversion Canal Planning, Right-of-Way,

41            Utilities and Construction

42            (Ascension, East Baton Rouge, Livingston)

43            Payable from General Obligation Bonds

44            Priority 1                                               $  515,747

45            Payable from Federal Funds                               $ 50,000,000

46            Total                                                    $ 50,515,747

47  (577494) Port Construction and Development Priority Program

48            (Statewide)

49            Payable from Transportation Trust Fund - Regular         $ 39,400,000

50  (578084) Statewide Flood Control Program

51            (Statewide)

52            Payable from Transportation Trust Fund - Regular         $ 20,000,000

                                    Page 30 of 174
    HB NO. 2                                                              ENROLLED

1   (579003) Public Improvements Multimodal Program Capital

2             Projects, Planning and Construction

3             (Statewide)

4             Payable from General Obligation Bonds

5             Priority 2                                                  $ 76,751,739
                                                                          $ 87,470,000
6             Priority 5                                                  $ 164,221,739

7             Total

8   Provided, however, that the funds appropriated herein shall be expended solely on the

9   following projects:

10  Mississippi River Deepening, Phase 3, Planning, Design, Construction, Rights-of-Way,

11  Relocations and Utilities

12  Houma Navigational Canal Deepening Project, Planning, Design, Construction, Rights-

13  of-Ways, Relocations and Utilities

14  Acadiana Gulf of Mexico Access Channel (AGMAC), Port of Iberia, Planning, Design,

15  Construction, Rights-of-Way, Relocations and Utilities

16  J. Bennett Johnston (Red River) Deepening

17  Short Line Railroad Upgrades

18  New Orleans Rail Gateway Program

19  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

20  Joint Legislative Committee on the Budget, the secretary of the Department of

21  Transportation and Development is authorized to combine the specific projects listed within

22  this appropriation into the single project entitled Public Improvements Multimodal Program

23  Capital Projects. Furthermore, all appropriations for the specific projects combined into the

24  single project entitled Public Improvements Multimodal Program Capital Projects, including

25  cash appropriations, interagency transfers, statutory dedications, general obligation bond

26  appropriations, and appropriations from any other means of finance, contained in this Act

27  and any prior Capital Outlay Act, and all previously approved cash and noncash lines of

28  credit approved by the State Bond Commission for the specific projects included within this

29  appropriation shall transfer to and be included within the Public Improvements Multimodal

30  Program Capital Projects appropriation when the projects are combined by the secretary of

31  the Department of Transportation and Development.

32  (579002) Public Improvements Public Works Program Capital

33            Projects, Planning and Construction

34            (Statewide)

35            Payable from General Obligation Bonds

36            Priority 2                                                  $ 30,399,935
                                                                          $ 94,830,000
37            Priority 5                                                  $ 125,229,935

38            Total

39  Provided, however, that the funds appropriated herein shall be expended solely on the

40  following projects:

41  Bayou Dechene Reservoir, Planning, Land Acquisition and Construction

42  Ouachita River and Tributaries Bank Stabilization and Levee Repairs

43  West of Atchafalaya Basin Feasibility Study

44  Rehabilitation and Repair of State-Maintained Reservoirs and Dams

45  Bundick Lake Level Control Structure

46  Turkey Creek Lake Repairs

47  Flood Control Reservoirs in the Amite River Basin Watershed

48  Mississippi River Levee Raising, Arkansas to Old River

49  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

50  Joint Legislative Committee on the Budget, the secretary of the Department of

51  Transportation and Development is authorized to combine the specific projects listed within

52  this appropriation into the single project entitled Public Improvements Public Works

53  Program Capital Projects. Furthermore, all appropriations for the specific projects combined

54  into the single project entitled Public Improvements Public Works Program Capital Projects,

                                  Page 31 of 174
    HB NO. 2                                                                  ENROLLED

1   including cash appropriations, interagency transfers, statutory dedications, general obligation

2   bond appropriations, and appropriations from any other means of finance, contained in this

3   Act and any prior Capital Outlay Act, and all previously approved cash and noncash lines

4   of credit approved by the State Bond Commission for the specific projects included within

5   this appropriation shall transfer to and be included within the Public Improvements Public

6   Works Program Capital Projects appropriation when the projects are combined by the

7   secretary of the Department of Transportation and Development.

8   07/276 ENGINEERING AND OPERATIONS

9   (576765) Reconstruction and/or Rehabilitation of DOTD

10            Maintenance Unit Facilities

11            (Statewide)

12            Payable from General Obligation Bonds

13            Priority 5                                            $ 47,500,000

14  (578086) Motor Vessel and Equipment Drydocking, Repairs,

15            Various Locations Statewide

16            (Statewide)

17            Payable from Transportation Trust Fund - Regular      $ 1,500,000

18  (578087) Facilities Program Major Repairs, Renovations,

19            Additions, New Facilities, Equipment Replacement at

20            Various DOTD Sites, Planning and Construction

21            (Statewide)

22            Payable from Transportation Trust Fund - Regular      $ 2,000,000

23  (579004) Engineering and Operations Facilities Program

24            Capital Projects, Planning and Construction

25            (Statewide)

26            Payable from General Obligation Bonds

27            Priority 5                                            $ 47,500,000
                                                                    $ 2,000,000
28            Payable from Transportation Trust Fund - Regular      $ 49,500,000

29            Total

30  Provided, however, that the funds appropriated herein shall be expended solely on the

31  following projects:

32  Reconstruction and/or Rehabilitation of DOTD Maintenance Unit Facilities

33  Facilities Program Major Repairs, Renovations, Additions, New Facilities, Equipment

34  Replacement at Various DOTD Sites

35  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

36  Joint Legislative Committee on the Budget, the secretary of the Department of

37  Transportation and Development is authorized to combine the specific projects listed within

38  this appropriation into the single project entitled Engineering and Operations Facilities

39  Program Capital Projects. Furthermore, all appropriations for the specific projects combined

40  into the single project entitled Engineering and Operations Facilities Program Capital

41  Projects, including cash appropriations, interagency transfers, statutory dedications, general

42  obligation bond appropriations, and appropriations from any other means of finance,

43  contained in this Act and any prior Capital Outlay Act, and all previously approved cash and

44  noncash lines of credit approved by the State Bond Commission for the specific projects

45  included within this appropriation shall transfer to and be included within the Engineering

46  and Operations Facilities Program Capital Projects appropriation when the projects are

47  combined by the secretary of the Department of Transportation and Development.

                           Page 32 of 174
    HB NO. 2                                                          ENROLLED

1   07/277 AVIATION IMPROVEMENTS

2   (578088) State Aviation and Airport Improvement Program

3             (Statewide)

4             Payable from the Transportation Trust Fund -

5             Regular                                                 $ 19,945,415
                                                                      $ 2,000,000
6             Payable from the Capital Outlay Savings Fund            $ 21,945,415

7             Total

8             DEPARTMENT OF PUBLIC SAFETY AND CORRECTIONS

9   08/400 DEPARTMENT OF CORRECTIONS

10  (576807) Statewide Fencing and Security Enhancements Project at

11            all State Adult Correctional Facilities

12            (Statewide)

13            Payable from General Obligation Bonds

14            Priority 5                                              $ 8,000,000

15            Payable from State General Fund (Direct) Non-Recurring

16            Revenues                                                $ 1,000,000

17            Total                                                   $ 9,000,000

18  (576808) HVAC Installation, Offender Housing, Planning and

19            Construction

20            (Statewide)

21            Payable from General Obligation Bonds

22            Priority 1                                              $ 5,473,930
                                                                      $ 29,000,000
23            Priority 5                                              $ 34,473,930

24            Total

25  08/402 LOUISIANA STATE PENITENTIARY

26  (576901) Electrical Distribution System Upgrade, Planning and

27            Construction

28            (West Feliciana)

29            Payable from General Obligation Bonds

30            Priority 1                                              $ 7,342,276

31            Priority 5                                              $ 17,000,000

32            Total                                                   $ 24,342,276

33  (576902) Main Prison Shower and Cellblock Plumbing Upgrade,

34            Planning and Construction

35            (West Feliciana)

36            Payable from General Obligation Bonds

37            Priority 1                                              $ 1,563,382

38  08/403 OFFICE OF JUVENILE JUSTICE

39  (577433) Community Based Program, Juvenile Justice

40            Improvements, Planning, Construction, Renovation,

41            Acquisition, and Equipment

42            (Statewide)

43            Payable from General Obligation Bonds

44            Priority 1                                              $ 50,849,226
                                                                      $ 52,000,000
45            Priority 5                                              $ 102,849,226

46            Total

                                Page 33 of 174
    HB NO. 2                                                              ENROLLED

1   08/406 LOUISIANA CORRECTIONAL INSTITUTE FOR WOMEN

2   (578892) Rebuild and/or Replace Facility Due to Damage from 2016

3             Flood Event

4             (Iberville)

5             Payable from General Obligation Bonds

6             Priority 1                                               $ 7,972,290

7   08/416 RAYBURN CORRECTIONAL CENTER

8   (576729) Security Perimeter Fence, Planning and Construction

9             (Washington)

10            Payable from General Obligation Bonds

11            Priority 1                                               $  115,567

12  08/419 OFFICE OF STATE POLICE

13  (578481) State Police Region 3 Headquarters, Planning and

14            Construction

15            (Rapides)

16            Payable from General Obligation Bonds

17            Priority 5                                               $ 6,550,000

18            Payable from State General Fund (Direct) Non-Recurring

19            Revenues                                                 $  650,000

20            Total                                                    $ 7,200,000

21  (578486) New Louisiana State Police Troop L Facility, Planning

22            and Construction

23            (St. Tammany)

24            Payable from General Obligation Bonds

25            Priority 1                                               $ 25,500,000

26            Priority 5                                               $ 1,500,000

27            Total                                                    $ 27,000,000

28  (578487) JESTC Training Facility Improvements, Planning and

29            Construction

30            (East Baton Rouge)

31            Payable from General Obligation Bonds

32            Priority 1                                               $ 3,750,000

33                   LOUISIANA DEPARTMENT OF HEALTH

34  09/320 OFFICE OF AGING AND ADULT SERVICES

35  (578896) Replace Roof and Storm Drains on all Patient Buildings,

36            Planning and Construction

37            (East Feliciana)

38            Payable from General Obligation Bonds

39            Priority 1                                               $  900,000

40  09/330 OFFICE OF BEHAVIORAL HEALTH

41  (577312) Central Louisiana State Hospital "Warehouse" Relocation,

42            Planning and Construction

43            (Rapides)

44            Payable from General Obligation Bonds

45            Priority 1                                               $ 2,100,000

46            Priority 5                                               $ 1,440,000

47            Total                                                    $ 3,540,000

                                  Page 34 of 174
    HB NO. 2                                                               ENROLLED

1   (577317) Central Louisiana State Hospital Demolition of Buildings

2             Located on Rainbow Drive

3             (Rapides)

4             Payable from Interagency Transfers                        $ 10,000,000

5   (577363) Center Building and Fire Alarm System Renovation and

6             Restoration, East Louisiana State Hospital, Planning and

7             Construction

8             (East Feliciana)

9             Payable from General Obligation Bonds

10            Priority 1                                                $ 2,000,000

11            Priority 5                                                $ 3,000,000

12            Total                                                     $ 5,000,000

13  (577364) ELMHS Water System Replacement

14            (East Feliciana)

15            Payable from General Obligation Bonds

16            Priority 5                                                $ 2,020,000

17            Payable from State General Fund (Direct) Non-Recurring

18            Revenues                                                  $  200,000

19            Total                                                     $ 2,220,000

20  (577365) Fire Alarm System Replacement for Ten Buildings,

21            Planning and Construction

22            (East Feliciana)

23            Payable from General Obligation Bonds

24            Priority 1                                                $ 2,453,200

25  09/340 OFFICE FOR CITIZENS WITH DEVELOPMENTAL DISABILITIES

26  (577065) Pinecrest New Kitchen, Planning and Construction

27            (Rapides)

28            Payable from Interagency Transfers                        $ 5,000,000

29            DEPARTMENT OF CONSERVATION AND ENERGY

30  11/431 OFFICE OF THE SECRETARY

31  (578673) Water Monitoring System

32            (East Baton Rouge)

33            Payable from General Obligation Bonds

34            Priority 1                                                $  924,968

35            Priority 5                                                $ 1,800,000

36            Total                                                     $ 2,724,968

37                   DEPARTMENT OF WILDLIFE AND FISHERIES

38  16/513 OFFICE OF WILDLIFE

39  (578294) Woodworth Central Office Complex and Pineville

40            Office/Region 3, Planning and Construction

41            (Rapides)

42            Payable from General Obligation Bonds

43            Priority 1                                                $ 2,022,698
                                                                        $ 4,160,000
44            Priority 5                                                $ 6,182,698

45            Total

46  (578307) Hammond Headquarters, Planning and Construction

47            (Tangipahoa)

48            Payable from General Obligation Bonds

49            Priority 1                                                $  324,036

                                  Page 35 of 174
    HB NO. 2                                                           ENROLLED

1   (578723) Kitterlin Creek Acquisition

2             (LaSalle)

3             Payable from General Obligation Bonds

4             Priority 5                                               $ 9,000,000

5             Payable from State General Fund (Direct) Non-Recurring

6             Revenues                                                 $ 2,000,000

7             Total                                                    $ 11,000,000

8                           DEPARTMENT OF EDUCATION

9   19/601 LSU BATON ROUGE

10  (576747) Science - Strategic Capital Plan Repairs and Upgrades -

11            Food Science Renovation, New Science Building,

12            Infrastructure and Utilities, Planning and Construction

13            (East Baton Rouge)

14            Payable from General Obligation Bonds

15            Priority 1                                               $ 16,938,033

16            Priority 5                                               $ 2,000,000

17            Total                                                    $ 18,938,033

18  (576748) Louisiana State University Library Learning Commons

19            and Associated Infrastructure and Renovations

20            (East Baton Rouge)

21            Payable from General Obligation Bonds

22            Priority 1                                               $ 38,843,667

23            Priority 5                                               $ 95,200,000

24            Payable from Fees and Self-Generated Revenues            $ 3,000,000

25            Total                                                    $ 137,043,667

26  (576749) Military and Security Sciences Center, Planning and

27            Construction

28            (East Baton Rouge)

29            Payable from General Obligation Bonds

30            Priority 1                                               $ 21,293,192

31  (576750) Construction Management & Engineering Sciences

32            Building, Planning and Construction

33            (East Baton Rouge)

34            Payable from General Obligation Bonds

35            Priority 5                                               $ 52,000,000

36  (576751) Veterinary Medicine Facilities Repairs/Addition

37            (East Baton Rouge)

38            Payable from General Obligation Bonds

39            Priority 1                                               $ 4,424,704
                                                                       $ 5,680,000
40            Priority 5                                               $ 10,104,704

41            Total

42  (578801) Facility Upgrade, Planning and Construction

43            (East Baton Rouge)

44            Payable from General Obligation Bonds

45            Priority 5                                               $ 9,000,000
                                                                       $ 9,000,000
46            Payable from Fees and Self-Generated Revenues            $ 18,000,000

47            Total

                                  Page 36 of 174
    HB NO. 2                                                                ENROLLED

1   (578984) Construction Education and Workforce Hub,

2             Planning and Construction

3             (East Baton Rouge)

4             Payable from General Obligation Bonds

5             Priority 5                                        $ 15,000,000
                                                                $ 15,000,000
6             Payable from Fees and Self-Generated Revenues     $ 30,000,000

7             Total

8   (579000) Louisiana State University Baton Rouge Campus

9             Capital Projects, Planning and Construction

10            (East Baton Rouge)

11            Payable from General Obligation Bonds

12            Priority 2                                        $ 81,499,596
                                                                $ 178,880,000
13            Priority 5                                        $ 260,379,596

14            Total

15  Provided, however, that the funds appropriated herein shall be expended solely on the

16  following projects:

17  Science - Strategic Capital Plan Repairs and Upgrades - Food Science Renovation, New

18  Science Building, Infrastructure and Utilities

19  Library Learning Commons and Associated Infrastructure and Renovations

20  Military and Security Sciences Center

21  Construction Management & Engineering Sciences Building

22  Veterinary Medicine Facilities Repairs/Addition

23  Facility Upgrade

24  Construction Education and Workforce Hub

25  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

26  Joint Legislative Committee on the Budget, the director of the office of facility planning and

27  control is authorized to combine the specific projects listed within this appropriation into the

28  single project entitled Louisiana State University Baton Rouge Campus Capital Projects.

29  Furthermore, all appropriations for the specific projects combined into the single project

30  entitled Louisiana State University Baton Rouge Campus Capital Projects, including cash

31  appropriations, appropriations of fees and self-generated revenues, interagency transfers,

32  statutory dedications, general obligation bond appropriations, and appropriations from any

33  other means of finance, contained in this Act and any prior Capital Outlay Act, and all

34  previously approved cash and noncash lines of credit approved by the State Bond

35  Commission for the specific projects included within this appropriation shall transfer to and

36  be included within the Louisiana State University Baton Rouge Campus Capital Projects

37  appropriation when the projects are combined by the director of the office of facility

38  planning and control.

39  19/602 LSU ALEXANDRIA

40  (576628) Student Success Center, Planning and Construction

41            (Rapides)

42            Payable from General Obligation Bonds

43            Priority 1                                        $ 2,900,000

44  (576629) Downtown Health Services Center, Planning and

45            Construction

46            (Rapides)

47            Payable from General Obligation Bonds

48            Priority 1                                        $ 19,259,545
                                                                $ 9,885,000
49            Priority 5                                        $ 29,144,545

50            Total

                                  Page 37 of 174
    HB NO. 2                                                            ENROLLED

1   (576630) Workforce Academic Center, Planning and Construction

2             (Rapides)

3             Payable from General Obligation Bonds

4             Priority 5                                             $ 21,304,391

5             Payable from Fees and Self-Generated Revenues          $ 2,000,000

6             Total                                                  $ 23,304,391

7   (578993) Parking Garage, Planning and Construction

8             (Rapides)

9             Payable from General Obligation Bonds

10            Priority 5                                             $ 6,750,000

11            Payable from State General Fund (Direct)               $  750,000

12            Total                                                  $ 7,500,000

13  ()        Property Acquisition
              (Rapides)
14            Payable from General Obligation Bonds

15                Priority 2

16                                                                   $ 4,000,000

17  Pending approval of the capital outlay budget request pursuant to the provisions of R.S.

18  39:112.

19  19/603 UNIVERSITY OF NEW ORLEANS

20  (577089) Hotel, Restaurant and Tourism Program Relocation

21            Buildout to North Central Plant Building - Phase 1,

22            Planning and Construction

23            (Orleans)

24            Payable from General Obligation Bonds

25            Priority 1                                             $ 5,793,570

26  (577090) Miscellaneous Roof Replacements, Planning and

27            Construction

28            (Orleans)

29            Payable from General Obligation Bonds

30            Priority 1                                             $ 4,800,000

31  19/604 LSU HEALTH SCIENCES CENTER - NEW ORLEANS

32  (576587) LSUHSC-NO Medical Education Building Laboratory

33            Renovation, Phase 1, Planning and Construction

34            (Orleans)

35            Payable from General Obligation Bonds

36            Priority 1                                             $  12,556

37  (576588) Health Science Center Facility Renovations - Dental

38            School Simulation Facility, Planning and Construction

39            (Orleans)

40            Payable from General Obligation Bonds

41            Priority 1                                             $ 20,931,927

42            Priority 5                                             $ 70,000,000

43            Total                                                  $ 90,931,927

44  (576592) Elevated Walkways Structural and ADA

45            Improvements, Planning and Construction

46            (Orleans)

47            Payable from General Obligation Bonds

48            Priority 5                                             $ 12,000,000

                            Page 38 of 174
    HB NO. 2                                                             ENROLLED

1   (576593) LSUHSC-NO Campus Stormwater Infrastructure Upgrades,

2             Planning and Construction

3             (Orleans)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 3,000,000

6   (578778) Center for Advanced Learning and Simulation

7             3rd Floor Renovations, Planning and Construction

8             (Orleans)

9             Payable from Fees and Self Generated Revenues           $ 3,000,000

10  19/605 LSU EUNICE

11  (576942) Manuel Hall Exterior Wall and Roof Repair,

12            Planning and Construction

13            (Acadia)

14            Payable from General Obligation Bonds

15            Priority 1                                              $ 1,054,802

16  (576943) Athletic Complex Facility, Planning and Construction

17            (Acadia)

18            Payable from General Obligation Bonds

19            Priority 1                                              $  228,007

20            Priority 5                                              $ 4,750,000

21            Payable from State General Fund (Direct) Non-Recurring

22            Revenues                                                $ 4,750,000

23            Total                                                   $ 9,728,007

24  (576944) STEAM Innovation Center, Phase 1,

25            Planning and Construction

26            (Acadia)

27            Payable from General Obligation Bonds

28            Priority 1                                              $ 9,500,000
                                                                      $ 13,400,000
29            Priority 5                                              $ 22,900,000

30            Total

31  19/606 LSU SHREVEPORT

32  (576634) HPE Renovation for Student Wellness Facility and

33            Campus Repairs, Planning and Construction

34            (Caddo)

35            Payable from General Obligation Bonds

36            Priority 5                                              $ 9,000,000

37            Payable from the balance of the Capital Outlay Savings

38            Fund previously allocated under the authority of Act 2

39            of 2025 for Shreveport, Shreveport Healthcare and

40            Development Corridor, Planning and Construction

41            (Caddo)                                                 $ 1,500,000

42            Total                                                   $ 10,500,000

43  (576848) Building Exterior Walls and Bridge Repair,

44            Planning and Construction

45            (Caddo)

46            Payable from General Obligation Bonds

47            Priority 1                                              $  951,628

                          Page 39 of 174
    HB NO. 2                                                                ENROLLED

1   (576900) High Voltage Grid System, Planning and

2             Construction

3             (Caddo)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $ 4,120,000

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                   $  500,000

8             Total                                                      $ 4,620,000

9   19/607 LSU AGRICULTURAL CENTER

10  (576601) Food Innovation Center, Planning and Construction

11            (East Baton Rouge)

12            Payable from General Obligation Bonds

13            Priority 1                                                 $ 1,993,355

14            Priority 5                                                 $ 2,000,000

15            Payable from State General Fund (Direct) Non-Recurring

16            Revenues                                                   $  750,000

17            Total                                                      $ 4,743,355

18  (576606) Animal and Food Science Facilities Renovations and

19            Modernization, Phase I through Phase V, Planning and

20            Construction

21            (East Baton Rouge)

22            Payable from General Obligation Bonds

23            Priority 1                                                 $ 1,460,479

24            Priority 5                                                 $ 28,203,500

25            Total                                                      $ 29,663,979

26  (576607) Renewable and Natural Resources Building Repairs,

27            Planning and Construction

28            (East Baton Rouge)

29            Payable from General Obligation Bonds

30            Priority 1                                                 $ 2,499,874
                                                                         $ 2,500,000
31            Priority 5                                                 $ 4,999,874

32            Total

33  (576611) John M. Parker Agricultural Center & Livestock Show Barn

34            Renovations and Repairs

35            (East Baton Rouge)

36            Payable from General Obligation Bonds

37            Priority 1                                                 $ 1,500,000

38            Priority 5                                                 $ 21,500,000

39            Total                                                      $ 23,000,000

40  (578935) Dean Lee Tornado Damage Building Repairs and

41            Reconstruction

42            (Rapides)

43            Payable from General Obligation Bonds

44            Priority 1                                                 $  97,687

45  19/609 PENNINGTON BIOMEDICAL RESEARCH CENTER

46  (576605) Replacement of Underground Chilled Water & Hot Water

47            Piping, Both Supply and Return, Planning and Construction

48            (East Baton Rouge)

49            Payable from General Obligation Bonds

50            Priority 1                                                 $ 2,200,000

                                  Page 40 of 174
    HB NO. 2                                                               ENROLLED

1   19/611 LSU HEALTH SCIENCES CENTER - SHREVEPORT

2   (576740) Comprehensive Emergency Water Supply Improvements,

3             Planning and Construction

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 1                                                $ 4,920,006

7   (576741) Gross Anatomy Lab Expansion and Modernization,

8             Planning and Construction

9             (Caddo)

10            Payable from General Obligation Bonds

11            Priority 1                                                $  26,872

12  (576742) Center for Medical Education and Wellness, Planning and

13            Construction

14            (Caddo)

15            Payable from General Obligation Bonds

16            Priority 1                                                $ 1,077,028

17  (576743) Stonewall Animal Research and Training Facility, Planning

18            and Construction

19            (DeSoto)

20            Payable from General Obligation Bonds

21            Priority 5                                                $ 5,000,000

22  (578410) Student and Faculty Parking Expansion, Planning and

23            Construction

24            (Caddo)

25            Payable from General Obligation Bonds

26            Priority 5                                                $ 3,000,000

27  19/612 BATON ROUGE COMMUNITY COLLEGE

28  (577595) Campus Development, Planning and Construction

29            (Pointe Coupee)

30            Payable from General Obligation Bonds

31            Priority 1                                                $ 4,000,000
                                                                        $ 2,000,000
32            Priority 5                                                $ 6,000,000

33            Total

34  (577596) Office of Motor Vehicles Building and Campus

35            Renovation, Demolition and Improvements,

36            Planning and Construction

37            (East Baton Rouge)

38            Payable from General Obligation Bonds

39            Priority 1                                                $ 6,789,354

40  19/614 SOUTHERN UNIVERSITY LAW CENTER

41  (577088) Renovations and Addition to Existing Law Library,

42            Planning and Construction

43            (East Baton Rouge)

44            Payable from General Obligation Bonds

45            Priority 1                                                $ 9,372,184

                                  Page 41 of 174
    HB NO. 2                                                              ENROLLED

1   19/616 SOUTHERN UNIVERSITY - BATON ROUGE

2   (577072) Global Innovation and Welcome Center, Phase II, Planning

3             and Construction

4             (East Baton Rouge)

5             Payable from General Obligation Bonds

6             Priority 5                                                  $ 30,000,000

7             Payable from State General Fund (Direct) Non-Recurring

8             Revenues                                                    $ 1,680,000

9             Total                                                       $ 31,680,000

10  (577073) New STEM Science Complex, Planning and Construction

11            (East Baton Rouge)

12            Payable from General Obligation Bonds

13            Priority 1                                                  $ 50,684,466

14  (577074) College of Business/Professional Accountancy, Planning

15            and Construction

16            (East Baton Rouge)

17            Payable from General Obligation Bonds

18            Priority 1                                                  $ 18,456,267

19            Priority 5                                                  $ 25,000,000

20            Payable from Fees and Self-Generated Revenues               $ 10,000,000

21            Total                                                       $ 53,456,267

22  (577075) J. K. Haynes Hall School of Nursing Renovation and

23            Addition, Planning and Construction

24            (East Baton Rouge)

25            Payable from General Obligation Bonds

26            Priority 1                                                  $ 10,300,000

27  (577076) New Southern University Laboratory School Complex,

28            Planning and Construction

29            (East Baton Rouge)

30            Payable from General Obligation Bonds

31            Priority 1                                                  $ 1,469,524

32            Priority 5                                                  $ 71,500,000

33            Total                                                       $ 72,969,524

34  (577077) Replace Chilled Water Lines, Planning and Construction

35            (East Baton Rouge)

36            Payable from General Obligation Bonds

37            Priority 1                                                  $ 24,500,000

38            Priority 5                                                  $ 7,500,000

39            Total                                                       $ 32,000,000

40  (577078) Ravine, Bluff and Riverbank Stabilization Project, Planning

41            and Construction

42            (East Baton Rouge)

43            Payable from General Obligation Bonds

44            Priority 1                                                  $ 1,500,000

45            Priority 5                                                  $ 30,500,600

46            Payable from Federal Funds via Interagency Transfers        $ 7,565,000

47            Total                                                       $ 39,565,600

                                  Page 42 of 174
    HB NO. 2                                                            ENROLLED

1   (578639) A.O. Williams Hall Renovations, Planning and Construction

2             (East Baton Rouge)

3             Payable from General Obligation Bonds

4             Priority 1                                                $ 10,941,331

5             Priority 5                                                $ 8,441,346

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                  $ 14,500,000

8             Total                                                     $ 33,882,677

9   (578934) Stewart Hall - Wall Mount HVAC Units 1st, 2nd and 3rd

10            Floors, Planning and Construction

11            (East Baton Rouge)

12            Payable from General Obligation Bonds

13            Priority 1                                                $ 1,663,215

14            Priority 5                                                $ 1,200,000

15            Total                                                     $ 2,863,215

16  (579005) Southern University Baton Rouge Campus

17            Capital Projects, Planning and Construction

18            (East Baton Rouge)

19            Payable from General Obligation Bonds

20            Priority 2                                                $ 115,514,803
                                                                        $ 178,141,946
21            Priority 5                                                $ 293,656,749

22            Total

23  Provided, however, that the funds appropriated herein shall be expended solely on the

24  following projects:

25  Global Innovation and Welcome Center, Phase II

26  New STEM Science Complex

27  College of Business/Professional Accountancy

28  J. K. Haynes Hall School of Nursing Renovation and Addition

29  New Southern University Laboratory School Complex

30  Replace Chilled Water Lines

31  Ravine, Bluff and Riverbank Stabilization Project

32  A.O. Williams Hall Renovations

33  Stewart Hall - Wall Mount HVAC Units 1st, 2nd and 3rd Floors

34  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

35  Joint Legislative Committee on the Budget, the director of the office of facility planning and

36  control is authorized to combine the specific projects listed within this appropriation into the

37  single project entitled Southern University Baton Rouge Campus Capital Projects.

38  Furthermore, all appropriations for the specific projects combined into the single project

39  entitled Southern University Baton Rouge Campus Capital Projects, including cash

40  appropriations, appropriations of fees and self-generated revenues, interagency transfers,

41  statutory dedications, general obligation bond appropriations, and appropriations from any

42  other means of finance, contained in this Act and any prior Capital Outlay Act, and all

43  previously approved cash and noncash lines of credit approved by the State Bond

44  Commission for the specific projects included within this appropriation shall transfer to and

45  be included within the Southern University Baton Rouge Campus Capital Projects

46  appropriation when the projects are combined by the director of the office of facility

47  planning and control.

48  19/617 SOUTHERN UNIVERSITY - NEW ORLEANS

49  (577079) University Cafeteria, Planning and Construction

50            (Orleans)

51            Payable from General Obligation Bonds

52            Priority 1                                                $ 7,411,545
                                                                        $ 6,900,000
53            Priority 5                                                $ 14,311,545

54            Total

                                    Page 43 of 174
    HB NO. 2                                                               ENROLLED

1   (577086) Nursing and Allied Health Building, Planning and

2             Construction

3             (Orleans)

4             Payable from Fees and Self-Generated Revenues             $ 3,000,000

5   (577087) University Housing Renovation, Planning and Construction

6             (Orleans)

7             Payable from General Obligation Bonds

8             Priority 2                                                $ 19,500,000

9   (578932) ADA Compliant Restrooms and Public Accommodations

10            in the Cafeteria, University Center, Health & Physical

11            Education, Library and Administration Building, Planning

12            and Construction

13            (Orleans)

14            Payable from General Obligation Bonds

15            Priority 1                                                $  977,998

16  (578933) Campus Exterior Lighting Upgrades, Planning and

17            Construction

18            (Orleans)

19            Payable from General Obligation Bonds

20            Priority 1                                                $  100,062

21  19/618 SOUTHERN UNIVERSITY - SHREVEPORT

22  (577081) Domestic Water Loop, Hot Water Loop and Drainage

23            Improvements, Planning and Construction

24            (Caddo)

25            Payable from General Obligation Bonds

26            Priority 5                                                $ 7,480,000

27  (577082) New Workforce Training and Technology Center, Planning

28            and Construction

29            (Caddo)

30            Payable from General Obligation Bonds

31            Priority 1                                                $ 1,506,598

32            Priority 5                                                $ 17,500,000

33            Total                                                     $ 19,006,598

34  (577085) Louis Collier Hall Science Building Replacement, Planning

35            and Construction

36            (Caddo)

37            Payable from General Obligation Bonds

38            Priority 1                                                $ 5,454,083

39            Priority 5                                                $ 12,450,000

40            Total                                                     $ 17,904,083

41  19/619 SOUTHERN UNIVERSITY - BATON ROUGE

42  (578961) Disaster Relief Mega Shelter and Safe Room, Planning and

43            Construction

44            (East Baton Rouge)

45            Payable from General Obligation Bonds

46            Priority 1                                                $ 1,138,067

47            Priority 5                                                $ 9,200,000

48            Total                                                     $ 10,338,067

                                  Page 44 of 174
    HB NO. 2                                                          ENROLLED

1   19/621 NICHOLLS STATE UNIVERSITY

2   (576406) Didier Fieldhouse, Planning and Construction

3             (Lafourche)

4             Payable from General Obligation Bonds

5             Priority 1                                           $ 3,100,000

6   (576407) Women's Student Athlete Performance Center, Planning

7             and Construction

8             (Lafourche)

9             Payable from General Obligation Bonds

10            Priority 1                                           $ 3,700,000

11  (576408) New Nursing Building, Planning and Construction

12            (Lafourche)

13            Payable from General Obligation Bonds

14            Priority 1                                           $ 12,143,600

15  (576409) May and Harvey Peltier Center (Welcome Center-Alumni

16            House), Planning and Construction

17            (Lafourche)

18            Payable from General Obligation Bonds

19            Priority 1                                           $ 1,000,000

20            Priority 5                                           $ 3,335,000

21            Total                                                $ 4,335,000

22  (576422) Coastal Center Facility, Planning and Construction

23            (Lafourche)

24            Payable from General Obligation Bonds

25            Priority 5                                           $ 3,500,000
                                                                   $ 3,500,000
26            Payable from Fees and Self-Generated Revenues        $ 7,000,000

27            Total

28  (576423) Al Danos New College of Business/School of Marine

29            Transportation Building, Planning and Construction

30            (Lafourche)

31            Payable from General Obligation Bonds

32            Priority 1                                           $ 2,500,000

33            Priority 5                                           $ 22,500,000

34            Total                                                $ 25,000,000

35  19/623 GRAMBLING STATE UNIVERSITY

36  (577133) Reroof, Waterproof, Envelope Repairs for Various

37            Buildings, Planning and Construction

38            (Lincoln)

39            Payable from General Obligation Bonds

40            Priority 1                                           $ 4,500,000
                                                                   $ 4,000,000
41            Priority 5                                           $ 8,500,000

42            Total

43  (577135) Criminal Justice Building Renovation

44            (Lincoln)

45            Payable from General Obligation Bonds

46            Priority 1                                           $  696,301

47            Priority 2                                           $ 12,000,000

48            Priority 5                                           $ 4,000,000

49            Total                                                $ 16,696,301

                                Page 45 of 174
    HB NO. 2                                                             ENROLLED

1   (577297) Indoor Athletics Facility, Planning and Construction

2             (Lincoln)

3             Payable from General Obligation Bonds

4             Priority 5                                              $ 12,000,000

5             Payable from Fees and Self-Generated                    $ 6,700,000
                                                                      $ 6,000,000
6             Revenues                                                $ 24,700,000

7             Payable from the Capital Outlay Savings Fund

8             Total

9   (578931) Campus Utility Infrastructure Assessment Emergency

10            Repair/Replacement, Planning and Construction

11            (Lincoln)

12            Payable from General Obligation Bonds

13            Priority 1                                              $ 7,277,741

14  (578986) Construction of Campus Dining and Student Union

15            Facility, Planning and Construction

16            (Lincoln)

17            Payable from Fees and Self-Generated Revenues           $ 25,000,000

18  (578987) Construction of GSU Hotel and Conference Center,

19            Planning and Construction

20            (Lincoln)

21            Payable from Fees and Self-Generated Revenues           $ 43,000,000

22  (578991) Campus Perimeter Fencing, Planning and Construction

23            (Lincoln)

24            Payable from Fees and Self-Generated Revenues           $ 5,000,000

25  (578992) Deferred Maintenance Repairs, Planning and Construction

26            (Lincoln)

27            Payable from Fees and Self-Generated Revenues           $ 16,400,000

28  19/625 LOUISIANA TECH UNIVERSITY

29  (576716) Renovation of George T. Madison Hall, Planning and

30            Construction

31            (Lincoln)

32            Payable from General Obligation Bonds

33            Priority 1                                              $ 31,683,762

34            Priority 5                                              $ 5,000,000

35            Total                                                   $ 36,683,762

36  (576733) Wyly Tower - Prescott Library - Emergency Waterproofing

37            and Restoration, Planning and Construction

38            (Lincoln)

39            Payable from General Obligation Bonds

40            Priority 2                                              $  500,000

41            Priority 5                                              $ 4,500,000

42            Total                                                   $ 5,000,000

43  (578927) Agriculture and Forestry Wood Products Education and

44            Research Center, Planning and Construction

45            (Lincoln)

46            Payable from General Obligation Bonds

47            Priority 1                                              $ 9,416,818

                            Page 46 of 174
    HB NO. 2                                                              ENROLLED

1   (578928) Central Steam Generator - Switch Gear, Planning and

2             Construction

3             (Lincoln)

4             Payable from General Obligation Bonds

5             Priority 1                                               $  169,906

6   (578929) Athletic Academic Center, Planning and Construction

7             (Lincoln)

8             Payable from General Obligation Bonds

9             Priority 1                                               $  1,860

10  19/627 MCNEESE STATE UNIVERSITY

11  (577048) Burton Business Center Exterior Mitigation, Planning and

12            Construction

13            (Calcasieu)

14            Payable from General Obligation Bonds

15            Priority 1                                               $ 7,000,000

16  (577049) Cowboy Stadium Repairs and Code Upgrade,

17            Planning and Construction

18            (Calcasieu)

19            Payable from General Obligation Bonds

20            Priority 2                                               $  200,000

21            Priority 5                                               $ 1,800,000

22            Total                                                    $ 2,000,000

23  (577242) Shearman Fine Arts Building Renovation and Addition,

24            Planning and Construction

25            (Calcasieu)

26            Payable from General Obligation Bonds

27            Priority 1                                               $ 4,182,206

28  (577243) McNeese Disaster Recovery, Planning and Construction

29            (Calcasieu)

30            Payable from General Obligation Bonds

31            Priority 1                                               $ 6,661,316

32  (577244) Contraband Bayou Erosion Retaining Wall, Phase II,

33            Planning and Construction

34            (Calcasieu)

35            Payable from General Obligation Bonds

36            Priority 1                                               $  414,114

37            Priority 5                                               $ 2,200,000

38            Total                                                    $ 2,614,114

39  19/629 UNIVERSITY OF LOUISIANA - MONROE

40  (576666) Brown Hall Renovation, Planning and Construction

41            (Ouachita)

42            Payable from General Obligation Bonds

43            Priority 5                                               $ 10,500,000

44            Payable from State General Fund (Direct) Non-Recurring

45            Revenues                                                 $  650,000

46            Total                                                    $ 11,150,000

47  (578920) Health Science Complex Renovation, Sugar Hall and

48            Caldwell Hall, Planning and Construction

49            (Ouachita)

50            Payable from General Obligation Bonds

51            Priority 1                                               $ 3,765,676

                            Page 47 of 174
    HB NO. 2                                                              ENROLLED

1   19/631 NORTHWESTERN STATE UNIVERSITY

2   (577059) Renovation of Nursing Education Center at Warrington

3             Place (Shreveport Campus), Planning and Construction

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 1                                                  $ 7,000,000

7             Priority 5                                                  $ 10,525,000

8             Total                                                       $ 17,525,000

9   (578919) Replacement of John S. Kyser Hall, Planning and

10            Construction

11            (Natchitoches)

12            Payable from General Obligation Bonds

13            Priority 1                                                  $ 6,544,641

14  19/634 SOUTHEASTERN LOUISIANA UNIVERSITY

15  (576508) Academic Athletic Training and Ancillary Athletic Facility,

16            Planning and Construction

17            (Tangipahoa)

18            Payable from General Obligation Bonds

19            Priority 1                                                  $ 16,814,543

20            Priority 5                                                  $ 3,400,000

21            Payable from State General Fund (Direct) Non-Recurring

22            Revenues                                                    $ 5,800,000

23            Payable from Fees and Self-Generated Revenues               $ 1,000,000

24            Total                                                       $ 27,014,543

25  (576509) Baton Rouge Nursing Center Renovation, Planning and

26            Construction

27            (East Baton Rouge)

28            Payable from General Obligation Bonds

29            Priority 1                                                  $ 13,210,900

30            Priority 5                                                  $ 2,000,000

31            Total                                                       $ 15,210,900

32  (576510) Nursing and Health Science Building, Planning and

33            Construction

34            (Tangipahoa)

35            Payable from General Obligation Bonds

36            Priority 1                                                  $ 1,001,729
                                                                          $ 30,300,000
37            Priority 5                                                  $ 31,301,729

38            Total

39  (578918) D. Vickers Hall Renovation and Addition, Planning and

40            Construction

41            (Tangipahoa)

42            Payable from General Obligation Bonds

43            Priority 1                                                  $ 6,978,220

44  19/640 UNIVERSITY OF LOUISIANA - LAFAYETTE

45  (577039) Health Care Education and Training Facility and UL/LSU

46            Health Science Education Collaboration Building, Planning

47            and Construction

48            (Lafayette)

49            Payable from General Obligation Bonds

50            Priority 1                                                  $ 21,425,391

51            Priority 5                                                  $ 91,920,000

52            Total                                                       $ 113,345,391

                                  Page 48 of 174
    HB NO. 2                                                               ENROLLED

1   (577040) Engineering Classroom Building, Planning and Construction

2             (Lafayette)

3             Payable from General Obligation Bonds

4             Priority 1                                                $ 27,894,149

5             Priority 5                                                $ 32,876,573

6             Total                                                     $ 60,770,722

7   (577041) Kinesiology, Hospitality Management, and Athletic

8             Administration Complex, Engineering, Stabilization,

9             Equipment, Planning and Construction

10            (Lafayette)

11            Payable from General Obligation Bonds

12            Priority 1                                                $ 3,854,466
                                                                        $ 48,141,000
13            Priority 5                                                $ 51,995,466

14            Total

15  (577042) Sciences Lab/Classroom Building, Planning and

16            Construction

17            (Lafayette)

18            Payable from General Obligation Bonds

19            Priority 1                                                $ 1,450,000
                                                                        $ 57,600,000
20            Priority 5                                                $ 59,050,000

21            Total

22  (577043) Learning Lab, Planning and Construction

23            (Lafayette)

24            Payable from General Obligation Bonds

25            Priority 5                                                $ 57,000,000

26  (577044) Billeaud Hall Renovation, Planning and Construction

27            (Lafayette)

28            Payable from General Obligation Bonds

29            Priority 5                                                $ 49,500,000

30  (577045) Montgomery Hall Renovation, Planning and Construction

31            (Lafayette)

32            Payable from General Obligation Bonds

33            Priority 5                                                $ 50,500,000

34  (578914) Foster Hall Renovation, Planning and Construction

35            (Lafayette)

36            Payable from General Obligation Bonds

37            Priority 1                                                $  292,272

38  (578915) DeClouet Hall Renovation, Planning and Construction

39            (Lafayette)

40            Payable from General Obligation Bonds

41            Priority 1                                                $  84,335

42  (578999) University of Louisiana Lafayette Campus

43            Capital Projects, Planning and Construction

44            (Lafayette)

45            Payable from General Obligation Bonds

46            Priority 2                                                $ 55,000,613
                                                                        $ 387,537,573
47            Priority 5                                                $ 442,538,186

48            Total

49  Provided, however, that the funds appropriated herein shall be expended solely on the

50  following projects:

                            Page 49 of 174
    HB NO. 2                                                             ENROLLED

1   Health Care Education and Training Facility and UL/LSU Health Science Education

2   Collaboration Building

3   Engineering Classroom Building

4   Kinesiology, Hospitality Management, and Athletic Administration Complex

5   Sciences Lab/Classroom Building

6   Learning Lab

7   Billeaud Hall Renovation

8   Montgomery Hall Renovation

9   Foster Hall Renovation

10  DeClouet Hall Renovation

11  Notwithstanding the provisions of Section 5 of this Act which requires the approval of the

12  Joint Legislative Committee on the Budget, the director of the office of facility planning and

13  control is authorized to combine the specific projects listed within this appropriation into the

14  single project entitled University of Louisiana Lafayette Campus Capital Projects.

15  Furthermore, all appropriations for the specific projects combined into the single project

16  entitled University of Louisiana Lafayette Campus Capital Projects, including cash

17  appropriations, appropriations of fees and self-generated revenues, interagency transfers,

18  statutory dedications, general obligation bond appropriations, and appropriations from any

19  other means of finance, contained in this Act and any prior Capital Outlay Act, and all

20  previously approved cash and noncash lines of credit approved by the State Bond

21  Commission for the specific projects included within this appropriation shall transfer to and

22  be included within the University of Louisiana Lafayette Campus Capital Projects

23  appropriation when the projects are combined by the director of the office of facility

24  planning and control.

25  19/647 LOUISIANA DELTA COMMUNITY COLLEGE

26  (577593) Campus Development for Louisiana Delta Community

27            College, Planning and Construction

28            (Union)

29            Payable from General Obligation Bonds

30                Priority 1                                          $       600,000

31                Priority 5                                          $ 16,900,000

32            Total                                                   $ 17,500,000

33  (578913) Campus Expansion for Louisiana Delta Community

34            College, Winnsboro, Planning and Construction

35            (Franklin)

36            Payable from General Obligation Bonds

37                Priority 1                                          $              2,463

38  19/649 LOUISIANA COMMUNITY AND TECHNICAL COLLEGE SYSTEM

39  (577400) Central Louisiana Technical Community College - Campus

40            Development Rod Brady Campus, Planning and

41            Construction

42            (LaSalle)

43            Payable from General Obligation Bonds

44                Priority 5                                          $ 17,500,000

45            Payable from State General Fund (Direct) Non-Recurring

46            Revenues                                                $ 1,500,000

47            Total                                                   $ 19,000,000

48  (577590) Resurface Campus Parking, Planning and Construction

49            (Calcasieu)

50            Payable from General Obligation Bonds

51                Priority 1                                          $       635,020

52                Priority 5                                          $ 2,000,000

53            Total                                                   $ 2,635,020

                                    Page 50 of 174
    HB NO. 2                                                                ENROLLED

1   (577591) Maritime/Petroleum Workforce Training Academy,

2             Planning and Construction

3             (Terrebonne)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $ 9,334,817

6   19/656 LOUISIANA SPECIAL SCHOOL DISTRICT

7   (578661) Replacement of Air Handling Units (AHU) on the

8             Administrative Building and B1 Building, Planning and

9             Construction

10            (East Baton Rouge)

11            Payable from Interagency Transfers                         $  500,000

12  (578662) Roof Replacement - Louisiana School for the Deaf Middle

13            and High School and Vocational School, Planning and

14            Construction

15            (East Baton Rouge)

16            Payable from Interagency Transfers                         $  717,877

17  19/657 LOUISIANA SCHOOL FOR MATH, SCIENCE AND THE ARTS

18  (577257) Louisiana School for Math, Science, and the Arts and

19            Northwestern State University Innovation Center, Planning

20            and Construction

21            (Natchitoches)

22            Payable from General Obligation Bonds

23            Priority 1                                                 $ 6,900,000

24            Priority 5                                                 $ 6,900,000

25            Total                                                      $ 13,800,000

26  19/671 BOARD OF REGENTS

27  (578907) Major Repairs and Deferred Maintenance of Buildings and

28            Facilities, Planning and Construction

29            (Statewide)

30            Payable from General Obligation Bonds

31            Priority 5                                                 $ 10,000,000

32  (578908) System-Wide Telecommunications Wiring and Equipment,

33            Planning and Construction

34            (Statewide)

35            Payable from General Obligation Bonds

36            Priority 1                                                 $ 1,995,822

37  (578911) Land Acquisition for Post Secondary Educational

38            Institutions

39            (Statewide)

40            Payable from General Obligation Bonds

41            Priority 1                                                 $  160,908

42  19/674 LOUISIANA UNIVERSITIES MARINE CONSORTIUM

43  (578572) Research Vessel (R/V Pelican) Replacement

44            (Terrebonne)

45            Payable from General Obligation Bonds

46            Priority 1                                                 $ 20,823,903

                                  Page 51 of 174
    HB NO. 2                                                                  ENROLLED

1   (578573) Houma Marine Campus Phase 2, Planning and Construction

2             (Terrebonne)

3             Payable from General Obligation Bonds

4             Priority 1                                                   $ 14,740,647

5   19/712 LOUISIANA TECHNICAL COLLEGE-SULLIVAN CAMPUS

6   (577589) New Diesel Automotive Building, Northshore Technical

7             Community College - Sullivan Campus, Planning and Construction

8             (Washington)

9             Payable from General Obligation Bonds

10            Priority 1                                                   $ 11,585,635

11  19/731 FLETCHER TECHNICAL COMMUNITY COLLEGE

12  (577588) Precision Agriculture Training Facility, Planning and

13            Construction

14            (Terrebonne)

15            Payable from General Obligation Bonds

16            Priority 1                                                   $ 5,441,625

17  19/788 NORTHSHORE TECHNICAL COMMUNITY COLLEGE

18  (577587) Livingston Campus Expansion, Planning and Construction

19            (Livingston)

20            Payable from General Obligation Bonds

21            Priority 5                                                   $ 9,200,000

22  (579027) New Hammond Area Campus, Planning and Construction

23            (Tangipahoa)

24            Payable from General Obligation Bonds

25            Priority 5                                                   $ 38,975,000

26                          JUDICAL EXPENSES

27  23/949 LOUISIANA JUDICIARY

28  (578900) Land Acquisition, Planning, and Construction of New

29            Courthouse for the Louisiana Court of Appeal, Third Circuit

30            (Calcasieu)

31            Payable from General Obligation Bonds

32            Priority 1                                                   $  268,700

33                          LEVEE DISTRICTS AND PORTS

34  36/L03 LAFOURCHE BASIN LEVEE DISTRICT

35  (578253) West Bank and Vicinity Western Tie-In, Planning and

36            Construction

37            (St. James)

38            Payable from General Obligation Bonds

39            Priority 5                                                   $ 30,000,000

40  36/L13 PONTCHARTRAIN LEVEE DISTRICT

41  (578551) Lake Pontchartrain West Shore Hurricane Protection

42            Project Enhancement

43            (Ascension, St. Charles, St. James, St. John the Baptist)

44            Payable from General Obligation Bonds

45            Priority 1                                                   $ 10,566,307

                                   Page 52 of 174
    HB NO. 2                                                             ENROLLED

1   (579022) Bayou Manchac Regional Clearing and Snagging,

2             Planning and Construction

3             (Ascension, East Baton Rouge, Iberville)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 7,370,000

6   (578647) Bayou Manchac Regional Flood Risk Reduction Permitting

7             (Ascension, East Baton Rouge, Iberville)

8             Payable from General Obligation Bonds

9             Priority 5                                              $ 1,240,000

10  (578648) LA 22 Gapping Project, Planning and Construction

11            (Ascension, Livingston, St. James)

12            Payable from General Obligation Bonds

13            Priority 2                                              $ 1,000,000
                                                                      $ 2,990,000
14            Priority 5                                              $ 3,990,000

15            Total

16  (578899) Amite Diversion Canal Weir, Planning and Construction

17            (Ascension, Livingston, St. James)

18            Payable from General Obligation Bonds

19            Priority 5                                              $ 11,000,000

20  36/L15 SQUIRREL RUN LEVEE DRAINAGE DISTRICT

21  (577399) Maintenance of Levee and FEMA Certification

22            (Iberia)

23            Payable from General Obligation Bonds

24            Priority 1                                              $  21,488

25            Payable from State General Fund (Direct) Non-Recurring

26            Revenues                                                $  200,000

27            Total                                                   $  221,488

28  36/L16 SOUTH LAFOURCHE LEVEE DISTRICT

29  (576774) Larose to Golden Meadow Pump Station SCADA

30            System, Planning and Construction

31            (Lafourche)

32            Payable from State General Fund (Direct) Non-Recurring

33            Revenues                                                $ 1,600,000

34  (578898) Larose to Golden Meadow Hurricane Protection System,

35            Planning and Construction

36            (Lafourche)

37            Payable from General Obligation Bonds

38            Priority 5                                              $ 10,200,000

39  36/L25 GRAND ISLE INDEPENDENT LEVEE DISTRICT

40  (578265) Grand Isle Back Levee Flood Protection, Planning and

41            Construction

42            (Jefferson)

43            Payable from General Obligation Bonds

44            Priority 1                                              $ 1,500,000

                            Page 53 of 174
    HB NO. 2                                                              ENROLLED

1   36/L26 NATCHITOCHES LEVEE AND DRAINAGE DISTRICT

2   (578449) Levee Setbacks for the Campti-Clarence Levee and

3             Powhatan Levee, Planning and Construction

4             (Natchitoches)

5             Payable from General Obligation Bonds

6             Priority 1                                               $  865,000

7             Priority 5                                               $ 2,160,000

8             Payable from State General Fund (Direct)                 $  800,000

9             Total                                                    $ 3,825,000

10  36/L27 TERREBONNE LEVEE AND CONSERVATION DISTRICT

11  (577568) District Office Building/Satellite EOC and Louisiana

12            Department of Wildlife and Fisheries Facility, Planning

13            and Construction

14            (Terrebonne)

15            Payable from General Obligation Bonds

16            Priority 5                                               $ 7,100,000

17            Payable from the Capital Outlay Savings Fund             $ 2,500,000

18            Total                                                    $ 9,600,000

19  36/L30 SOUTHEAST LOUISIANA FLOOD PROTECTION

20            AUTHORITY EAST

21  (576886) Lakefront Airport Flood Protection, Planning,

22            Design, and Permit Analysis

23            (Orleans)

24            Payable from General Obligation Bonds

25            Priority 2                                               $  500,000

26            Priority 5                                               $ 22,000,000

27            Total                                                    $ 22,500,000

28  36/L34 LAKEFRONT MANAGEMENT AUTHORITY

29  (576757) Seabrook Public Boat Launch Rehabilitation, Planning and

30            Construction

31            (Orleans)

32            Payable from General Obligation Bonds

33            Priority 1                                               $  92,800

34            Priority 5                                               $ 1,780,000

35            Total                                                    $ 1,872,800

36  36/L36 LAFITTE AREA INDEPENDENT LEVEE DISTRICT

37  (578578) Goose Bayou/The Pen Levee Basin, Planning and

38            Construction

39            (Jefferson)

40            Payable from General Obligation Bonds

41            Priority 1                                               $ 1,000,000

42  (578894) Lower Lafitte (Orange Street) Basin, Planning and

43            Construction

44            (Jefferson)

45            Payable from General Obligation Bonds

46            Priority 1                                               $ 3,570,631

                                Page 54 of 174
    HB NO. 2                                                               ENROLLED

1   36/P00 VIDALIA PORT

2   (576692) Vidalia Port Expansion, Phase 3, Planning

3             and Construction

4             (Concordia)

5             Payable from General Obligation Bonds

6             Priority 2                                                $  500,000

7             Priority 5                                                $ 4,500,000

8             Total                                                     $ 5,000,000

9   36/P02 CAMERON PARISH PORT HARBOR AND TERMINAL DISTRICT

10  (578767) Dock Restoration and Expansion, Planning and Construction

11            (Cameron)

12            Payable from General Obligation Bonds

13            Priority 5                                                $ 4,400,000

14            Payable from State General Fund (Direct) Non-Recurring

15            Revenues                                                  $  500,000

16            Total                                                     $ 4,900,000

17  36/P03 GREATER BATON ROUGE PORT COMMISSION

18  (578891) Inland Rivers Marine Terminal Dock and Access Roadway

19            Construction Project, Planning and Construction

20            (East Baton Rouge)

21            Payable from General Obligation Bonds

22            Priority 5                                                $ 14,759,790

23  36/P04 CADDO/BOSSIER PARISH PORT

24  (578606) Caddo Bossier Parishes Port Commission Land Purchase,

25            Planning and Construction

26            (Caddo)

27            Payable from General Obligation Bonds

28            Priority 1                                                $ 8,000,000

29  36/P05 WEST CALCASIEU PORT

30  (578077) New Property Along Gulf Intracoastal Waterway, Planning

31            and Construction

32            (Calcasieu)

33            Payable from General Obligation Bonds

34            Priority 1                                                $  500,000

35            Priority 5                                                $ 1,500,000

36            Total                                                     $ 2,000,000

37  (578078) Construct New Dredged Material Reception Area,

38            Planning and Construction

39            (Calcasieu)

40            Payable from General Obligation Bonds

41            Priority 5                                                $ 2,700,000

42  36/P10 GREATER LAFOURCHE PORT COMMISSION

43  (577564) Fourchon Bridge and Connector Road, Planning and

44            Construction

45            (Lafourche)

46            Payable from General Obligation Bonds

47            Priority 1                                                $ 4,447,500
                                                                        $ 5,410,000
48            Priority 5                                                $ 9,857,500

49            Total

                                  Page 55 of 174
    HB NO. 2                                                              ENROLLED

1   (577565) Port Fourchon to Belle Pass Channel Deepening Project,

2             Planning and Construction

3             (Lafourche)

4             Payable from General Obligation Bonds

5             Priority 1                                                  $ 2,000,000

6             Priority 5                                                  $ 18,000,000

7             Total                                                       $ 20,000,000

8   36/P15 MORGAN CITY PORT

9   (576949) Dock Expansion - Bulkheading, State Drydock Repair, and

10            Related Dredging, Planning and Construction

11            (St. Mary)

12            Payable from General Obligation Bonds

13            Priority 1                                                  $ 8,000,000

14            Priority 5                                                  $ 27,000,000

15            Total                                                       $ 35,000,000

16  36/P16 IBERIA PORT

17  (578270) Road Repair, Replacement, and Improvements, Planning

18            and Construction

19            (Iberia)

20            Payable from General Obligation Bonds

21            Priority 1                                                  $ 1,700,000

22            Priority 5                                                  $ 13,000,000

23            Payable from State General Fund (Direct) Non-Recurring

24            Revenues                                                    $ 3,300,000

25            Total                                                       $ 18,000,000

26  (578272) Acadiana Gulf of Mexico Access Channel (AGMAC),

27            Port of Iberia, Planning, Design, Dredging Construction,

28            Rights-of-Way, Relocations and Utilities

29            (Iberia)

30            Payable from General Obligation Bonds

31            Priority 5                                                  $ 5,000,000

32  36/P17 PORT OF NEW ORLEANS

33  (578166) Louisiana International Terminal Drainage, Site

34            Preparation, Mitigation, Roadway and Rail Improvements,

35            Planning and Construction

36            (St. Bernard)

37            Payable from General Obligation Bonds

38            Priority 5                                                  $ 140,000,000

39  (578167) St. Claude Bridge Rehabilitation, Planning and Construction

40            (Orleans)

41            Payable from General Obligation Bonds

42            Priority 5                                                  $ 27,500,000

43  (578168) St. Bernard Transportation Corridor, Planning and

44            Construction

45            (St. Bernard)

46            Payable from General Obligation Bonds

47            Priority 1                                                  $ 2,000,000
                                                                          $ 48,000,000
48            Priority 5                                                  $ 50,000,000

49            Total

                                Page 56 of 174
    HB NO. 2                                                                ENROLLED

1   36/P20 ST. BERNARD PORT

2   (578484) Arabi Terminal Roadway Improvements, Planning and

3             Construction

4             (St. Bernard)

5             Payable from General Obligation Bonds

6             Priority 1                                                 $ 1,300,000

7             Priority 5                                                 $ 1,300,000

8             Total                                                      $ 2,600,000

9   36/P21 PORT OF SOUTH LOUISIANA

10  (576953) Globalplex New Guard Station, Planning and Construction

11            (St. John the Baptist)

12            Payable from General Obligation Bonds

13            Priority 1                                                 $ 1,580,000

14  (576954) Globalplex Rail Connector, Planning and Construction

15            (St. John the Baptist)

16            Payable from General Obligation Bonds

17            Priority 5                                                 $ 3,640,000

18  (576955) Globalplex Terminal Building #71 and Other Globalplex

19            Terminal Building Upgrades, Planning and Construction

20            (St. John the Baptist)

21            Payable from General Obligation Bonds

22            Priority 1                                                 $  567,361

23            Priority 5                                                 $ 1,000,000

24            Total                                                      $ 1,567,361

25  (576956) Globalplex Warehouse and Conveyance System, Planning

26            and Construction

27            (St. John the Baptist)

28            Payable from General Obligation Bonds

29            Priority 5                                                 $ 24,385,000

30  (576960) Globalplex Roadway Improvements: Parking Area near

31            Building 60, Planning and Construction

32            (St. John the Baptist)

33            Payable from General Obligation Bonds

34            Priority 1                                                 $  743,152

35  (576962) Globalplex Dock Access Bridge and Equipment

36            Replacement/Repair, Planning and Construction

37            (St. John the Baptist)

38            Payable from General Obligation Bonds

39            Priority 1                                                 $ 1,012,032

40  (576963) Globalplex Road Improvements and Drainage Between

41            Globalplex Buildings 71 and 76, Planning and Construction

42            (St. John the Baptist)

43            Payable from General Obligation Bonds

44            Priority 1                                                 $  437,188

45  (578881) Globalplex Roadway Improvements at Parking Area Near

46            Building 2, Planning and Construction

47            (St. John the Baptist)

48            Payable from General Obligation Bonds

49            Priority 1                                                 $ 2,865,000

                                      Page 57 of 174
    HB NO. 2                                                                ENROLLED

1   36/P23 TERREBONNE PORT COMMISSION

2   (577002) Maritime Manufacturing Facility, Planning and Construction

3             (Terrebonne)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $ 18,000,000

6             Priority 5                                                 $ 26,000,000

7             Total                                                      $ 44,000,000

8   (577003) Slip Dredging, Houma Navigation Canal Dredging,

9             Planning and Construction

10            (Terrebonne)

11            Payable from General Obligation Bonds

12            Priority 5                                                 $ 2,000,000

13  36/P26 PORT OF LAKE CHARLES

14  (576909) Berths 4, 5, and 6 Wharf and Shed Reconstruction at City

15            Docks, Planning and Construction

16            (Calcasieu)

17            Payable from General Obligation Bonds

18            Priority 1                                                 $ 17,641,023

19            Priority 5                                                 $ 33,900,000

20            Total                                                      $ 51,541,023

21  (578879) Two Mobile Harbor Cranes for BT-1, Planning and

22            Construction

23            (Calcasieu)

24            Payable from General Obligation Bonds

25            Priority 1                                                 $  574,501

26  36/P33 SOUTH TANGIPAHOA PARISH PORT

27  (577650) Building 2 Barge Dock Restoration and Improvements,

28            Planning and Construction

29            (Tangipahoa)

30            Payable from General Obligation Bonds

31            Priority 5                                                 $ 1,000,000

32  36/P35 MERMENTAU RIVER HARBOR AND TERMINAL

33            DISTRICT

34  (578877) Slip Improvements, Planning and Construction

35            (Acadia)

36            Payable from General Obligation Bonds

37            Priority 1                                                 $  57,852

38  36/P36 CENTRAL LOUISIANA REGIONAL PORT

39  (577513) CLRP High Water Hardstand and Access Road, Planning

40            and Construction

41            (Rapides)

42            Payable from General Obligation Bonds

43            Priority 1                                                 $  97,989

44            Priority 5                                                 $ 1,800,000

45            Payable from the Capital Outlay Savings Fund               $  800,000

46            Total                                                      $ 2,697,989

                                Page 58 of 174
    HB NO. 2                                                              ENROLLED

1   36/P41 JEFFERSON PARISH ECONOMIC DEVELOPMENT

2             AND PORT DISTRICT

3   (577350) Restore Rail Connection and Crossing to Avondale Marine,

4             Planning and Construction

5             (Jefferson)

6             Payable from General Obligation Bonds

7             Priority 1                                               $ 1,100,000

8             Priority 5                                               $ 2,700,000

9             Total                                                    $ 3,800,000

10  36/P43 COLUMBIA PORT COMMISSION

11  (576691) Railroad Spur, Planning and Construction

12            (Caldwell)

13            Payable from General Obligation Bonds

14            Priority 1                                               $  94,380

15            Priority 5                                               $ 1,841,000

16            Total                                                    $ 1,935,380

17  36/P46 VINTON HARBOR AND TERMINAL DISTRICT

18  (577280) Barge Loading/Unloading Berth at Vinton Harbor and

19            Terminal District, Planning and Construction

20            (Calcasieu)

21            Payable from General Obligation Bonds

22            Priority 5                                               $ 1,980,637

23                         MISCELLANEOUS NON-STATE

24  50/J01 ACADIA PARISH

25  (577693) Old Spanish Trail Roadway Improvements To Provide For

26            Freight Traffic Bypass of Dangerous Railroad Crossing,

27            Planning and Construction

28            (Acadia)

29            Payable from General Obligation Bonds

30            Priority 1                                               $  684,921

31  (577694) Ye Olde Country Road and Muskrat Road Improvements,

32            Planning and Construction

33            (Acadia)

34            Payable from General Obligation Bonds

35            Priority 1                                               $  210,000

36            Priority 5                                               $ 1,860,000

37            Total                                                    $ 2,070,000

38  50/J02 ALLEN PARISH

39  (577230) Road Rehabilitation, Planning and Construction

40            (Allen)

41            Payable from General Obligation Bonds

42            Priority 5                                               $ 1,550,000

43  (577231) Bridge Improvements, Planning and Construction

44            (Allen)

45            Payable from General Obligation Bonds

46            Priority 5                                               $ 3,050,000

                           Page 59 of 174
    HB NO. 2                                                                ENROLLED

1   50/J03 ASCENSION PARISH

2   (577391) Early Childhood Education Project, Planning and

3             Construction

4             (Ascension)

5             Payable from General Obligation Bonds

6             Priority 1                                                 $ 2,700,000

7   (577395) LA 3127 Connector from Hwy. 70 to LA 1, Planning and

8             Construction

9             (Ascension)

10            Payable from General Obligation Bonds

11            Priority 5                                                 $ 9,500,000

12            Payable from State General Fund (Direct) Non-Recurring

13            Revenues                                                   $ 2,500,000

14            Total                                                      $ 12,000,000

15  (578553) LA 431 at LA 931 Roundabout, Planning and Construction

16            (Ascension)

17            Payable from General Obligation Bonds

18            Priority 5                                                 $ 1,000,000

19            Payable from the Capital Outlay Savings Fund               $  400,000

20            Total                                                      $ 1,400,000

21  (578556) LA 44 at LA 933/Parker Road Roundabout, Planning and

22            Construction

23            (Ascension)

24            Payable from General Obligation Bonds

25            Priority 5                                                 $ 1,650,000

26            Payable from the Capital Outlay Savings Fund               $  500,000

27            Total                                                      $ 2,150,000

28  (578558) Upgrades and New Water Treatment Plant, Planning and

29            Construction

30            (Ascension)

31            Payable from General Obligation Bonds

32            Priority 5                                                 $ 14,825,000

33            Payable from State General Fund (Direct) Non-Recurring

34            Revenues                                                   $ 1,150,000

35            Total                                                      $ 15,975,000

36  (578562) LA 73 at LA 30 Roundabout, Planning

37            and Construction

38            (Ascension)

39            Payable from General Obligation Bonds

40            Priority 5                                                 $ 4,250,000

41  (578704) LA 73 at LA 429 (Cornerview Road), Planning

42            and Construction

43            (Ascension)

44            Payable from the balance of reappropriated State General

45            Fund (Direct) previously allocated under the authority of

46            Act 5 of 2024 for Ascension Parish, LA 73 at LA 30

47            Roundabout, Planning and Construction (Ascension)          $ 3,750,000

                                Page 60 of 174
    HB NO. 2                                                          ENROLLED

1   50/J04 ASSUMPTION PARISH

2   (577674) Plattenville Drainage Improvements, Planning and

3             Construction

4             (Assumption)

5             Payable from General Obligation Bonds

6             Priority 1                                           $  13,867

7   (577675) Assumption Parish Pumps and Drainage, Planning and

8             Construction

9             (Assumption)

10            Payable from General Obligation Bonds

11            Priority 1                                           $  467,500

12  50/J05 AVOYELLES PARISH

13  (578017) Parishwide Roadway Improvements, Planning and

14            Construction

15            (Avoyelles)

16            Payable from General Obligation Bonds

17            Priority 1                                           $ 1,000,000
                                                                   $ 1,000,000
18            Priority 5                                           $ 2,000,000

19            Total

20  50/J06 BEAUREGARD PARISH

21  (578112) Camp Edgewood Road Improvements Phase 2, Planning

22            and Construction

23            (Beauregard)

24            Payable from General Obligation Bonds

25            Priority 5                                           $ 1,000,000

26            Payable from the Capital Outlay Savings Fund         $  290,000

27            Total                                                $ 1,290,000

28  (578113) Greentown Road Improvements Phase 2,

29            Planning and Construction

30            (Beauregard)

31            Payable from General Obligation Bonds

32            Priority 2                                           $  562,000

33  (578114) Lumus Road Rehabilitation, Planning and Construction

34            (Beauregard)

35            Payable from General Obligation Bonds

36            Priority 5                                           $  562,500

37  (578115) H.B. Hickman Road Rehabilitation,

38            Planning and Construction

39            (Beauregard)

40            Payable from General Obligation Bonds

41            Priority 5                                           $  765,000

42  (578116) Hoy Road Rehabilitation, Planning and Construction

43            (Beauregard)

44            Payable from General Obligation Bonds

45            Priority 5                                           $  562,500

46  (578867) Longview Road Improvements, Beauregard Parish Police

47            Jury, Planning and Construction

48            (Beauregard)

49            Payable from General Obligation Bonds

50            Priority 1                                           $  360,000

                                Page 61 of 174
    HB NO. 2                                                                ENROLLED

1   50/J07 BIENVILLE PARISH

2   (577716) Ridge Road Improvements, Planning and Construction

3             (Bienville)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $ 1,200,000

6             Priority 5                                                 $ 6,250,000

7             Total                                                      $ 7,450,000

8   50/J08 BOSSIER PARISH

9   (578172) Improvements to LA Highway 3 (Benton Road) and I-220

10            Interchange, Planning and Construction

11            (Bossier)

12            Payable from General Obligation Bonds

13            Priority 1                                                 $ 2,000,000

14            Priority 5                                                 $ 4,700,000

15            Payable from the Capital Outlay Savings Fund               $ 1,000,000

16            Total                                                      $ 7,700,000

17  (578174) Improvements to Highway 157, LA Highway 3227 to US

18            Highway 80, Planning and Construction

19            (Bossier)

20            Payable from General Obligation Bonds

21            Priority 1                                                 $ 5,000,000

22            Priority 5                                                 $ 5,200,000

23            Total                                                      $ 10,200,000

24  (578175) US Hwy. 71 Four Lane Extension/Colleen Drive

25            Improvements, Planning and Construction

26            (Bossier)

27            Payable from General Obligation Bonds

28            Priority 5                                                 $ 4,600,000

29            Payable from the balance of State General Fund (Direct)

30            previously allocated under the authority of Act 5 of 2024

31            for the Division of Administration, Statewide Roofing

32            Asset Management Program and Waterproofing, Related

33            Repairs and Equipment Replacement Program

34            (Statewide)                                                $ 2,000,000

35            Payable from the Capital Outlay Savings Fund               $  400,000

36            Total                                                      $ 7,000,000

37  50/J10 CALCASIEU PARISH

38  (577743) Calcasieu Police Jury Gravity Sewer Trunk Mains and

39            Pumping Station South Ward 3 and South Ward 4,

40            Planning and Construction

41            (Calcasieu)

42            Payable from General Obligation Bonds

43            Priority 1                                                 $ 7,598,116

44            Priority 5                                                 $ 4,500,000

45            Total                                                      $ 12,098,116

46  50/J11 CALDWELL PARISH

47  (578129) Swim Lake Road, Planning and Construction

48            (Caldwell)

49            Payable from General Obligation Bonds

50            Priority 1                                                 $  426,000

                           Page 62 of 174
    HB NO. 2                                                                ENROLLED

1   (578131) Wiles Road and Kountry Korner Road, Planning and

2             Construction

3             (Caldwell)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $  477,500

6   50/J12 CAMERON PARISH

7   (577772) Parishwide Road Rehabilitation, Planning and Construction

8             (Cameron)

9             Payable from General Obligation Bonds

10            Priority 1                                                 $  500,000

11            Priority 5                                                 $ 5,500,000

12            Payable from the Capital Outlay Savings Fund               $  300,000

13            Total                                                      $ 6,300,000

14  50/J13 CATAHOULA PARISH

15  (579012) Catahoula Parish Roadway Improvements, Planning and

16            Construction

17            (Catahoula)

18            Payable from General Obligation Bonds

19            Priority 5                                                 $ 2,000,000

20            Payable from the Capital Outlay Savings Fund               $ 1,000,000

21            Total                                                      $ 3,000,000

22  Pending approval of the capital outlay budget request pursuant to the provisions of R.S.

23  39:112.

24  50/J15 CONCORDIA PARISH

25  (577252) Roadway Reconstruction, Doty Road, Planning and

26            Construction

27            (Concordia)

28            Payable from State General Fund (Direct) Non-Recurring

29            Revenues                                                   $ 3,000,000

30  50/J16 DESOTO PARISH

31  (577006) DeSoto Parish Police Jury Five (5) Year Capital Road Plan,

32            Planning and Construction

33            (DeSoto)

34            Payable from General Obligation Bonds

35            Priority 5                                                 $ 30,000,000

36  50/J17 EAST BATON ROUGE PARISH

37  (577934) East Baton Rouge Parish Flood Risk Reduction

38            Project- Expand, Repair, and Modify Drainage System

39            throughout East Baton Rouge Parish

40            (East Baton Rouge)

41            Payable from General Obligation Bonds

42            Priority 1                                                 $ 8,391,389

43            Priority 5                                                 $ 22,000,000

44            Total                                                      $ 30,391,389

                                  Page 63 of 174
    HB NO. 2                                                                ENROLLED

1   50/J18 EAST CARROLL PARISH

2   (578614) East Carroll Parish Courthouse Assessment and Restoration,

3             Planning and Construction

4             (East Carroll)

5             Payable from General Obligation Bonds

6             Priority 5                                                 $ 9,600,000

7             Payable from the Capital Outlay Savings Fund               $  500,000

8             Total                                                      $ 10,100,000

9   (578868) Spillway Structure Repairs for Lake Providence Lake and

10            Cleaning of Outfall Canal from the Lake Downstream,

11            Planning and Construction

12            (East Carroll)

13            Payable from General Obligation Bonds

14            Priority 1                                                 $  100,000

15            Priority 5                                                 $  300,000

16            Total                                                      $  400,000

17  50/J21 FRANKLIN PARISH

18  (577641) Franklin Parish Activity Center, Planning and Construction

19            (Franklin)

20            Payable from General Obligation Bonds

21            Priority 1                                                 $  945,004

22            Priority 5                                                 $ 1,800,000

23            Total                                                      $ 2,745,004

24  (577999) Riley Road Improvements, Planning and Construction

25            (Franklin)

26            Payable from General Obligation Bonds

27            Priority 1                                                 $ 1,000,000

28  (578000) Erosion Control and Bank Stabilization at Big Creek Bridge

29            and Looney Canal, Planning and Construction

30            (Franklin)

31            Payable from State General Fund (Direct) Non-Recurring

32            Revenues                                                   $  600,000

33  (578756) Franklin Medical Center Improvements, Planning and

34            Construction

35            (Franklin)

36            Payable from State General Fund (Direct) Non-Recurring

37            Revenues                                                   $  500,000

38  50/J22 GRANT PARISH

39  (577870) Courthouse Renovations - Phase I, Planning and

40            Construction

41            (Grant)

42            Payable from State General Fund (Direct) Non-Recurring

43            Revenues                                                   $  63,000

44  (577871) Landfill Road Improvements, Planning and Construction

45            (Grant)

46            Payable from General Obligation Bonds

47            Priority 1                                                 $  565,000

                              Page 64 of 174
    HB NO. 2                                                              ENROLLED

1   50/J23 IBERIA PARISH

2   (576914) Sewer Collection System Improvements

3             (Iberia)

4             Payable from General Obligation Bonds

5             Priority 1                                               $ 1,500,000

6             Priority 2                                               $ 1,000,000

7             Priority 5                                               $ 9,400,000

8             Payable from State General Fund (Direct) Non-Recurring

9             Revenues                                                 $ 1,500,000

10            Payable from the Capital Outlay Savings Fund             $  500,000

11            Total                                                    $ 13,900,000

12  (576926) Iberia Parish - Sewer Treatment Plant, Planning and

13            Construction

14            (Iberia)

15            Payable from General Obligation Bonds

16            Priority 1                                               $ 1,000,000
                                                                       $ 9,000,000
17            Priority 5                                               $ 10,000,000

18            Total

19  (576932) Parish Jail Improvements, Planning and Construction

20            (Iberia)

21            Payable from General Obligation Bonds

22            Priority 1                                               $  840,000

23  (578858) Courthouse Elevators, Planning and Construction

24            (Iberia)

25            Payable from General Obligation Bonds

26            Priority 1                                               $  171,900

27  50/J24 IBERVILLE PARISH

28  (576575) Choctaw Bayou Drainage and Ecological Improvements,

29            Planning and Construction

30            (Iberville)

31            Payable from General Obligation Bonds

32            Priority 5                                               $ 1,650,000

33  (577831) Water Line Improvements Highway 69 - Upgrade

34            2" Lines to 4" Lines and Add Customers,

35            Planning and Construction

36            (Iberville)

37            Payable from the Capital Outlay Savings Fund             $  600,000

38  (577905) Statewide Radio System Tower - Bayou Sorrel/Bayou Pigeon

39            Fire Department, Planning and Construction

40            (Iberville)

41            Payable from the Capital Outlay Savings Fund             $  500,000

42  50/J25 JACKSON PARISH

43  (578857) Lakeshore Drive Rehabilitation and Improvements,

44            Planning and Construction

45            (Jackson)

46            Payable from General Obligation Bonds

47            Priority 1                                               $ 1,455,903

                            Page 65 of 174
    HB NO. 2                                                                ENROLLED

1   50/J26 JEFFERSON PARISH

2   (576424) 11th Street Roadway Replacement and Upgrade of

3             Subsurface Drainage System between Queens and

4             Manhattan Boulevard, Planning and Construction

5             (Jefferson)

6             Payable from General Obligation Bonds

7             Priority 1                                                 $  137,656

8             Priority 5                                                 $ 9,175,000

9             Total                                                      $ 9,312,656

10  (576425) 4th Street Shared-Use Path (Barataria Blvd. to Gretna City

11            Limits), Planning and Construction

12            (Jefferson)

13            Payable from General Obligation Bonds

14            Priority 1                                                 $  225,000

15            Priority 5                                                 $ 4,146,600

16            Total                                                      $ 4,371,600

17  (576426) Airline Drive (US 61) at 17th Street Canal Drainage

18            Crossing and Railroad Bridge Replacement

19            (Jefferson)

20            Payable from General Obligation Bonds

21            Priority 1                                                 $ 2,000,000
                                                                         $ 14,090,000
22            Priority 5                                                 $ 16,090,000

23            Total

24  (576427) Bainbridge Canal Closure from Veterans Boulevard to

25            Terminal Drive, Planning and Construction

26            (Jefferson)

27            Payable from General Obligation Bonds

28            Priority 1                                                 $  516,194

29            Priority 2                                                 $ 2,000,000

30            Priority 5                                                 $ 11,800,000

31            Total                                                      $ 14,316,194

32  (576428) Barataria Blvd. (LA 45) Drainage Improvements (Merlin

33            Lane to Pritchard Road), Planning and Construction

34            (Jefferson)

35            Payable from General Obligation Bonds

36            Priority 5                                                 $ 6,500,000

37  (576432) Bonnabel Canal Bank Stabilization (West Side) - Veterans

38            Blvd. to West Esplanade, Planning and Construction

39            (Jefferson)

40            Payable from General Obligation Bonds

41            Priority 1                                                 $ 2,538,507

42            Priority 5                                                 $ 4,700,000

43            Total                                                      $ 7,238,507

44  (576434) Bucktown Harbor Boardwalk and Kayak Launch, Planning

45            and Construction

46            (Jefferson)

47            Payable from General Obligation Bonds

48            Priority 5                                                 $ 1,575,000

49  (576436) Bucktown Harbor Multi-Purpose Pavillion, Planning and

50            Construction

51            (Jefferson)

52            Payable from General Obligation Bonds

53            Priority 1                                                 $ 3,500,000

                                Page 66 of 174
    HB NO. 2                                                             ENROLLED

1   (576443) East Bank Backup Generators East: Sewer Lift Station

2             Backup Generators (Clearview at W. Napoleon, Cleary at

3             W. Napoleon, Houma at W. Napoleon and Galleria Sewer

4             Station), Planning and Construction

5             (Jefferson)

6             Payable from General Obligation Bonds

7             Priority 1                                              $ 1,750,000

8   (576444) East Bank Backup Generators West: Sewer Lift Station

9             Backup Generators (Camp Plauche, Transcontinental at

10            West Metairie, and Transcontinental at Vineland)

11            (Jefferson)

12            Payable from General Obligation Bonds

13            Priority 5                                              $ 2,000,000

14  (576452) Gretna Government Complex Parking Lot, Planning and

15            Construction

16            (Jefferson)

17            Payable from General Obligation Bonds

18            Priority 1                                              $ 2,429,137

19            Priority 5                                              $ 7,671,600

20            Total                                                   $ 10,100,737

21  (576453) Hickory Avenue (LA 3154) Rehabilitation (River Road to

22            10th Street), Planning and Construction

23            (Jefferson)

24            Payable from General Obligation Bonds

25            Priority 1                                              $  600,000

26            Priority 5                                              $ 6,270,000

27            Total                                                   $ 6,870,000

28  (576454) Hope Haven Natatorium, Planning and Construction

29            (Jefferson)

30            Payable from General Obligation Bonds

31            Priority 5                                              $ 15,000,000

32  (576455) Huey P. Long Bridge Lighting

33            (Jefferson)

34            Payable from General Obligation Bonds

35            Priority 5                                              $ 4,075,000

36  (576456) Jefferson Park Sport Field Renovation, Planning and

37            Construction

38            (Jefferson)

39            Payable from General Obligation Bonds

40            Priority 1                                              $ 2,000,000
                                                                      $ 4,840,000
41            Priority 5                                              $ 6,840,000

42            Total

43  (576472) Metairie Road Drainage Improvements (Causeway Blvd.

44            to Focis St.), Planning and Construction

45            (Jefferson)

46            Payable from General Obligation Bonds

47            Priority 1                                              $ 7,100,000

48            Priority 5                                              $ 6,460,000

49            Total                                                   $ 13,560,000

                            Page 67 of 174
    HB NO. 2                                                                ENROLLED

1   (576474) New Access Road in the Churchill Technology and

2             Business Park for Delgado's Advanced Manufacturing

3             and River City Campus, Planning and Construction

4             (Jefferson)

5             Payable from General Obligation Bonds

6             Priority 1                                                 $ 1,550,000

7   (576478) Preservation and Restoration of Historic Structures for

8             Hope Haven/Madonna Manor Campus, Planning and

9             Construction

10            (Jefferson)

11            Payable from General Obligation Bonds

12            Priority 1                                                 $ 5,628,748

13            Priority 5                                                 $ 2,000,000

14            Payable from the Capital Outlay Savings Fund               $  500,000

15            Total                                                      $ 8,128,748

16  (576484) Sewer Lift Station Backup Generators - North, Planning and

17            Construction

18            (Jefferson)

19            Payable from General Obligation Bonds

20            Priority 1                                                 $  26,921

21  (576486) Shrewsbury Road at Jefferson Highway Culvert

22            Replacement, Planning and Construction

23            (Jefferson)

24            Payable from General Obligation Bonds

25            Priority 5                                                 $ 2,000,000

26  (576493) West Esplanade Pump Station, Planning and Construction

27            (Jefferson)

28            Payable from General Obligation Bonds

29            Priority 5                                                 $ 3,700,000

30  (576495) Woodlake Estates Drainage Improvements, Planning and

31            Construction

32            (Jefferson)

33            Payable from General Obligation Bonds

34            Priority 1                                                 $  356,750

35            Priority 5                                                 $ 2,000,000

36            Total                                                      $ 2,356,750

37  (576496) Woodland West Drainage Improvements, Planning and

38            Construction

39            (Jefferson)

40            Payable from General Obligation Bonds

41            Priority 1                                                 $  344,655

42            Priority 5                                                 $ 1,000,000

43            Total                                                      $ 1,344,655

44  (576498) Woodmere Playground Improvements, Planning and

45            Construction

46            (Jefferson)

47            Payable from General Obligation Bonds

48            Priority 1                                                 $ 2,150,962
                                                                         $ 1,000,000
49            Priority 5                                                 $ 3,150,962

50            Total

                            Page 68 of 174
    HB NO. 2                                                                ENROLLED

1   (576500) Woodmere Youth Center, Planning and Construction

2             (Jefferson)

3             Payable from General Obligation Bonds

4             Priority 1                                                 $  50,500

5   (576501) Asian American Cultural and Service Center, Planning and

6             Construction

7             (Jefferson)

8             Payable from General Obligation Bonds

9             Priority 5                                                 $ 3,550,000

10  (578569) Estelle Recreation Complex, Planning

11            and Construction

12            (Jefferson)

13            Payable from the balance of State General Fund (Direct)

14            previously allocated under the authority of Act 465 of

15            2023 for Jefferson Parish, Vietnamese American Cultural

16            and Service Center, Planning and Construction

17            (Jefferson)                                                $  400,000

18            Payable from the balance of State General Fund (Direct)

19            previously allocated under the authority of Act 5 of 2024

20            for the Division of Administration, Statewide Roofing

21            Asset Management Program and Waterproofing, Related

22            Repairs and Equipment Replacement Program

23            (Statewide)                                                $  600,000

24            Total                                                      $ 1,000,000

25  (578582) Fat City Leisure Park and Annex

26            (Jefferson)

27            Payable from State General Fund (Direct) Non-Recurring

28            Revenues                                                   $ 3,000,000

29            Payable from the Capital Outlay Savings Fund               $ 2,375,000

30            Total                                                      $ 5,375,000

31  (578800) PARD Playground Field Improvements,

32            Planning and Construction

33            (Jefferson)

34            Payable from the balance of State General Fund (Direct)

35            previously allocated under the authority of Act 465 of

36            2023 for Jefferson Parish, Vietnamese American Cultural

37            and Service Center, Planning and Construction

38            (Jefferson)                                                $  600,000

39  (578854) Brown Avenue Canal Improvements between the Westbank

40            Expressway and Harold Street, Planning and Construction

41            (Jefferson)

42            Payable from General Obligation Bonds

43            Priority 1                                                 $ 1,802,898

44  50/J27 JEFFERSON DAVIS PARISH

45  (578035) Parish Wide Road and Bridge Improvement Project,

46            Planning and Construction

47            Payable from General Obligation Bonds

48            Priority 2                                                 $  380,000

49            Priority 5                                                 $ 3,445,000

50            Total                                                      $ 3,825,000

                                Page 69 of 174
    HB NO. 2                                                            ENROLLED

1   (578037) Wastewater Collection, Transfer and Treatment Systems,

2             Planning and Construction

3             (Jefferson Davis)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 2,000,000

6   50/J28 LAFAYETTE PARISH

7   (576522) E Broussard Roundabout, Planning and Construction

8             (Lafayette)

9             Payable from General Obligation Bonds

10            Priority 5                                                $ 3,000,000

11  (576523) Cue Road Extension, Planning and Construction

12            (Lafayette)

13            Payable from General Obligation Bonds

14            Priority 5                                                $ 4,000,000

15  (576526) Parish Road Overlay, Planning and Construction

16            (Lafayette)

17            Payable from General Obligation Bonds

18            Priority 5                                                $ 7,000,000

19  (576527) Rue Du Belier Widening, Planning and Construction

20            (Lafayette)

21            Payable from General Obligation Bonds

22            Priority 1                                                $ 2,000,000
                                                                        $ 5,000,000
23            Priority 5                                                $ 7,000,000

24            Total

25  (576528) Parish Government Complex, Jail, New Design, Planning

26            and Construction

27            (Lafayette)

28            Payable from General Obligation Bonds

29            Priority 5                                                $ 35,000,000

30  (576533) State Interchange Improvements, Planning and Construction

31            (Lafayette)

32            Payable from General Obligation Bonds

33            Priority 5                                                $ 11,325,000

34  (576534) Bayou Vermilion Flood Control, Planning and Construction

35            (Lafayette)

36            Payable from General Obligation Bonds

37            Priority 1                                                $ 9,492,500

38            Priority 5                                                $ 22,000,000

39            Total                                                     $ 31,492,500

40  (576535) Parish Government Complex, Parish Courthouse, Planning

41            and Construction

42            (Lafayette)

43            Payable from General Obligation Bonds

44            Priority 1                                                $ 1,149,500

45  (576538) Ingress and Egress Interchange Improvements, Planning

46            and Construction

47            (Lafayette)

48            Payable from General Obligation Bonds

49            Priority 5                                                $ 10,000,000

                                 Page 70 of 174
    HB NO. 2                                                            ENROLLED

1   (576539) Heymann Park Improvements Project, Planning and

2             Construction

3             (Lafayette)

4             Payable from General Obligation Bonds

5             Priority 1                                             $ 1,925,000
                                                                     $ 5,700,000
6             Priority 5                                             $ 1,000,000
                                                                     $ 8,625,000
7             Payable from the Capital Outlay Savings Fund

8             Total

9   (576540) University Avenue Corridor Improvements, Planning,

10            Construction and Acquisition

11            (Lafayette)

12            Payable from General Obligation Bonds

13            Priority 1                                             $ 13,000,000

14  (578855) Isaac Verot Coulee - Main Channel Hardening, Planning

15            and Construction

16            (Lafayette)

17            Payable from General Obligation Bonds

18            Priority 5                                             $ 11,000,000

19  50/J29 LAFOURCHE PARISH

20  (577922) Hero's Park Recreation Center and Head Start in

21            Thibodaux, Planning and Construction

22            (Lafourche)

23            Payable from General Obligation Bonds

24            Priority 1                                             $  500,000

25            Priority 5                                             $ 3,700,000

26            Payable from the Capital Outlay Savings Fund           $  300,000

27            Total                                                  $ 4,500,000

28  (578159) Butch Hill Pump Station Replacement, Planning and

29            Construction

30            (Lafourche)

31            Payable from General Obligation Bonds

32            Priority 1                                             $  646,000

33            Priority 5                                             $ 17,300,000

34            Total                                                  $ 17,946,000

35  (578856) South Lafourche Airport Corridor Project

36            (Lafourche)

37            Payable from General Obligation Bonds

38            Priority 1                                             $ 5,281,009

39  50/J31 LINCOLN PARISH

40  (578208) Bridge Replacements on Mitchell and Shady Grove Roads,

41            Planning and Construction

42            (Lincoln)

43            Payable from General Obligation Bonds

44            Priority 1                                             $  380,000

45  50/J32 LIVINGSTON PARISH

46  (577438) Juban Road North Extension between US 190 (Florida

47            Blvd.) and LA 1026 (Lockhart Road), Planning and

48            Construction

49            (Livingston)

50            Payable from General Obligation Bonds

51            Priority 5                                             $ 6,005,000

                                Page 71 of 174
    HB NO. 2                                                             ENROLLED

1   (577883) Amite River Boat Launch, Planning and Construction

2             (Livingston)

3             Payable from General Obligation Bonds

4             Priority 5                                              $ 6,700,000

5             Payable from the Capital Outlay Savings Fund            $  700,000

6             Total                                                   $ 7,400,000

7   (578160) Cook Road Extension Economic Development Corridor

8             (Pete's Highway Frontage Road)

9             (Livingston)

10            Payable from General Obligation Bonds

11            Priority 1                                              $ 1,073,907

12  (578979) Livingston Parish Emergency Response and

13            Evacuation Center, Planning and Construction

14            (Livingston)

15            Payable from General Obligation Bonds

16            Priority 1                                              $ 2,889,899
                                                                      $ 2,000,000
17            Priority 2                                              $ 41,920,000
                                                                      $ 46,809,899
18            Priority 5

19            Total

20  50/J34 MOREHOUSE PARISH

21  (577801) Public Works Center, Planning and Construction

22            (Morehouse)

23            Payable from General Obligation Bonds

24            Priority 1                                              $  128,299

25  50/J35 NATCHITOCHES PARISH

26  (577436) Courthouse Security Improvements, Planning and

27            Construction

28            (Natchitoches)

29            Payable from General Obligation Bonds

30            Priority 1                                              $  391,522

31  (578210) Resurfacing of Goldonna Road, Planning and Construction

32            (Natchitoches)

33            Payable from General Obligation Bonds

34            Priority 1                                              $ 3,560,000

35  50/J37 OUACHITA PARISH

36  (577938) Force Main Replacement for Lift Station N, Planning,

37            Right-of-Way, and Construction

38            (Ouachita)

39            Payable from General Obligation Bonds

40            Priority 1                                              $ 1,000,000

41  (577939) Steep Bayou/Tupawek Bayou Sewer, Planning,

42            Construction, and Right-of-Way Acquisition

43            (Ouachita)

44            Payable from General Obligation Bonds

45            Priority 1                                              $  354,137

46            Priority 5                                              $ 3,580,000

47            Total                                                   $ 3,934,137

                              Page 72 of 174
    HB NO. 2                                                             ENROLLED

1   (577944) Bayou Mouchoir Drainage Improvements

2             (Ouachita)

3             Payable from General Obligation Bonds

4             Priority 1                                              $  477,500

5   (577945) Cheniere Lake Area 1 Improvements, Planning and

6             Construction

7             (Ouachita)

8             Payable from General Obligation Bonds

9             Priority 1                                              $  846,430

10  (578143) Millhaven Estates Drainage and Roadway

11            Improvements, Planning, Right-of-Way,

12            and Construction

13            (Ouachita)

14            Payable from General Obligation Bonds

15            Priority 2                                              $  845,000

16            Priority 5                                              $ 1,265,000

17            Total                                                   $ 2,110,000

18  50/J38 PLAQUEMINES PARISH

19  (577452) Water Tower Repairs, Planning and Construction

20            (Plaquemines)

21            Payable from General Obligation Bonds

22            Priority 1                                              $  250,000

23            Priority 5                                              $ 6,000,000

24            Payable from the Capital Outlay Savings Fund            $  450,000

25            Total                                                   $ 6,700,000

26  (577453) Renovation of Building on Government Complex

27            to house Clerk of Court, Assessor, and Judges Offices,

28            Planning and Construction

29            (Plaquemines)

30            Payable from General Obligation Bonds

31            Priority 5                                              $ 7,000,000

32            Payable from the Capital Outlay Savings Fund            $ 1,000,000

33            Total                                                   $ 8,000,000

34  (577454) Belle Chasse Water Treatment Facility Increase Capacity

35            Project, Planning and Construction

36            (Plaquemines)

37            Payable from General Obligation Bonds

38            Priority 1                                              $  250,000

39            Priority 5                                              $ 21,950,000

40            Total                                                   $ 22,200,000

41  (577457) Empire Bridge Lighting, Planning and Construction

42            (Plaquemines)

43            Payable from General Obligation Bonds

44            Priority 5                                              $ 1,680,000

45  (577586) Plaquemines Parish Training Center, Planning and

46            Construction

47            (Plaquemines)

48            Payable from General Obligation Bonds

49            Priority 5                                              $ 23,000,000

                                Page 73 of 174
    HB NO. 2                                                               ENROLLED

1   (577634) Hwy. 11 Sewer Collection System, Planning and

2             Construction

3             (Plaquemines)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 3,600,000

6   (577923) Redesign and Rebuilding of the Nov-13 Flood Gate

7             Project, Planning and Construction

8             (Plaquemines)

9             Payable from General Obligation Bonds

10            Priority 5                                                $ 1,800,000

11  (578792) Plaquemines Parish Public Safety Answering Point (PSAP),

12            Construction and Equipment

13            (Plaquemines)

14            Payable from General Obligation Bonds

15            Priority 5                                                $ 2,000,000

16            Payable from the Capital Outlay Savings Fund              $ 2,000,000

17            Total                                                     $ 4,000,000

18  50/J39 POINTE COUPEE PARISH

19  (577605) Courthouse Restoration - Phase 2, Planning and

20            Construction

21            (Pointe Coupee)

22            Payable from General Obligation Bonds

23            Priority 1                                                $  82,689

24  (577970) Portage Canal Drainage Project, Planning and Construction

25            (Pointe Coupee)

26            Payable from General Obligation Bonds

27            Priority 5                                                $ 3,000,000

28            Payable from the Capital Outlay Savings Fund              $  250,000

29            Total                                                     $ 3,250,000

30  (577971) Roy O Martin/Crestwood Subdivision, Planning and

31            Construction

32            (Pointe Coupee)

33            Payable from General Obligation Bonds

34            Priority 5                                                $  900,000

35  (577974) Watershed Drainage Improvements Bayou Grosse Tete,

36            Bayou Cholpe, Bayou Choctaw, False River Outfall

37            Channel, and Johnson Bayou, Planning and Construction

38            (Pointe Coupee)

39            Payable from General Obligation Bonds

40            Priority 1                                                $ 1,843,620

41  (578020) Electronic Water and Gas Meter System,

42            Planning and Construction

43            (Pointe Coupee)

44            Payable from General Obligation Bonds

45            Priority 2                                                $  700,000

46            Priority 5                                                $ 6,300,000

47            Total                                                     $ 7,000,000

                               Page 74 of 174
    HB NO. 2                                                           ENROLLED

1   (578496) False River Ecosystem Restoration Project, Including

2             Bulkhead Replacement, Planning and Construction

3             (Pointe Coupee)

4             Payable from General Obligation Bonds

5             Priority 1                                            $  1,000

6             Priority 5                                            $ 5,250,000

7             Total                                                 $ 5,251,000

8   50/J40 RAPIDES PARISH

9   (578042) Hickory Hill Road Overlay, Planning and

10            Construction

11            (Rapides)

12            Payable from General Obligation Bonds

13            Priority 5                                            $  805,000

14  (578043) Gunter Road/Barron Chapel Road Street Improvements,

15            Planning and Construction

16            (Rapides)

17            Payable from General Obligation Bonds

18            Priority 1                                            $  441,639

19  (578044) Philadelphia Road Street Improvements, Planning and

20            Construction

21            (Rapides)

22            Payable from General Obligation Bonds

23            Priority 1                                            $  500,000

24  (578379) Tioga Road Overlay, Planning and Construction

25            (Rapides)

26            Payable from General Obligation Bonds

27            Priority 5                                            $  630,000

28  (578382) New Fire Station at LSU Alexandria Serving Rapides

29            Parish - Fire District 18, Planning and Construction

30            (Rapides)

31            Payable from General Obligation Bonds

32            Priority 1                                            $ 1,300,000
                                                                    $ 1,500,000
33            Priority 5                                            $ 2,800,000

34            Total

35  (578793) Surfacing the Shoulder of Trinity Church Road

36            to Accommodate Staging of School Traffic,

37            Planning and Construction

38            (Rapides)

39            Payable from the Capital Outlay Savings Fund          $  355,000

40  50/J41 RED RIVER PARISH

41  (578312) E911, Sheriff Station, and Administrative Offices,

42            Planning and Construction

43            (Red River)

44            Payable from General Obligation Bonds

45            Priority 2                                            $  500,000

46            Payable from the Capital Outlay Savings Fund          $  500,000

47            Total                                                 $ 1,000,000

                               Page 75 of 174
    HB NO. 2                                                             ENROLLED

1   50/J42 RICHLAND PARISH

2   (577901) Richland Parish Road Improvements for Christian Drive,

3             Planning and Construction

4             (Richland)

5             Payable from General Obligation Bonds

6             Priority 2                                                 $ 1,200,000

7             Priority 5                                                 $ 1,200,000

8             Total                                                      $ 2,400,000

9   50/J44 ST. BERNARD PARISH

10  (577372) St. Bernard Parish Fire Station #10, Planning and

11            Construction

12            (St. Bernard)

13            Payable from the Capital Outlay Savings Fund               $ 4,200,000

14  (577373) St. Bernard Parish Jail Renovations, Planning and

15            Construction

16            (St. Bernard)

17            Payable from General Obligation Bonds

18            Priority 1                                                 $ 2,535,411
                                                                         $ 3,200,000
19            Priority 5                                                 $ 5,735,411

20            Total

21  (577548) St. Bernard 40 Arpent Trail Bridge over LA 47, Planning

22            and Construction

23            (St. Bernard)

24            Payable from General Obligation Bonds

25            Priority 5                                                 $ 2,400,000

26  (577638) St. Bernard Parish Daniel Drive Sewer Main Repairs

27            Project, Planning and Construction

28            (St. Bernard)

29            Payable from General Obligation Bonds

30            Priority 5                                                 $ 2,700,000

31  (577639) St. Bernard Parish St. Claude Avenue Culvert

32            Improvements Project, Planning and Construction

33            (St. Bernard)

34            Payable from General Obligation Bonds

35            Priority 5                                                 $ 3,500,000

36  (577685) St. Bernard Parish Canal Project (Hebert/Creely/Bluebird),

37            Planning and Construction

38            (St. Bernard)

39            Payable from General Obligation Bonds

40            Priority 5                                                 $ 11,000,000

41  50/J45 ST. CHARLES PARISH

42  (577278) Primrose Canal Sheet Pile, Planning and Construction

43            (St. Charles)

44            Payable from General Obligation Bonds

45            Priority 5                                                 $ 3,250,000

                                Page 76 of 174
    HB NO. 2                                                               ENROLLED

1   (577293) Fifth Street Drainage Improvements, Planning and

2             Construction

3             (St. Charles)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 4,000,000

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                  $  450,000

8             Payable from the Capital Outlay Savings Fund              $  500,000

9             Total                                                     $ 4,950,000

10  (577296) West Bank Water Treatment Plant, E Plant Construction,

11            Planning and Construction

12            (St. Charles)

13            Payable from General Obligation Bonds

14            Priority 5                                                $ 33,000,000

15  (577351) Des Allemands Bulkhead - Phase 1, Planning and

16            Construction

17            (St. Charles)

18            Payable from General Obligation Bonds

19            Priority 2                                                $ 1,000,000

20            Priority 5                                                $ 2,622,500

21            Payable from the Capital Outlay Savings Fund              $  500,000

22            Total                                                     $ 4,122,500

23  (577353) Paul Fredrick Street and Kinler Street Demolition and

24            Reconstruction

25            (St. Charles)

26            Payable from General Obligation Bonds

27            Priority 5                                                $ 2,825,000

28  50/J46 ST. HELENA PARISH

29  (577914) Audubon Library, Planning and Construction

30            (St. Helena)

31            Payable from General Obligation Bonds

32            Priority 1                                                $ 1,863,600

33  50/J47 ST. JAMES PARISH

34  (577377) Parishwide Road Rehabilitation, Planning and Construction

35            (St. James)

36            Payable from General Obligation Bonds

37            Priority 1                                                $  745,362

38            Payable from State General Fund (Direct) Non-Recurring

39            Revenues                                                  $ 1,000,000

40            Total                                                     $ 1,745,362

41  (577378) West Shore Risk Reduction Connector Levee

42            (St. James)

43            Payable from General Obligation Bonds

44            Priority 1                                                $ 3,514,698
                                                                        $ 16,650,000
45            Priority 5                                                $ 20,164,698

46            Total

                              Page 77 of 174
    HB NO. 2                                                             ENROLLED

1   (577379) LA 3127 Widening (LA 20 to LA 3213), Planning and

2             Construction

3             (St. James)

4             Payable from General Obligation Bonds

5             Priority 1                                              $ 3,563,747

6             Priority 5                                              $ 21,400,000

7             Total                                                   $ 24,963,747

8   (577782) South Nobile Drainage Improvements,

9             Planning and Construction

10            (St. James)

11            Payable from General Obligation Bonds

12            Priority 5                                              $  905,000

13            Payable from State General Fund (Direct) Non-Recurring

14            Revenues                                                $  85,000

15            Total                                                   $  990,000

16  (577812) Bayou Chevreuil Boat Launch, Planning

17            and Construction

18            (St. James)

19            Payable from General Obligation Bonds

20            Priority 5                                              $  400,000

21            Payable from State General Fund (Direct) Non-Recurring

22            Revenues                                                $  500,000

23            Total                                                   $  900,000

24  (577813) Above Ground Water Storage Tank,

25            Planning and Construction

26            (St. James)

27            Payable from General Obligation Bonds

28            Priority 5                                              $ 1,800,000

29  50/J48 ST. JOHN THE BAPTIST PARISH

30  (576657) Parallel Woodland Canal Excavation and Airline Hwy.

31            Culvert Improvement, Planning and Construction

32            (St. John the Baptist)

33            Payable from General Obligation Bonds

34            Priority 2                                              $  523,000

35            Priority 5                                              $ 5,235,000

36            Total                                                   $ 5,758,000

37  (577485) Big Belle Terre Lift Station Rehabilitation Project,

38            Planning and Construction

39            (St. John the Baptist)

40            Payable from General Obligation Bonds

41            Priority 2                                              $  170,000

42            Priority 5                                              $ 1,530,000

43            Total                                                   $ 1,700,000

44  50/J49 ST. LANDRY PARISH

45  (577925) District Attorney Building Chiller Replacement,

46            Planning and Construction

47            (St. Landry)

48            Payable from General Obligation Bonds

49            Priority 2                                              $  500,000

50            Payable from the Capital Outlay Savings Fund            $  500,000

51            Total                                                   $ 1,000,000

                                      Page 78 of 174
    HB NO. 2                                                               ENROLLED

1   (578299) Parish Wide Road Program, Planning and Construction

2             (St. Landry)

3             Payable from General Obligation Bonds

4             Priority 1                                                $ 2,500,000

5             Payable from State General Fund (Direct) Non-Recurring

6             Revenues                                                  $ 2,400,000

7             Total                                                     $ 4,900,000

8   (578345) Opelousas General Hospital Water Wells - Main

9             and South Campuses, Planning and Construction

10            (St. Landry)

11            Payable from General Obligation Bonds

12            Priority 2                                                $  435,000

13            Priority 5                                                $ 3,915,000

14            Total                                                     $ 4,350,000

15  (578844) Courthouse Renovations, Planning and Construction

16            (St. Landry)

17            Payable from General Obligation Bonds

18            Priority 1                                                $  21,440

19  50/J50 ST. MARTIN PARISH

20  (577441) St. Martin Parish- Theobold Road Improvements,

21            Planning and Construction

22            (St. Martin)

23            Payable from the balance of State General Fund (Direct)

24            Revenues previously allocated under the authority of Act

25            28 of 2007 for I-10 Frontage Road, LA 328 to LA 347,

26            Planning and Construction

27            (St. Martin)                                              $  235,000

28  (577661) Milhomme Bridge Improvements, Planning

29            and Construction

30            (St. Martin)

31            Payable from General Obligation Bonds

32            Priority 5                                                $ 1,000,000

33  (577684) St. Martin- Parc Hardy Improvements, Planning and

34            Construction

35            (St. Martin)

36            Payable from the balance of State General Fund (Direct)

37            Non-Recurring Revenues previously allocated under the

38            authority of Act 20 of 2009 for I-10 Frontage Road, LA

39            328 to LA 347, Planning and Construction

40            (St. Martin)                                              $  450,000

41  (578818) Spanish Trail Industrial Park Access Road, Planning and

42            Construction

43            (St. Martin)

44            Payable from General Obligation Bonds

45            Priority 1                                                $ 1,343,268

46  (578829) I-10 Frontage Road, LA 328 to LA 347, Planning and

47            Construction

48            (St. Martin)

49            Payable from General Obligation Bonds

50            Priority 5                                                $ 1,000,000

                                Page 79 of 174
    HB NO. 2                                                                ENROLLED

1   (578843) Joe Daigre Canal Drainage Improvements, Planning and

2             Construction

3             (St. Martin)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $  672,999

6             Priority 5                                                 $  550,000

7             Total                                                      $ 1,222,999

8   50/J51 ST. MARY PARISH

9   (577470) New Central Fire Station for St. Mary Parish

10            Fire Protection District No. 11 in the Four

11            Corners Community, Planning and Construction

12            (St. Mary)

13            Payable from General Obligation Bonds

14            Priority 5                                                 $  150,000

15            Payable from State General Fund (Direct)                   $  150,000

16            Total                                                      $  300,000

17  (577479) Emergency Power Improvements at St. Mary Parish

18            Courthouse, Planning and Construction

19            (St. Mary)

20            Payable from General Obligation Bonds

21            Priority 1                                                 $  165,409

22  (578819) Reconstruction of Martin Luther King Roadway in

23            Charenton for St. Mary Parish Government, within

24            Existing Right-of-Way, Planning and Construction

25            (St. Mary)

26            Payable from General Obligation Bonds

27            Priority 1                                                 $  47,245

28  50/J52 ST. TAMMANY PARISH

29  (578535) Hwy 1088/I-12 AML Corridor Initiative, Planning and

30            Construction

31            (St. Tammany)

32            Payable from General Obligation Bonds

33            Priority 1                                                 $ 1,000,000

34            Priority 2                                                 $ 2,000,000

35            Priority 5                                                 $ 11,625,000

36            Total                                                      $ 14,625,000

37  (578536) Castine Wastewater Treatment Plant Expansion - AML

38            Phase 2, Planning and Construction

39            (St. Tammany)

40            Payable from the Capital Outlay Savings Fund               $  500,000

41  (578538) Safe Haven Campus for Behavioral and Mental Health,

42            Planning, Construction and Renovation for Triage

43            (St. Tammany)

44            Payable from General Obligation Bonds

45            Priority 1                                                 $ 3,027,703

46            Priority 5                                                 $ 8,350,000

47            Total                                                      $ 11,377,703

48  (578539) University Square Learning Center Facilities, Planning and

49            Construction

50            (St. Tammany)

51            Payable from General Obligation Bonds

52            Priority 5                                                 $ 9,378,000

                             Page 80 of 174
    HB NO. 2                                                              ENROLLED

1   (578540) South Slidell Levee Protection Rehabilitation: (USACE

2             533d Report or Planning, Land Acquisition, and

3             Construction of Levees West and East of Interstate 10)

4             (St. Tammany)

5             Payable from General Obligation Bonds

6             Priority 5                                               $ 9,108,000

7   (579023) Ben Thomas - Stone Road to Powell Drive, Design,

8             Planning, and Construction

9             (St. Tammany)

10            Payable from General Obligation Bonds

11            Priority 1                                               $ 1,500,000
                                                                       $ 3,615,000
12            Priority 5                                               $ 5,115,000

13            Total

14  (578542) Harrison Avenue Widening, Planning and Construction

15            (St. Tammany)

16            Payable from General Obligation Bonds

17            Priority 5                                               $ 13,300,000

18  (578543) Emerald Forrest Boulevard to LA 59, Design, Planning and

19            Construction

20            (St. Tammany)

21            Payable from General Obligation Bonds

22            Priority 5                                               $ 13,000,000

23  (578544) Sharp Road Improvements and Sidewalk, Planning and

24            Construction

25            (St. Tammany)

26            Payable from General Obligation Bonds

27            Priority 5                                               $ 6,125,000

28  (578820) Highway 11 - Opportunity Zone, Sewer & Water

29            Improvements, Planning and Construction

30            (St. Tammany)

31            Payable from General Obligation Bonds

32            Priority 5                                               $ 28,000,000

33  (578821) Fabourg Coquille Water Quality Improvements, Planning

34            and Construction

35            (St. Tammany)

36            Payable from General Obligation Bonds

37            Priority 5                                               $ 6,050,000

38  (578822) LA 1077 Widening, Design, Right of Way, Planning and

39            Construction

40            (St. Tammany)

41            Payable from General Obligation Bonds

42            Priority 1                                               $  20,000

43            Priority 5                                               $ 20,000,000

44            Total                                                    $ 20,020,000

45  (578823) Hwy 11 Regional Water Consolidation Design, Planning

46            and Construction

47            (St. Tammany)

48            Payable from General Obligation Bonds

49            Priority 5                                               $ 20,000,000

                                Page 81 of 174
    HB NO. 2                                                            ENROLLED

1   (578957) East St. Tammany Regional Sewer Consolidation Design,

2             Planning and Construction

3             (St. Tammany)

4             Payable from General Obligation Bonds

5             Priority 5                                             $ 30,000,000

6   (578966) Safe Haven Behavioral Health Campus Roads, Design,

7             Planning and Construction

8             (St. Tammany)

9             Payable from General Obligation Bonds

10            Priority 5                                             $ 2,250,000

11  50/J53 TANGIPAHOA PARISH

12  (577140) South Airport Road, North Hoover Road Improvements,

13            Planning and Construction

14            (Tangipahoa)

15            Payable from General Obligation Bonds

16            Priority 1                                             $ 2,186,727

17  (577141) North Hoover Road Improvements Phase 2, Planning and

18            Construction

19            (Tangipahoa)

20            Payable from General Obligation Bonds

21            Priority 1                                             $ 2,720,500

22            Priority 5                                             $ 6,000,000

23            Total                                                  $ 8,720,500

24  (577142) Region 9 Emergency Distribution Center & Public Works,

25            Planning and Construction

26            (Tangipahoa)

27            Payable from General Obligation Bonds

28            Priority 5                                             $ 4,000,000

29  (578990) Airport Road Roundabouts, Planning and

30            Construction

31            (Tangipahoa)

32            Payable from General Obligation Bonds

33            Priority 5                                             $ 5,000,000

34  50/J54 TENSAS PARISH

35  (576694) Tensas Parish/Port Priority Site Plan, Planning and

36            Construction

37            (Tensas)

38            Payable from General Obligation Bonds

39            Priority 1                                             $  170,550

40  (576697) Recreation Facility, Planning and Construction

41            (Tensas)

42            Payable from General Obligation Bonds

43            Priority 1                                             $  193,929

44            Priority 5                                             $ 7,370,000

45            Payable from the Capital Outlay Savings Fund           $ 1,000,000

46            Total                                                  $ 8,563,929

                             Page 82 of 174
    HB NO. 2                                                              ENROLLED

1   50/J55 TERREBONNE PARISH

2   (577841) Westside/Alma Street Drainage, Planning and Construction

3             (Terrebonne)

4             Payable from General Obligation Bonds

5             Priority 1                                               $  101,868

6   (577842) Terrebonne Sports Complex, Planning and Construction

7             (Terrebonne)

8             Payable from General Obligation Bonds

9             Priority 1                                               $ 1,055,239

10  (577917) Replacement of D-18 Pump Station Falgout Canal, Theriot,

11            La., Planning and Construction

12            (Terrebonne)

13            Payable from General Obligation Bonds

14            Priority 5                                               $ 2,125,000

15  (577921) Replacement of Brady Road Bridge, Planning and

16            Construction

17            (Terrebonne)

18            Payable from General Obligation Bonds

19            Priority 1                                               $ 5,266,000

20            Priority 5                                               $  580,000

21            Payable from the Capital Outlay Savings Fund             $ 2,000,000

22            Total                                                    $ 7,846,000

23  (577990) Bayou LaCarpe Watershed Project, Location C, Design and

24            Construction

25            (Terrebonne)

26            Payable from General Obligation Bonds

27            Priority 1                                               $  314,308

28            Priority 5                                               $ 9,000,000

29            Total                                                    $ 9,314,308

30  (577993) Valhi Extension (Savanne to LA 311), Planning and

31            Construction

32            (Terrebonne)

33            Payable from General Obligation Bonds

34            Priority 5                                               $ 32,000,000

35  (577995) Company Canal Miter Gate in Bourg, Planning and

36            Construction

37            (Terrebonne)

38            Payable from General Obligation Bonds

39            Priority 5                                               $ 9,000,000

40  (577996) Bayou Terrebonne Miter Gate, Twin Span Location,

41            Planning and Construction

42            (Terrebonne)

43            Payable from General Obligation Bonds

44            Priority 5                                               $ 9,000,000

45  (578239) Planning, Design, Land Purchase, and Construction of

46            Neuro Medical Facility, Planning and Construction

47            (Terrebonne)

48            Payable from General Obligation Bonds

49            Priority 5                                               $ 12,500,000

                            Page 83 of 174
    HB NO. 2                                                             ENROLLED

1   (578315) South Louisiana Wetland Discovery Center - Phase 2 -

2             Bayou Country Institute, Planning and Construction

3             (Terrebonne)

4             Payable from General Obligation Bonds

5             Priority 1                                              $  387,931

6   50/J56 UNION PARISH

7   (578691) Courthouse Renovations, Planning and Construction

8             (Union)

9             Payable from State General Fund (Direct)                $  200,000

10            Payable from the Capital Outlay Savings Fund            $  200,000

11            Total                                                   $  400,000

12  50/J57 VERMILION PARISH

13  (577352) Parish Wide Road Improvements, Planning and

14            Construction

15            (Vermilion)

16            Payable from General Obligation Bonds

17            Priority 5                                              $ 4,600,000

18  50/J58 VERNON PARISH

19  (578065) Vernon Parish Historic Courthouse Renovations,

20            Planning and Construction

21            (Vernon)

22            Payable from the Capital Outlay Savings Fund            $  150,000

23  (578066) Bailey Road Improvements, Planning and Construction

24            (Vernon)

25            Payable from General Obligation Bonds

26            Priority 1                                              $ 1,500,000

27            Priority 2                                              $ 2,000,000

28            Priority 5                                              $ 1,780,000

29            Total                                                   $ 5,280,000

30  (578067) Section Line Road Improvements,

31            Planning and Construction

32            (Vernon)

33            Payable from General Obligation Bonds

34            Priority 5                                              $  900,000

35  (578825) Vernon/Fort Johnson formerly Fort Polk Thoroughfare

36            Electrical Power Extension, and Utilities Including

37            Generators

38            (Vernon)

39            Payable from General Obligation Bonds

40            Priority 1                                              $  298,557

41  50/J59 WASHINGTON PARISH

42  (578234) Pearl River Navigational Canal, Planning, Construction,

43            and Acquisition

44            (Washington)

45            Payable from General Obligation Bonds

46            Priority 1                                              $  500,000

                               Page 84 of 174
    HB NO. 2                                                                ENROLLED

1   50/J64 WINN PARISH

2   (578337) Roadway Reconstruction, Eugene Garrett Road, Planning

3             and Construction

4             (Winn)

5             Payable from General Obligation Bonds

6             Priority 1                                                 $  367,675

7   (578347) Roadway Reconstruction, Frank White Road, Planning and

8             Construction

9             (Winn)

10            Payable from General Obligation Bonds

11            Priority 1                                                 $  15,092

12  50/M01 ABBEVILLE

13  (578275) Electrical Distribution Improvements,

14            Planning and Construction

15            (Vermilion)

16            Payable from the Capital Outlay Savings Fund               $  250,000

17  50/M02 ABITA SPRINGS

18  (578219) Water System Improvements,

19            Planning and Construction

20            (St. Tammany)

21            Payable from General Obligation Bonds

22            Priority 5                                                 $ 2,000,000

23  (578220) Wastewater Treatment System Improvements,

24            Planning and Construction

25            (St. Tammany)

26            Payable from General Obligation Bonds

27            Priority 5                                                 $ 2,700,000

28            Payable from the Capital Outlay Savings Fund               $  300,000

29            Total                                                      $ 3,000,000

30  50/M05 ALEXANDRIA

31  (577768) Sugarhouse Road/Eddie Williams Boulevard to LA

32            Highway 1, Phase I and II, Planning and Construction

33            ($5,000,000 Local Match)

34            (Rapides)

35            Payable from General Obligation Bonds

36            Priority 5                                                 $ 4,620,000

37  50/M06 AMITE

38  (578074) Regional Wastewater Treatment and Transmission Facilities,

39            Planning and Construction

40            (Tangipahoa)

41            Payable from General Obligation Bonds

42            Priority 1                                                 $ 20,700,000

43            Priority 5                                                 $ 12,050,000

44            Total                                                      $ 32,750,000

                                Page 85 of 174
    HB NO. 2                                                                ENROLLED

1   (578826) Amite Governmental Complex, Planning and Construction

2             (Tangipahoa)

3             Payable from General Obligation Bonds

4             Priority 1                                                 $  195,799

5             Priority 5                                                 $ 2,600,000

6             Total                                                      $ 2,795,799

7   50/M07 ANACOCO

8   (578196) Anacoco Street Rehabilitation and Water Line

9             Replacement - Port Arthur Ave., Planning and Construction

10            (Vernon)

11            Payable from General Obligation Bonds

12            Priority 2                                                 $  540,000

13  50/M09 ARCADIA

14  (578739) Water Facilities Improvements, Planning

15            and Construction

16            (Bienville)

17            Payable from General Obligation Bonds

18            Priority 5                                                 $ 2,025,000

19  50/M14 BAKER

20  (578445) Drainage Improvements and Upgrades, Planning and Construction

21            (East Baton Rouge)

22            Payable from General Obligation Bonds

23            Priority 5                                                 $ 2,600,000

24            Payable from the Capital Outlay Savings Fund               $  500,000

25            Total                                                      $ 3,100,000

26  (578446) Sidewalk Construction for Underdeveloped Streets and

27            Culverts, Planning and Construction

28            (East Baton Rouge)

29            Payable from General Obligation Bonds

30            Priority 5                                                 $ 1,875,000

31  50/M15 BALDWIN

32  (577532) Potable Water System Improvements, Planning and

33            Construction

34            (St. Mary)

35            Payable from General Obligation Bonds

36            Priority 1                                                 $  53,796

37            Priority 5                                                 $  700,000

38            Total                                                      $  753,796

39  (577533) Wastewater System Repair and Improvements, Planning

40            and Construction

41            (St. Mary)

42            Payable from General Obligation Bonds

43            Priority 5                                                 $ 1,000,000

44  50/M17 BASILE

45  (578181) Gas System and Drainage System Improvements,

46            Planning and Construction

47            (Evangeline)

48            Payable from General Obligation Bonds

49            Priority 5                                                 $  878,000

                                  Page 86 of 174
    HB NO. 2                                                               ENROLLED

1   50/M19 BASTROP

2   (578522) Sewer Treatment Facility and Improvements,

3             Planning and Construction

4             (Morehouse)

5             Payable from General Obligation Bonds

6             Priority 5                                                $  675,000

7             Payable from the Capital Outlay Savings Fund              $  75,000

8             Total                                                     $  750,000

9   50/M20 BATON ROUGE

10  (577926) Raising Cane's River Center, Planning,

11            Design and Renovation

12            (East Baton Rouge)

13            Payable from General Obligation Bonds

14            Priority 5                                                $ 18,000,000

15            Payable from the Capital Outlay Savings Fund              $  750,000

16            Total                                                     $ 18,750,000

17  (577928) Chaneyville Fire District No. 7 Reames Road Fire Station,

18            Planning and Construction

19            (East Baton Rouge)

20            Payable from General Obligation Bonds

21            Priority 1                                                $  300,000

22  (577929) Hooper Road Widening and Sewer Improvements

23            (Blackwater Bayou to Sullivan Road) Planning,

24            Engineering, Utilities and Construction

25            (East Baton Rouge)

26            Payable from General Obligation Bonds

27            Priority 1                                                $ 1,500,000
                                                                        $ 8,000,000
28            Priority 5                                                $ 9,500,000

29            Total

30  (577930) Old Hammond Hwy. (LA 426) Roadway Improvements

31            from Blvd. De Province to Millerville Road, Planning and

32            Construction

33            (East Baton Rouge)

34            Payable from General Obligation Bonds

35            Priority 1                                                $ 1,450,000

36            Priority 5                                                $ 8,250,000

37            Total                                                     $ 9,700,000

38  50/M22 BENTON

39  (578022) Wastewater Collection Improvements (Courthouse

40            Subbasin), Planning and Construction

41            (Bossier)

42            Payable from General Obligation Bonds

43            Priority 1                                                $ 1,700,000
                                                                        $ 1,700,000
44            Priority 5                                                $ 3,400,000

45            Total

                                  Page 87 of 174
    HB NO. 2                                                            ENROLLED

1   50/M26 BLANCHARD

2   (576897) Water Distribution System Improvements

3             (State Line Rd. Area), Planning and Construction

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 2                                             $  900,000

7             Priority 5                                             $ 1,000,000

8             Total                                                  $ 1,900,000

9   (578827) Wastewater Facilities Improvements, Planning and

10            Construction

11            (Caddo)

12            Payable from General Obligation Bonds

13            Priority 5                                             $ 2,000,000

14  50/M27 BOGALUSA

15  (578828) Community Center and Emergency Shelter, Planning and

16            Construction

17            (Washington)

18            Payable from General Obligation Bonds

19            Priority 1                                             $  399,725

20  (578878) Davenport Avenue Bridge, Servitude Street Emergency

21            Replacement and Repair, Planning and Construction

22            (Washington)

23            Payable from General Obligation Bonds

24            Priority 5                                             $  565,000

25  50/M29 BOSSIER CITY

26  (578490) Water Treatment Improvements - Nanofiltration System,

27            Planning and Construction

28            (Bossier)

29            Payable from General Obligation Bonds

30            Priority 1                                             $ 2,000,000

31            Priority 5                                             $ 21,000,000

32            Total                                                  $ 23,000,000

33  (578491) Swan Lake/Deen Point Waterline Extension, Planning and

34            Construction

35            (Bossier)

36            Payable from General Obligation Bonds

37            Priority 5                                             $ 6,120,000

38  50/M32 BROUSSARD

39  (576937) Water System Groundwater Storage Tank, Planning and

40            Construction

41            (Lafayette)

42            Payable from General Obligation Bonds

43            Priority 1                                             $  125,000

44            Priority 5                                             $ 1,000,000

45            Total                                                  $ 1,125,000

                            Page 88 of 174
    HB NO. 2                                                               ENROLLED

1   (576938) Marteau Road Water Well, Planning and Construction

2             (Lafayette)

3             Payable from General Obligation Bonds

4             Priority 1                                                $  390,000

5             Priority 5                                                $ 4,200,000

6             Total                                                     $ 4,590,000

7   (576939) Albertson Parkway Water Well and Ground Storage Tank,

8             Planning and Construction

9             (Lafayette)

10            Payable from General Obligation Bonds

11            Priority 1                                                $ 1,890,000

12            Priority 5                                                $ 2,716,000

13            Total                                                     $ 4,606,000

14  (576940) Highway 89 Improvements, Planning and Construction

15            (Lafayette)

16            Payable from General Obligation Bonds

17            Priority 1                                                $ 3,635,748

18            Priority 5                                                $ 4,000,000

19            Total                                                     $ 7,635,748

20  (578880) Reconstruct South Bernard Road from LA Hwy 182 to US

21            Hwy 90, Planning and Construction

22            (Lafayette)

23            Payable from General Obligation Bonds

24            Priority 1                                                $  199,927

25  50/M38 CANKTON

26  (576916) Water System Upgrades, Planning and Construction

27            (St. Landry)

28            Payable from General Obligation Bonds

29            Priority 5                                                $  250,000

30  50/M39 CARENCRO

31  (577951) City Wide Water Main Rehabilitation Project, Planning and

32            Construction

33            (Lafayette)

34            Payable from General Obligation Bonds

35            Priority 5                                                $ 4,500,000

36            Payable from State General Fund (Direct) Non-Recurring

37            Revenues                                                  $ 1,500,000

38            Payable from State General Fund (Direct)                  $  600,000

39            Total                                                     $ 6,600,000

40  (578893) I-49 to Gloria Switch Coulee Project, Planning and

41            Construction

42            (Lafayette)

43            Payable from General Obligation Bonds

44            Priority 1                                                $  203,058

45  50/M45 CHURCH POINT

46  (577897) Sewer System Improvements, Planning and

47            Construction

48            (Acadia)

49            Payable from General Obligation Bonds

50            Priority 5                                                $ 3,900,000

                            Page 89 of 174
    HB NO. 2                                                             ENROLLED

1   (577899) Street and Drainage Improvements, Planning

2             and Construction

3             (Acadia)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 5,300,000

6   50/M48 CLAYTON

7   (577781) Clayton Street Improvements, Planning and Construction

8             (Concordia)

9             Payable from General Obligation Bonds

10            Priority 5                                              $ 3,500,000

11  50/M50 COLFAX

12  (578895) Street Improvements, Planning and Construction

13            (Grant)

14            Payable from General Obligation Bonds

15            Priority 1                                              $  131,157

16            Priority 5                                              $ 1,250,000

17            Total                                                   $ 1,381,157

18  50/M54 COTTON VALLEY

19  (578897) Sewerage System Improvements, Planning and Construction

20            (Webster)

21            Payable from General Obligation Bonds

22            Priority 1                                              $ 1,189,000

23  50/M57 COVINGTON

24  (578046) LA 21 and Tyler Street Roundabout, Planning and

25            Construction

26            (St. Tammany)

27            Payable from General Obligation Bonds

28            Priority 5                                              $ 2,700,000

29  (578047) Downtown Historic District Overlays, Planning and

30            Construction

31            (St. Tammany)

32            Payable from General Obligation Bonds

33            Priority 1                                              $  28,473

34            Priority 5                                              $  640,000

35            Total                                                   $  668,473

36  (578274) Wastewater Collection System Rehabilitation

37            Improvements, Planning and Construction

38            (St. Tammany)

39            Payable from the Capital Outlay Savings Fund            $ 1,000,000

40  50/M58 CROWLEY

41  (577745) Oddfellows Road Improvements, Planning and

42            Construction

43            (Acadia)

44            Payable from General Obligation Bonds

45            Priority 5                                              $ 6,040,000

46  (577762) Sewer System Upgrade, Planning and Construction

47            (Acadia)

48            Payable from the Capital Outlay Savings Fund            $  350,000

                                Page 90 of 174
    HB NO. 2                                                              ENROLLED

1   50/M60 DELCAMBRE

2   (577774) Street and Drainage Improvements,

3             Planning and Construction

4             (Vermilion)

5             Payable from the Capital Outlay Savings Fund             $  250,000

6   50/M63 DENHAM SPRINGS

7   (577253) Home Depot Road Improvements (LA 3003 to LA 3002),

8             Planning and Construction

9             (Livingston)

10            Payable from General Obligation Bonds

11            Priority 5                                               $ 2,770,000

12  (577254) DEMCO Drive/Convention Drive,

13            Planning and Construction

14            (Livingston)

15            Payable from General Obligation Bonds

16            Priority 5                                               $ 5,000,000
                                                                       $ 1,100,000
17            Payable from the Capital Outlay Savings Fund             $ 6,100,000

18            Total

19  50/M64 DEQUINCY

20  (577309) Street Rehabilitation, Planning and Construction

21            (Calcasieu)

22            Payable from General Obligation Bonds

23            Priority 5                                               $ 2,000,000

24            Payable from the Capital Outlay Savings Fund             $  100,000

25            Total                                                    $ 2,100,000

26  50/M65 DERIDDER

27  (577298) Street Rehabilitation, Planning and Construction

28            (Beauregard)

29            Payable from General Obligation Bonds

30            Priority 5                                               $  750,000

31            Payable from the Capital Outlay Savings Fund             $  100,000

32            Total                                                    $  850,000

33  (577740) Water Line Improvements, Planning and Construction

34            (Beauregard)

35            Payable from General Obligation Bonds

36            Priority 5                                               $  450,000

37  (577742) P.W. West Drainage Improvements,

38            Planning and Construction

39            (Beauregard)

40            Payable from General Obligation Bonds

41            Priority 5                                               $  517,500

42

43  50/M68 DONALDSONVILLE

44  (578171) Lala Regira Field Renovations, Planning and Construction

45            (Ascension)

46            Payable from General Obligation Bonds

47            Priority 1                                               $  286,500

                            Page 91 of 174
    HB NO. 2                                                                ENROLLED

1   (578180) Natural Gas System Infrastructure Improvement Phase III,

2             Planning and Construction

3             (Ascension)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $ 1,006,204

6   (578637) Septage Receiving Station, Planning and

7             Construction

8             (Ascension)

9             Payable from General Obligation Bonds

10            Priority 5                                                 $ 1,260,000

11            Payable from the balance of reappropriated State General

12            Fund (Direct) previously allocated under the authority of

13            Act 5 of 2024 for Ascension Parish, LA 73 at LA 30

14            Roundabout, Planning and Construction (Ascension)          $  400,000

15            Total                                                      $ 1,660,000

16  (578641) LA 3089 Railroad Crossing, Planning and

17            Construction

18            (Ascension)

19            Payable from General Obligation Bonds

20            Priority 5                                                 $ 2,150,000

21            Payable from the balance of reappropriated State General

22            Fund (Direct) previously allocated under the authority of

23            Act 5 of 2024 for Ascension Parish, LA 73 at LA 30

24            Roundabout, Planning and Construction (Ascension)          $  100,000

25            Total                                                      $ 2,250,000

26  (578665) Stormwater Resilience Project, Planning and Construction

27            (Ascension)

28            Payable from General Obligation Bonds

29            Priority 1                                                 $  120,000

30            Priority 5                                                 $ 1,102,500

31            Total                                                      $ 1,222,500

32  50/M74 DUSON

33  (577307) LA Highway 95 Roundabout, Planning and Construction

34            (Acadia)

35            Payable from General Obligation Bonds

36            Priority 1                                                 $ 2,542,129

37  50/M83 EUNICE

38  (577839) Street Improvements, Planning and Construction

39            (St. Landry)

40            Payable from General Obligation Bonds

41            Priority 5                                                 $ 3,780,000

42  (578611) Renovations to City Hall/Police Department,

43            Planning and Construction

44            (St. Landry)

45            Payable from General Obligation Bonds

46            Priority 5                                                 $  990,000

47  50/M84 EVERGREEN

48  (578901) Evergreen Water System Improvements

49            (Avoyelles)

50            Payable from General Obligation Bonds

51            Priority 1                                                 $  4,055

                            Page 92 of 174
    HB NO. 2                                                             ENROLLED

1   50/M85 FARMERVILLE

2   (578070) Lake D'Arbonne Mega Ramp, Planning and Construction

3             (Union)

4             Payable from General Obligation Bonds

5             Priority 1                                              $ 2,000,000

6             Priority 5                                              $ 2,185,000

7             Total                                                   $ 4,185,000

8   50/M87 FERRIDAY

9   (576695) Water Renovations, Planning and Construction

10            (Concordia)

11            Payable from General Obligation Bonds

12            Priority 1                                              $  298,987

13            Priority 2                                              $ 1,500,000

14            Priority 5                                              $ 3,000,000

15            Payable from the Capital Outlay Savings Fund            $ 1,500,000

16            Total                                                   $ 6,298,987

17  (576696) Town of Ferriday Municipal Complex and Wastewater

18            Collection and Treatment Improvements, Planning and

19            Construction

20            (Concordia)

21            Payable from General Obligation Bonds

22            Priority 1                                              $  700,000

23            Priority 5                                              $ 18,400,000

24            Total                                                   $ 19,100,000

25  50/M91 FORDOCHE

26  (577095) Water Distribution System Improvements, Planning and

27            Construction

28            (Pointe Coupee)

29            Payable from General Obligation Bonds

30            Priority 1                                              $ 2,822,475

31            Priority 5                                              $  500,000

32            Total                                                   $ 3,322,475

33  50/MA3 GOLDEN MEADOW

34  (577486) Armand/Alcide Area Drainage, Planning and

35            Construction

36            Payable from State General Fund (Direct) Non-Recurring

37            Revenues                                                $ 1,010,000

38  (578902) Upgrade to North Sewerage Treatment Plant, Planning and

39            Construction

40            (Lafourche)

41            Payable from General Obligation Bonds

42            Priority 1                                              $  4,065

43  50/MA5 GONZALES

44  (578471) Roadway Improvements, Planning, Design,

45            and Construction

46            (Ascension)

47            Payable from General Obligation Bonds

48            Priority 2                                              $  37,000

49            Priority 5                                              $ 2,705,000

50            Total                                                   $ 2,742,000

                                Page 93 of 174
    HB NO. 2                                                            ENROLLED

1   (578903) Connector Road for City of Gonzales Hospital District,

2             Planning and Construction

3             (Ascension)

4             Payable from General Obligation Bonds

5             Priority 1                                             $  37,208

6   50/MA6 GRAMBLING

7   (578214) Water Distribution System Replacement, Planning and

8             Construction

9             (Lincoln)

10            Payable from General Obligation Bonds

11            Priority 5                                             $ 1,920,000

12  (578216) Wastewater System Expansion, Planning and Construction

13            (Lincoln)

14            Payable from General Obligation Bonds

15            Priority 5                                             $ 2,000,000

16  50/MB2 GRAYSON

17  (578064) Water Treatment Plant, Planning and Construction

18            (Caldwell)

19            Payable from General Obligation Bonds

20            Priority 5                                             $ 3,650,000

21            Payable from the Capital Outlay Savings Fund           $  300,000

22            Total                                                  $ 3,950,000

23  50/MB5 GRETNA

24  (578747) City Hall Exterior and Interior Renovation

25            (Jefferson)

26            Payable from General Obligation Bonds

27            Priority 1                                             $  383,347

28            Priority 5                                             $ 1,500,000

29            Total                                                  $ 1,883,347

30  50/MB7 GUEYDAN

31  (577139) Police and Fire Station Reconstruction,

32            Planning and Construction

33            (Vermilion)

34            Payable from General Obligation Bonds

35            Priority 5                                             $ 1,687,500

36  50/MB8 HALL SUMMIT

37  ()        Park Redevelopment and Community Center,

38            Planning and Construction

39            (Red River)

40            Payable from General Obligation Bonds

41            Priority 5                                             $ 2,790,000

42            Payable from the Capital Outlay Savings Fund           $  310,000

43            Total                                                  $ 3,100,000

44  Pending submittal of a capital outlay budget request pursuant to the provisions of R.S.

45  39:112.

                            Page 94 of 174
    HB NO. 2                                                                ENROLLED

1   ()        Hall Summit Roadway Rehabilitation for Various Streets,

2             Planning and Construction

3             (Red River)

4             Payable from General Obligation Bonds

5             Priority 2                                                 $  300,000

6             Priority 5                                                 $ 2,700,000

7             Total                                                      $ 3,000,000

8   Pending submittal of a capital outlay budget request pursuant to the provisions of R.S.

9   39:112.

10  50/MC1 HARAHAN

11  (577445) Jefferson Highway Safety Street Lighting Project,

12            Planning and Construction

13            (Jefferson)

14            Payable from General Obligation Bonds

15            Priority 5                                                 $  675,000

16  (577630) Halsey Drive Neighborhood Drainage Installation, Planning

17            and Construction

18            (Jefferson)

19            Payable from General Obligation Bonds

20            Priority 5                                                 $  783,880

21            Payable from the Capital Outlay Savings Fund               $  300,000

22            Total                                                      $ 1,083,880

23  (577783) Cover Eroding Ditch at Colonial Club Entrance,

24            Planning and Construction

25            (Jefferson)

26            Payable from the Capital Outlay Savings Fund               $  300,000

27  (577804) Glenwood Park Subdivision Emergency Drainage,

28            Planning and Construction

29            (Jefferson)

30            Payable from General Obligation Bonds

31            Priority 2                                                 $  100,000

32            Priority 5                                                 $  900,000

33            Total                                                      $ 1,000,000

34  (578904) Emergency Sewer Collection and Treatment System

35            Overhaul, Planning and Construction

36            (Jefferson)

37            Payable from General Obligation Bonds

38            Priority 5                                                 $ 1,000,000

39  (578998) Emergency Road Repair and Replacement, Planning

40            and Construction

41            (Jefferson)

42            Payable from the balance of the Capital Outlay Savings

43            Fund previously allocated under the authority of Act 5

44            of 2024 for Harahan, Emergency Road Replacement, Monroe

45            Street, and Resor Avenue, Planning and Construction

46            (Jefferson) and Act 5 of 2024 for Harahan, Emergency Road

47            Repair/Replacement, Ok Avenue and Elfer Street, Planning

48            and Construction (Jefferson)                               $ 1,500,000

                                Page 95 of 174
    HB NO. 2                                                             ENROLLED

1   50/MC3 HAUGHTON

2   (578586) I-20 Water & Sewer Force Main Crossing & Lift Station

3             (Bossier)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 4,200,000

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                $  500,000

8             Total                                                   $ 4,700,000

9   (578588) LA 157 Widening from I-20 to Railroad South of

10            W. McKinley Ave., Planning and Construction

11            (Bossier)

12            Payable from General Obligation Bonds

13            Priority 2                                              $  500,000

14            Priority 5                                              $ 5,000,000

15            Payable from the Capital Outlay Savings Fund            $  550,000

16            Total                                                   $ 6,050,000

17  (578590) Communications Tower for Public Safety & Utilities,

18            Planning and Construction

19            (Bossier)

20            Payable from the Balance of State General

21            Fund (Direct) Non-Recurring previously allocated

22            under the authority of Act 5 of 2024 for Fletcher

23            Technical Community College, Precision Agriculture

24            Training Facility, Planning and Construction

25            (Terrebonne)                                            $  450,000

26  50/MC4 HAYNESVILLE

27  (578018) Water Distribution System Improvements (Phase II),

28            Planning and Construction

29            (Claiborne)

30            Payable from General Obligation Bonds

31            Priority 5                                              $ 1,000,000

32  (578958) Water Distribution System Improvements, Planning and

33            Construction

34            (Claiborne)

35            Payable from General Obligation Bonds

36            Priority 1                                              $  855,000

37            Payable from the Capital Outlay Savings Fund            $  150,000

38            Total                                                   $ 1,005,000

39  50/MC6 HENDERSON

40  (576946) Sewer System Improvements, Planning and Construction

41            (St. Martin)

42            Payable from General Obligation Bonds

43            Priority 1                                              $ 3,000,000

44            Priority 5                                              $ 2,670,000

45            Total                                                   $ 5,670,000

                            Page 96 of 174
    HB NO. 2                                                           ENROLLED

1   50/MC7 HESSMER

2   (578649) Village-Wide Street Improvements, Planning

3             and Construction

4             (Avoyelles)

5             Payable from General Obligation Bonds

6             Priority 2                                            $  115,000

7             Priority 5                                            $  920,000

8             Total                                                 $ 1,035,000

9   50/MC9 HOMER

10  (578244) Wastewater Treatment Plant Upgrades, Planning

11            and Construction

12            (Claiborne)

13            Payable from General Obligation Bonds

14            Priority 5                                            $  775,000

15            Payable from the Capital Outlay Savings Fund          $  100,000

16            Total                                                 $  875,000

17  (578905) Town Hall Renovations, Planning and Construction

18            (Claiborne)

19            Payable from General Obligation Bonds

20            Priority 5                                            $  796,404

21  (578906) Street Improvement Project, Planning and Construction

22            (Claiborne)

23            Payable from General Obligation Bonds

24            Priority 5                                            $  600,000

25  50/MD1 HORNBECK

26  (577305) Road Rehabilitation, Planning and Construction

27            (Vernon)

28            Payable from General Obligation Bonds

29            Priority 5                                            $  600,000

30            Payable from the Capital Outlay Savings Fund          $  100,000

31            Total                                                 $  700,000

32  (578909) West Side Water System Expansion, Planning and

33            Construction

34            (Sabine, Vernon)

35            Payable from General Obligation Bonds

36            Priority 1                                            $  74,903

37  50/MD2 HOSSTON

38  (578500) Water System Improvements, Water Well, Water Main,

39            SCADA, Generator, and Miscellaneous Equipment,

40            Planning and Construction

41            (Caddo)

42            Payable from General Obligation Bonds

43            Priority 5                                            $  600,000

44            Payable from the balance of General

45            Obligation Bond proceeds previously

46            allocated under the authority of Act 485

47            of 2021 for Carencro, I-49 to Gloria Switch

48            Coulee Project, Planning and Construction

49            (Lafayette)                                           $  203,058

50            Total                                                 $  803,058

                                Page 97 of 174
    HB NO. 2                                                               ENROLLED

1   50/MD4 IDA

2   (578503) Water System Improvements, Water Wells, Tanks, and

3             Booster Stations Construction, Planning and Construction

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 1                                                $ 1,092,435

7   (578524) Water System Improvements - Water Main

8             Replacements, Phase 1, Planning and

9             Construction

10            (Caddo)

11            Payable from General Obligation Bonds

12            Priority 5                                                $ 2,700,000

13  50/MD6 IOTA

14  (577697) Street Improvements, Planning and Construction

15            (Acadia)

16            Payable from General Obligation Bonds

17            Priority 5                                                $ 1,625,000

18  (577698) Belt Press System for Sanitary Sewerage Sludge

19            Treatment, Planning and Construction

20            (Acadia)

21            Payable from General Obligation Bonds

22            Priority 5                                                $ 1,260,000

23  50/ME1 JEAN LAFITTE

24  (578654) Amphitheater Stage, Planning and Construction

25            (Jefferson)

26            Payable from General Obligation Bonds

27            Priority 1                                                $  400,000

28  50/ME2 JEANERETTE

29  (578276) Sewer System Improvements, Planning and Construction

30            (Iberia)

31            Payable from General Obligation Bonds

32            Priority 5                                                $ 3,320,000

33  (578277) Water System Improvements, Planning and Construction

34            (Iberia)

35            Payable from General Obligation Bonds

36            Priority 5                                                $  575,000

37  (578278) City Hall Renovations, Planning and Construction

38            (Iberia)

39            Payable from General Obligation Bonds

40            Priority 5                                                $  370,000

41  50/ME4 JENNINGS

42  (577902) Fred and Ruth Zigler Memorial Dr. Extension, Planning and

43            Construction

44            (Jefferson Davis)

45            Payable from General Obligation Bonds

46            Priority 5                                                $ 7,955,000

47            Payable from the Capital Outlay Savings Fund              $  200,000

48            Total                                                     $ 8,155,000

                                 Page 98 of 174
    HB NO. 2                                                                  ENROLLED

1   50/ME6 JONESVILLE

2   (578407) Glenn Ditch Pump Station, Planning and Construction

3             (Catahoula)

4             Payable from General Obligation Bonds

5             Priority 5                                                   $  325,000

6             Payable from the Capital Outlay Savings Fund                 $  325,000

7             Total                                                        $  650,000

8   50/ME8 KAPLAN

9   (576965) Street and Drainage Improvements, Planning and

10            Construction

11            (Vermilion)

12            Payable from General Obligation Bonds

13            Priority 5                                                   $  850,000

14  50/MF1 KENNER

15  (577014) Lincoln Manor Drainage Phase 2, Planning and Construction

16            (Jefferson)

17            Payable from General Obligation Bonds

18            Priority 1                                                   $  500,000

19            Priority 5                                                   $  750,000

20            Payable from the Capital Outlay Savings Fund                 $  100,000

21            Total                                                        $ 1,350,000

22  (577015) Roosevelt Boulevard Improvements (Airline Drive to West

23            Metairie Ave.), Planning and Construction

24            (Jefferson)

25            Payable from General Obligation Bonds

26            Priority 5                                                   $ 4,730,000

27            Payable from the Capital Outlay Savings Fund                 $  500,000

28            Total                                                        $ 5,230,000

29  (577018) Kenner Fire Department Facility Replacement - New Fire

30            Station, Planning and Construction

31            (Jefferson)

32            Payable from General Obligation Bonds

33            Priority 5                                                   $ 1,000,000

34            Payable from the Capital Outlay Savings Fund                 $ 1,000,000

35            Total                                                        $ 2,000,000

36  (577037) Pump to the River Pump Station Phase I, Planning and

37            Construction

38            (Jefferson)

39            Payable from General Obligation Bonds

40            Priority 1                                                   $ 1,421,379

41            Priority 5                                                   $ 15,050,000

42            Total                                                        $ 16,471,379

43  (578912) Lincoln Manor Subdivision Drainage Improvement,

44            including 30th Street Roadway and Drainage Improvements

45            from Loyola Drive to Ohio Street, Planning and Construction

46            (Jefferson)

47            Payable from General Obligation Bonds

48            Priority 1                                                   $  119,998

                            Page 99 of 174
    HB NO. 2                                                              ENROLLED

1   50/MF6 KROTZ SPRINGS

2   (578936) Water System Infrastructure Improvements, Planning and

3             Construction

4             (St. Landry)

5             Payable from General Obligation Bonds

6             Priority 1                                               $  70,000

7             Priority 5                                               $  630,000

8             Total                                                    $  700,000

9   50/MF7 LAFAYETTE

10  (576531) Johnston Street Infrastructure Improvements,

11            Planning and Construction

12            (Lafayette)

13            Payable from General Obligation Bonds

14            Priority 1                                               $ 2,500,000
                                                                       $ 22,500,000
15            Priority 5                                               $ 25,000,000

16            Total

17  (577005) Downtown/Freetown/UL Drainage Improvements,

18            Planning and Construction

19            (Lafayette)

20            Payable from General Obligation Bonds

21            Priority 2                                               $ 2,000,000
                                                                       $ 10,000,000
22            Priority 5                                               $ 12,000,000

23            Total

24  50/MF8 LAKE ARTHUR

25  (577818) Wastewater Treatment Facility Improvements, Planning and

26            Construction

27            (Jefferson Davis)

28            Payable from General Obligation Bonds

29            Priority 5                                               $ 1,050,000

30  (577819) Wastewater Collection System Improvements, Planning and

31            Construction

32            (Jefferson Davis)

33            Payable from General Obligation Bonds

34            Priority 5                                               $  990,000

35            Payable from the Capital Outlay Savings Fund             $  100,000

36            Total                                                    $ 1,090,000

37  (577820) Water System Improvements, Planning and Construction

38            (Jefferson Davis)

39            Payable from General Obligation Bonds

40            Priority 5                                               $  990,000

41            Payable from the Capital Outlay Savings Fund             $  900,000

42            Total                                                    $ 1,890,000

43  50/MF9 LAKE CHARLES

44  (578189) Lakefront Development

45            (Calcasieu)

46            Payable from General Obligation Bonds

47            Priority 1                                               $  221,222

48            Priority 2                                               $  500,000

49            Priority 5                                               $ 2,000,000

50            Payable from the Capital Outlay Savings Fund             $ 1,000,000

51            Total                                                    $ 3,721,222

                                 Page 100 of 174
    HB NO. 2                                                                  ENROLLED

1   (578190) Relocation of Public Works Campus, Planning and

2             Construction

3             (Calcasieu)

4             Payable from General Obligation Bonds

5             Priority 1                                                   $ 3,642,453
                                                                           $ 1,000,000
6             Priority 2                                                   $ 6,000,000
                                                                           $ 10,642,453
7             Priority 5

8             Total

9   (578191) Enterprise Boulevard Extension, Planning and

10            Construction

11            (Calcasieu)

12            Payable from General Obligation Bonds

13            Priority 5                                                   $ 5,000,000

14  (578194) Downtown Parking Garage Rehabilitation, Planning

15            and Construction

16            (Calcasieu)

17            Payable from General Obligation Bonds

18            Priority 5                                                   $ 1,500,000

19  (578917) Sallier Street Rehabilitation, Planning and Construction

20            (Calcasieu)

21            Payable from General Obligation Bonds

22            Priority 1                                                   $ 1,000,000

23            Priority 5                                                   $ 2,000,000

24            Total                                                        $ 3,000,000

25  50/MG1 LAKE PROVIDENCE

26  (577723) Town of Lake Providence Sewer System Improvements,

27            Planning and Construction

28            (East Carroll)

29            Payable from General Obligation Bonds

30            Priority 5                                                   $ 1,740,000

31  50/MG3 LEESVILLE

32  (577846) Street Rehabilitation and Extension, Planning and

33            Construction

34            (Vernon)

35            Payable from General Obligation Bonds

36            Priority 1                                                   $  3,433

37            Priority 5                                                   $  750,000

38            Total                                                        $  753,433

39  (577847) Drainage Improvements, Planning and Construction

40            (Vernon)

41            Payable from the Capital Outlay Savings Fund                 $  300,000

42  (577849) City of Leesville, Sanitary Sewer Extension for Fort Johnson

43            formerly Fort Polk Entrance Road, Planning and

44            Construction

45            (Vernon)

46            Payable from General Obligation Bonds

47            Priority 1                                                   $ 2,356,294

48            Priority 5                                                   $ 2,000,000

49            Total                                                        $ 4,356,294

                                Page 101 of 174
    HB NO. 2                                                               ENROLLED

1   50/MG7 LIVINGSTON

2   (578352) Old Courthouse Renovations, Planning and Construction

3             (Livingston)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 3,000,000

6   50/MG8 LIVONIA

7   (577098) Water Well, Planning and Construction

8             (Pointe Coupee)

9             Payable from General Obligation Bonds

10            Priority 1                                                $  988,425

11            Payable from State General Fund (Direct)                  $  150,000

12            Total                                                     $ 1,138,425

13  50/MH5 LUTCHER

14  (578921) Roadway Improvements, Planning and Construction

15            (St. James)

16            Payable from General Obligation Bonds

17            Priority 2                                                $  500,000

18            Priority 5                                                $ 1,000,000

19            Total                                                     $ 1,500,000

20  50/MH6 MADISONVILLE

21  (577123) Road Improvements, Planning and Construction

22            (St. Tammany)

23            Payable from General Obligation Bonds

24            Priority 5                                                $ 1,000,000

25            Payable from the Capital Outlay Savings Fund              $  100,000

26            Total                                                     $ 1,100,000

27  (577126) Water Main Improvements, Planning and Construction

28            (St. Tammany)

29            Payable from the Capital Outlay Savings Fund              $  500,000

30  50/MH8 MANDEVILLE

31  (577264) Police Department Building, Planning and Construction

32            (St. Tammany)

33            Payable from General Obligation Bonds

34            Priority 1                                                $ 1,000,000

35            Priority 2                                                $ 1,000,000

36            Total                                                     $ 2,000,000

37  50/MH9 MANGHAM

38  (578922) Mangham Recreation Complex, Planning and Construction

39            (Richland)

40            Payable from General Obligation Bonds

41            Priority 1                                                $  28,879

42  50/MI3 MANY

43  (577666) Water Treatment Plant Improvements, Acquisition, Planning

44            and Construction

45            (Sabine)

46            Payable from General Obligation Bonds

47            Priority 5                                                $ 1,500,000

                                Page 102 of 174
    HB NO. 2                                                                ENROLLED

1   50/MI5 MARION

2   (578413) Municipal Complex, Planning and Construction

3             (Union)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $  700,000

6   50/MI6 MARKSVILLE

7   (578045) Airport Road and West Waddil Street Improvements,

8             Planning and Construction

9             (Avoyelles)

10            Payable from General Obligation Bonds

11            Priority 5                                                 $  740,000

12            Payable from State General Fund (Direct) Non-Recurring

13            Revenues                                                   $  70,000

14            Total                                                      $  810,000

15  50/MI8 MAURICE

16  (577241) New Village Hall, Planning and Construction

17            (Vermilion)

18            Payable from General Obligation Bonds

19            Priority 1                                                 $ 1,365,000

20  (578051) Sewer Treatment Plant Extension, Planning and

21            Construction

22            (Vermilion)

23            Payable from General Obligation Bonds

24            Priority 5                                                 $ 6,100,000

25            Payable from State General Fund (Direct) Non-Recurring

26            Revenues                                                   $  400,000

27            Total                                                      $ 6,500,000

28  50/MJ1 MELVILLE

29  (578001) Improvements to Multiple Streets in Melville, Planning and

30            Construction

31            (St. Landry)

32            Payable from General Obligation Bonds

33            Priority 1                                                 $  120,000

34            Priority 5                                                 $ 1,200,000

35            Total                                                      $ 1,320,000

36  50/MJ2 MERMENTAU

37  (577699) Street Improvements, Planning and Construction

38            (Acadia)

39            Payable from General Obligation Bonds

40            Priority 5                                                 $  435,000

41  50/MJ5 MINDEN

42  (578182) Potable Water Ground Storage Tank, Planning and

43            Construction

44            (Webster)

45            Payable from General Obligation Bonds

46            Priority 1                                                 $  546,684

                            Page 103 of 174
    HB NO. 2                                                                ENROLLED

1   (578184) Robertson Lift Station Improvements, Planning and

2             Construction

3             (Webster)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $  890,000

6             Payable from the balance of State General Fund (Direct)

7             previously allocated under the authority of Act 5 of 2024

8             for the Division of Administration, Statewide Roofing

9             AssetManagement Program and Waterproofing, Related

10            Repairs and Equipment Replacement Program

11            (Statewide)                                                $  890,000

12            Total                                                      $ 1,780,000

13  (578520) Fire Station, Planning and Construction

14            (Webster)

15            Payable from General Obligation Bonds

16            Priority 2                                                 $  594,500

17            Priority 5                                                 $ 2,205,500

18            Total                                                      $ 2,800,000

19  50/MJ6 MONROE

20  (578317) I-20 Interchange Improvement and Kansas Garrett

21            Connector, Kansas Lane Connector, Planning and

22            Construction

23            ($1,000,000 Local and $6,000,000 Federal Match)

24            (Ouachita)

25            Payable from General Obligation Bonds

26            Priority 1                                                 $ 12,513,983
                                                                         $ 15,468,121
27            Priority 5                                                 $ 27,982,104

28            Total

29  (578318) Booker T. Washington Stormwater System Evaluation and

30            Upgrades, Planning and Construction

31            (Ouachita)

32            Payable from General Obligation Bonds

33            Priority 2                                                 $ 2,000,000

34            Priority 5                                                 $ 3,030,000

35            Total                                                      $ 5,030,000

36  (578319) Young's Bayou Watershed Enhancement of Channel

37            Capacity, Planning and Construction

38            (Ouachita)

39            Payable from General Obligation Bonds

40            Priority 1                                                 $  500,000

41            Priority 5                                                 $ 10,900,000

42            Total                                                      $ 11,400,000

43  (578320) Georgia Street Pump Station, Including Generator and

44            Auxiliary Pumps, Planning, Engineering, Right-of-Way,

45            Utilities and Construction

46            (Ouachita)

47            Payable from General Obligation Bonds

48            Priority 1                                                 $ 6,000,000

49            Priority 5                                                 $ 5,640,000

50            Total                                                      $ 11,640,000

                            Page 104 of 174
    HB NO. 2                                                              ENROLLED

1   (578323) Calypso Street Pump Station Rehabilitation, Planning,

2             Engineering, Design, Right-of-Way, Utilities, and

3             Construction

4             (Ouachita)

5             Payable from General Obligation Bonds

6             Priority 2                                               $ 1,000,000

7             Priority 5                                               $ 1,030,000

8             Total                                                    $ 2,030,000

9   50/MJ9 MOORINGSPORT

10  (576739) Caddo Lakeside Lodge Project, Planning and Construction

11            (Caddo)

12            Payable from the Capital Outlay Savings Fund             $  280,000

13  50/MK4 MORSE

14  (577701) Wastewater Treatment Facility, Planning and Construction

15            (Acadia)

16            Payable from General Obligation Bonds

17            Priority 5                                               $ 1,610,000

18  (578923) Water Tower Improvements, Planning and Construction

19            (Acadia)

20            Payable from General Obligation Bonds

21            Priority 1                                               $  29,585

22  50/MK9 NATCHITOCHES

23  (577573) Second Street and Touline Street Concrete Pavement and

24            Replacement, Planning and Construction

25            (Natchitoches)

26            Payable from General Obligation Bonds

27            Priority 1                                               $ 2,000,000

28            Payable from State General Fund (Direct) Non-Recurring

29            Revenues                                                 $  280,000

30            Total                                                    $ 2,280,000

31  50/ML1 NEW IBERIA

32  (577028) New Iberia- Street Improvements, Planning and

33            Construction

34            (Iberia)

35            Payable from General Obligation Bonds

36            Priority 5                                               $ 4,500,000
                                                                       $ 1,000,000
37            Payable from the Capital Outlay Savings Fund             $ 5,500,000

38            Total

39  (577029) New Iberia - Drainage Improvements, Planning and

40            Construction

41            (Iberia)

42            Payable from General Obligation Bonds

43            Priority 5                                               $ 4,200,000
                                                                       $ 1,000,000
44            Payable from State General Fund (Direct)                 $ 5,200,000

45            Total

                              Page 105 of 174
    HB NO. 2                                                            ENROLLED

1   (577031) Improvements to Buildings in City Parks, Planning and

2             Construction

3             (Iberia)

4             Payable from General Obligation Bonds

5             Priority 1                                             $ 3,142,000

6             Priority 5                                             $ 5,000,000

7             Total                                                  $ 8,142,000

8   (578924) Frontage Road Improvements, Planning and Construction

9             (Iberia)

10            Payable from General Obligation Bonds

11            Priority 1                                             $ 1,000,000

12  50/ML2 NEW LLANO

13  (578613) Maintenance Building Improvements,

14            Planning and Construction

15            (Vernon)

16            Payable from the Capital Outlay Savings Fund           $  260,000

17  50/ML3 NEW ORLEANS

18  (577423) Monticello Canal Culverts at Airline Highway

19            (Orleans)

20            Payable from General Obligation Bonds

21            Priority 1                                             $  750,000

22            Priority 5                                             $ 8,250,000

23            Total                                                  $ 9,000,000

24  (577425) West Bank Ferry Terminal Renovations, Planning and

25            Construction

26            (Orleans)

27            Payable from General Obligation Bonds

28            Priority 1                                             $  300,000

29            Priority 5                                             $  300,000

30            Total                                                  $  600,000

31  (577426) Dryades Kitchen Incubator, Planning and Construction

32            (Orleans)

33            Payable from General Obligation Bonds

34            Priority 5                                             $  350,000

35  (577427) Richard Lee Playground, Planning and Construction

36            (Orleans)

37            Payable from General Obligation Bonds

38            Priority 1                                             $  133,699

39            Priority 5                                             $ 3,000,000

40            Total                                                  $ 3,133,699

41  (577429) Lincoln Beach Redevelopment, Planning and Construction

42            (Orleans)

43            Payable from General Obligation Bonds

44            Priority 5                                             $ 5,500,000

45  (577430) Old New Orleans VA Building Rehabilitation

46            (Orleans)

47            Payable from General Obligation Bonds

48            Priority 1                                             $  313,546

                            Page 106 of 174
    HB NO. 2                                                                ENROLLED

1   (577431) New Sewerage and Water Board Power Plant, Planning and

2             Construction

3             (Orleans)

4             Payable from General Obligation Bonds

5             Priority 1                                                 $ 3,000,000

6             Priority 5                                                 $ 26,000,000

7             Total                                                      $ 29,000,000

8   (578004) New City Hall, Planning and Construction

9             (Orleans)

10            Payable from General Obligation Bonds

11            Priority 5                                                 $ 1,000,000

12            Payable from the balance of State General Funds (Direct)

13            previously allocated under the authority of Act 5 of 2024

14            for the Division of Administration, Statewide Roofing

15            Asset Management Program and Waterproofing, Related

16            Repairs and Equipment Replacement Program

17            (Statewide)                                                $ 1,000,000

18            Total                                                      $ 2,000,000

19  (578006) New Consolidated Westbank Fire Station,

20            Planning and Construction

21            (Orleans)

22            Payable from General Obligation Bonds

23            Priority 2                                                 $ 1,750,000
                                                                         $ 5,000,000
24            Priority 5                                                 $ 6,750,000

25            Total

26  (578048) Municipal Auditorium Stabilization/Armstrong Park

27            Redevelopment, Planning and Construction

28            (Orleans)

29            Payable from General Obligation Bonds

30            Priority 2                                                 $ 1,000,000
                                                                         $ 15,000,000
31            Priority 5                                                 $ 16,000,000

32            Total

33  (578466) Sewerage and Water Board Water Treatment

34            Modernization, 5 Year Capital Improvement

35            Plan, Planning and Construction

36            (Orleans)

37            Payable from General Obligation Bonds

38            Priority 2                                                 $ 9,500,000
                                                                         $ 4,500,000
39            Priority 5                                                 $ 14,000,000

40            Total

41  50/ML4 NEW ROADS

42  (578442) Industrial Park Development Project, Including

43            Underground Electrical System Upgrades, Planning and

44            Construction

45            (Pointe Coupee)

46            Payable from State General Fund (Direct) Non-Recurring

47            Revenues                                                   $  988,000

                               Page 107 of 174
    HB NO. 2                                                             ENROLLED

1   50/ML8 NORWOOD

2   (576923) Sewer Collection and Treatment System Improvements,

3             Planning and Construction

4             (East Feliciana)

5             Payable from General Obligation Bonds

6             Priority 5                                              $  872,000

7             Payable from the Capital Outlay Savings Fund            $  100,000

8             Total                                                   $  972,000

9   50/MM2 OAKDALE

10  (577977) Citywide Sewer Improvements, Planning and Construction

11            (Allen)

12            Payable from General Obligation Bonds

13            Priority 5                                              $ 3,400,000

14            Payable from the Capital Outlay Savings Fund            $  750,000

15            Total                                                   $ 4,150,000

16  50/MM4 OIL CITY

17  (578368) Wastewater Collection and Treatment Improvements,

18            Planning and Construction

19            (Caddo)

20            Payable from General Obligation Bonds

21            Priority 5                                              $ 1,000,000

22            Payable from the Capital Outlay Savings Fund            $  900,000

23            Total                                                   $ 1,900,000

24  50/MM6 OPELOUSAS

25  (577407) Opelousas Street and Drainage Improvements

26            (St. Landry)

27            Payable from General Obligation Bonds

28            Priority 1                                              $ 1,000,000

29            Payable from State General Fund (Direct) Non-Recurring

30            Revenues                                                $ 2,250,000

31            Total                                                   $ 3,250,000

32  (578925) Water Meter Replacement and Upgrades, Planning and

33            Construction

34            (St. Landry)

35            Payable from General Obligation Bonds

36            Priority 1                                              $  40,705

37  50/MM9 PATTERSON

38  (578628) Replacement of Water and Gas Meters in Patterson,

39            Planning and Construction

40            (St. Mary)

41            Payable from General Obligation Bonds

42            Priority 1                                              $  439,300

43  50/MN1 PEARL RIVER

44  (577158) Drainage Improvements, Planning and Construction

45            (St. Tammany)

46            Payable from General Obligation Bonds

47            Priority 5                                              $ 1,440,000

48            Payable from the Capital Outlay Savings Fund            $  100,000

49            Total                                                   $ 1,540,000

                                Page 108 of 174
    HB NO. 2                                                              ENROLLED

1   (577961) Roadway Improvements, Planning and Construction

2             (St. Tammany)

3             Payable from the Capital Outlay Savings Fund             $  500,000

4   50/MN3 PINEVILLE

5   (578926) Cedar Lake Pump Station Reconstruction, Design, Planning

6             and Construction

7             (Rapides)

8             Payable from General Obligation Bonds

9             Priority 5                                               $  585,000

10  (578965) New Police Complex and City Court Additions and

11            Improvements, Planning and Construction

12            (Rapides)

13            Payable from General Obligation Bonds

14            Priority 1                                               $  140,000

15            Priority 5                                               $ 8,965,000

16            Payable from State General Fund (Direct) Non-Recurring

17            Revenues                                                 $ 1,985,000

18            Total                                                    $ 11,090,000

19  50/MO1 PONCHATOULA

20  (578830) Fire Station Complex US 51 - Veterans Avenue, Land

21            Acquisition, Planning and Construction

22            (Tangipahoa)

23            Payable from General Obligation Bonds

24            Priority 1                                               $  648,375

25            Priority 5                                               $  800,000

26            Total                                                    $ 1,448,375

27  50/MO6 PROVENCAL

28  (577963) New Water Well and Emergency Water Connection,

29            Planning and Construction

30            (Natchitoches)

31            Payable from General Obligation Bonds

32            Priority 1                                               $  600,000

33  50/MO8 RAYNE

34  ()        Water Tower Repairs, Planning and Construction

35            (Acadia)

36            Payable from the Capital Outlay Savings Fund             $  350,000

37  50/MO9 RAYVILLE

38  (578529) Water Service Facilities for Economic Development,

39            Planning and Construction

40            (Richland)

41            Payable from General Obligation Bonds

42            Priority 5                                               $ 8,022,300

43  (578530) Rayville Road Improvements for Economic Development,

44            Planning and Construction

45            (Richland)

46            Payable from General Obligation Bonds

47            Priority 5                                               $ 2,550,000

                                Page 109 of 174
    HB NO. 2                                                              ENROLLED

1   (578674) Municipal Complex, Planning and Construction

2             (Richland)

3             Payable from General Obligation Bonds

4             Priority 5                                               $ 5,000,000

5   (578675) Wastewater Transport and Treatment Facilities for

6             Economic Development

7             (Richland)

8             Payable from General Obligation Bonds

9             Priority 5                                               $ 3,500,000

10  50/MP9 ROSELAND

11  (578629) Sewer System Improvements, Planning and Construction

12            (Tangipahoa)

13            Payable from General Obligation Bonds

14            Priority 2                                               $ 1,179,207

15            Payable from the Capital Outlay Savings Fund             $  50,000

16            Total                                                    $ 1,229,207

17  50/MQ1 ROSEPINE

18  (577828) Rehabilitation of Main Street, Planning and Construction

19            (Vernon)

20            Payable from General Obligation Bonds

21            Priority 1                                               $  450,000

22  50/MQ2 RUSTON

23  (578287) East Kentucky/Cedar Creek Road Intersection

24            Improvements, Planning and Construction

25            (West Feliciana)

26            Payable from General Obligation Bonds

27            Priority 5                                               $  478,200

28  (578288) New Road from Highway 150 to I-20 South Frontage

29            Road, Planning and Construction

30            (Lincoln)

31            Payable from General Obligation Bonds

32            Priority 1                                               $  815,718

33            Priority 5                                               $ 1,740,000

34            Payable from the Capital Outlay Savings Fund             $ 1,600,000

35            Total                                                    $ 4,155,718

36  50/MQ3 ST. FRANCISVILLE

37  (577161) Emergency Erosion Repairs, Planning and Construction

38            (West Feliciana)

39            Payable from General Obligation Bonds

40            Priority 1                                               $ 3,204,647

41  (577162) Commerce Street Improvements and Utilities Relocation,

42            Planning and Construction

43            (West Feliciana)

44            Payable from General Obligation Bonds

45            Priority 1                                               $ 1,100,000

46            Priority 5                                               $ 2,100,000

47            Total                                                    $ 3,200,000

                                Page 110 of 174
    HB NO. 2                                                             ENROLLED

1   50/MQ4 ST. JOSEPH

2   (578831) St. Joseph's Community House, Planning and Construction

3             (Tensas)

4             Payable from General Obligation Bonds

5             Priority 5                                              $  690,000

6   50/MQ5 ST. MARTINVILLE

7   (577943) Main Street Enhancement Project, Planning and

8             Construction

9             (St. Martin)

10            Payable from General Obligation Bonds

11            Priority 1                                              $ 1,450,000

12  (578003) Public Works Buildings Renovation, Planning

13            and Construction

14            (St. Martin)

15            Payable from State General Fund (Direct) Non-Recurring

16            Revenues                                                $  660,000

17  (578005) Water Drainage Project, Planning and Construction

18            (St. Martin)

19            Payable from General Obligation Bonds

20            Priority 1                                              $  200,000

21            Priority 5                                              $  660,000

22            Payable from State General Fund (Direct) Non-Recurring

23            Revenues                                                $ 1,340,000

24            Total                                                   $ 2,200,000

25  (578009) SLCC Sewer Extension, Planning and Construction

26            (St. Martin)

27            Payable from General Obligation Bonds

28            Priority 5                                              $ 1,650,000

29  (578146) Rehab Existing Sidewalks and Installation of

30            New Sidewalks, Planning and Construction

31            (St. Martin)

32            Payable from General Obligation Bonds

33            Priority 5                                              $ 1,400,000

34  50/MQ8 SCOTT

35  (576677) LA 93 Roadway Improvements- I-10 Ramp to Renaud

36            Drive, Planning, Construction, and Land Acquisition

37            (Lafayette)

38            Payable from General Obligation Bonds

39            Priority 1                                              $ 2,800,000

40            Priority 5                                              $ 5,845,000

41            Payable from State General Fund (Direct) Non-Recurring

42            Revenues                                                $ 1,500,000

43            Payable from State General Fund (Direct)                $ 1,500,000

44            Total                                                   $ 11,645,000

45  (576678) Eraste Landry Road Extension, Planning and Construction

46            (Lafayette)

47            Payable from General Obligation Bonds

48            Priority 1                                              $ 1,015,000

49            Priority 5                                              $ 7,992,000

50            Total                                                   $ 9,007,000

                                Page 111 of 174
    HB NO. 2                                                                ENROLLED

1   (576679) Bridge Replacement and Overlay, Planning and

2             Construction

3             (Lafayette)

4             Payable from General Obligation Bonds

5             Priority 5                                                 $ 1,200,000

6             Payable from State General Fund (Direct) Non-Recurring

7             Revenues                                                   $ 1,300,000

8             Total                                                      $ 2,500,000

9   (578832) Water and Sewer Line Installation along Apollo Road

10            Extension, including Utilities, Planning and Construction

11            (Lafayette)

12            Payable from General Obligation Bonds

13            Priority 1                                                 $ 3,128,750

14  50/MQA ST. GEORGE

15  (577981) Manchac- Fountain Regional Detention and Preservation,

16            Planning and Construction

17            (East Baton Rouge)

18            Payable from General Obligation Bonds

19            Priority 5                                                 $ 36,000,000

20            Payable from the Capital Outlay Savings Fund               $ 1,000,000

21            Total                                                      $ 37,000,000

22  (577985) Jefferson Highway Safety Widening and Drainage

23            Improvements, Planning and Construction

24            (East Baton Rouge)

25            Payable from General Obligation Bonds

26            Priority 5                                                 $ 8,400,000

27            Payable from the Capital Outlay Savings Fund               $  500,000

28            Total                                                      $ 8,900,000

29  (577989) St. George Regional Drainage Improvements, Planning

30            and Construction

31            (East Baton Rouge)

32            Payable from State General Fund (Direct) Non-Recurring

33            Revenues                                                   $  996,000

34  50/MR1 SHREVEPORT

35  (577747) Shreveport Regional Airport Expansion and Improvements,

36            Planning and Construction

37            (Caddo)

38            Payable from General Obligation Bonds

39            Priority 5                                                 $ 50,000,000

40  (577749) Shreveport Healthcare and Development Corridor, Planning

41            and Construction

42            (Caddo)

43            Payable from General Obligation Bonds

44            Priority 1                                                 $ 1,500,000

45            Priority 5                                                 $ 40,000,000

46            Total                                                      $ 41,500,000

47  (577750) District 3 Road Rehabilitation, Planning and Construction

48            (Caddo)

49            Payable from General Obligation Bonds

50            Priority 5                                                 $  500,000

                                  Page 112 of 174
    HB NO. 2                                                             ENROLLED

1   (577751) Bayou Pierre Drainage and Recreation, Planning and

2             Construction

3             (Caddo)

4             Payable from General Obligation Bonds

5             Priority 2                                              $ 4,000,000
                                                                      $ 20,000,000
6             Priority 5                                              $ 3,000,000
                                                                      $ 27,000,000
7             Payable from the Capital Outlay Savings Fund

8             Total

9   (577752) Amtrak Platform and Facility, Planning and Construction

10            (Caddo)

11            Payable from General Obligation Bonds

12            Priority 5                                              $ 10,000,000

13  (577753) University Park Subdivision Improvements, Planning and

14            Construction

15            (Caddo)

16            Payable from General Obligation Bonds

17            Priority 5                                              $ 6,000,000

18  (577754) C.C. Antoine Museum and Art Center,

19            Planning and Construction

20            (Caddo)

21            Payable from the Capital Outlay Savings Fund            $  100,000

22  (577760) Hirsch Coliseum Improvements, Planning and Construction

23            (Caddo)

24            Payable from General Obligation Bonds

25            Priority 5                                              $ 9,000,000

26  (577763) Thomas L. Amiss Water Treatment Plant Improvements

27            Planning and Construction

28            (Caddo)

29            Payable from General Obligation Bonds

30            Priority 5                                              $ 13,000,000

31  (578835) Greenwood Road Extension, (Greenwood Industrial Park

32            Road - Asphalt Road), Planning and Construction

33            (Caddo)

34            Payable from General Obligation Bonds

35            Priority 1                                              $  69,600

36            Priority 5                                              $ 2,000,000

37            Total                                                   $ 2,069,600

38  (578836) C.C. Antoine Park, Planning and Construction

39            (Caddo)

40            Payable from General Obligation Bonds

41            Priority 5                                              $  350,000

42  50/MR5 SIMMESPORT

43  (577982) Water System Improvements, Planning and

44            Construction

45            (Avoyelles)

46            Payable from State General Fund (Direct) Non-Recurring

47            Revenues                                                $  365,000

                            Page 113 of 174
    HB NO. 2                                                                  ENROLLED

1   50/MR6 SIMPSON

2   (577947) Standpipe Tank Refurbishment, Planning and Construction

3             (Vernon)

4             Payable from the Capital Outlay Savings Fund                 $  100,000

5   50/MR8 SLAUGHTER

6   (576786) Water System Improvements, Planning and Construction

7             (East Feliciana)

8             Payable from General Obligation Bonds

9             Priority 1                                                   $ 2,500,000

10  (576788) Road Rehabilitations, Planning and Construction

11            (East Feliciana)

12            Payable from the Capital Outlay Savings Fund                 $  100,000

13  (577058) Drainage Improvements, Planning and Construction

14            (East Feliciana)

15            Payable from General Obligation Bonds

16            Priority 2                                                   $  400,000

17  50/MR9 SLIDELL

18  (578260) Pedestrian Crosswalks on US 11 at Kostmayer Avenue,

19            Westchester Place, Pennsylvania Ave., and West Hall Street,

20            Planning and Construction

21            (St. Tammany)

22            Payable from General Obligation Bonds

23            Priority 2                                                   $  250,000

24            Priority 5                                                   $ 2,000,000

25            Total                                                        $ 2,250,000

26  50/MS4 SPRINGFIELD

27  (577167) Recreational Park, Planning and Construction

28            (Livingston)

29            Payable from the balance of State General Fund (Direct)

30            previously allocated under the authority of Act 465 of 2023

31            for Springfield Roadway Rehabilitation, Planning and

32            Construction (Livingston)                                    $  655,000

33  (577168) Water System Improvements and Upgrades, Planning and

34            Construction

35            (Livingston)

36            Payable from General Obligation Bonds

37            Priority 1                                                   $ 3,847,400

38  50/MS5 SPRINGHILL

39  (577208) Water System Improvements - Phase 3, Planning and

40            Construction

41            (Webster)

42            Payable from General Obligation Bonds

43            Priority 1                                                   $ 2,377,200
                                                                           $ 4,100,000
44            Priority 5                                                   $ 6,477,200

45            Total

                                Page 114 of 174
    HB NO. 2                                                             ENROLLED

1   50/MS7 STERLINGTON

2   (578750) Sewer Collection System Improvements,

3             Planning and Construction

4             (Ouachita)

5             Payable from General Obligation Bonds

6             Priority 2                                              $  400,000

7             Priority 5                                              $ 4,600,000

8             Total                                                   $ 5,000,000

9   50/MS9 SULPHUR

10  (577578) Installation of Water Meters

11            (Calcasieu)

12            Payable from General Obligation Bonds

13            Priority 5                                              $ 2,000,000

14  (577579) Maplewood Drive Rehabilitation

15            (Calcasieu)

16            Payable from General Obligation Bonds

17            Priority 1                                              $ 4,474,454

18            Priority 5                                              $ 5,137,500

19            Payable from State General Fund (Direct) Non-Recurring

20            Revenues                                                $ 1,200,000

21            Total                                                   $ 10,811,954

22  (577580) City of Sulphur, Phase 3 Wastewater Treatment Facility

23            Improvements, Planning and Construction

24            (Calcasieu)

25            Payable from General Obligation Bonds

26            Priority 5                                              $ 1,300,000

27  (577581) Maplewood Pump Station, Planning and Construction

28            (Calcasieu)

29            Payable from General Obligation Bonds

30            Priority 1                                              $ 1,075,000

31  50/MT1 SUN

32  (578837) Roof Replacement of Town Hall Building

33            (St. Tammany)

34            Payable from General Obligation Bonds

35            Priority 1                                              $  200,000

36  50/MT2 SUNSET

37  (577464) City Hall Renovations and New Addition,

38            Planning and Construction

39            (St. Landry)

40            Payable from General Obligation Bonds

41            Priority 5                                              $ 1,470,000

42            Payable from the Capital Outlay Savings Fund            $  150,000

43            Total                                                   $ 1,620,000

44  50/MT3 TALLULAH

45  (578838) Emergency Water Production, Transmission and Treatment,

46            Acquisition, Planning and Construction

47            (Madison)

48            Payable from General Obligation Bonds

49            Priority 1                                              $  62,125

                             Page 115 of 174
    HB NO. 2                                                                 ENROLLED

1   50/MT5 THIBODAUX

2   (577912) LA 648/Acadia Road Intersection Improvements Project,

3             Planning and Construction

4             (Lafourche)

5             Payable from General Obligation Bonds

6             Priority 5                                                  $ 3,000,000

7   (577913) Replacement of Canal Boulevard Bridges and Construction

8             of Menard Pedestrian Bike Trail, Planning and Construction

9             (Lafourche)

10            Payable from General Obligation Bonds

11            Priority 1                                                  $ 5,929,963

12  (578810) Emergency Operations Center, Planning and

13            Construction

14            (Lafourche)

15            Payable from General Obligation Bonds

16            Priority 5                                                  $ 2,470,000

17            Payable from State General Fund (Direct)                    $  400,000

18            Total                                                       $ 2,870,000

19  50/MU2 VIDALIA

20  (576918) Utility System Upgrade, Planning, Acquisition,

21            Construction and Equipment

22            (Concordia)

23            Payable from General Obligation Bonds

24            Priority 1                                                  $ 3,943,913
                                                                          $ 7,000,000
25            Priority 5                                                  $ 10,943,913

26            Total

27  (576919) Development of a Slackwater Port on the Mississippi River,

28            Planning and Construction

29            (Concordia)

30            Payable from General Obligation Bonds

31            Priority 1                                                  $  364,616

32  50/MU4 VILLE PLATTE

33  (578469) Wastewater Treatment Facility Rehabilitation, Planning and

34            Construction

35            (Evangeline)

36            Payable from General Obligation Bonds

37            Priority 5                                                  $ 12,481,000

38  50/MU5 VINTON

39  (577553) Water Plant Improvements, Planning and Construction

40            (Calcasieu)

41            Payable from General Obligation Bonds

42            Priority 5                                                  $ 1,800,000

43  (577555) Street Rehabilitation, Planning and Construction

44            (Calcasieu)

45            Payable from General Obligation Bonds

46            Priority 1                                                  $  100,000

47            Priority 5                                                  $  500,000

48            Total                                                       $  600,000

                            Page 116 of 174
    HB NO. 2                                                            ENROLLED

1   50/MU6 VIVIAN

2   (576899) Streets and Drainage Improvements (Phase II),

3             Planning and Construction

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 2                                             $  200,000

7             Priority 5                                             $  408,850

8             Total                                                  $  608,850

9   (578839) Water and Wastewater System Improvements and

10            Extension, Planning and Construction

11            (Caddo)

12            Payable from General Obligation Bonds

13            Priority 1                                             $  94,523

14  50/MU7 WALKER

15  (577688) Gas System Upgrades, Planning and Construction

16            (Livingston)

17            Payable from General Obligation Bonds

18            Priority 5                                             $ 3,600,000

19            Payable from the Capital Outlay Savings Fund           $  400,000

20            Total                                                  $ 4,000,000

21  (577689) Wastewater Treatment Plant Upgrades,

22            Planning and Construction

23            (Livingston)

24            Payable from General Obligation Bonds

25            Priority 2                                             $  200,000

26            Priority 5                                             $ 1,800,000

27            Total                                                  $ 2,000,000

28  50/MV1 WELSH

29  (577986) Frontage Road Extension, Planning and Construction

30            (Jefferson Davis)

31            Payable from General Obligation Bonds

32            Priority 1                                             $ 1,000,000
                                                                     $ 2,000,000
33            Priority 2                                             $ 1,145,000
                                                                     $ 4,145,000
34            Priority 5

35            Total

36  (577987) Replacement of Water Meters, Planning and Construction

37            (Jefferson Davis)

38            Payable from General Obligation Bonds

39            Priority 5                                             $  675,000

40  (577988) Street Rehabilitation, Planning and Construction

41            (Jefferson Davis)

42            Payable from General Obligation Bonds

43            Priority 5                                             $  675,000

                                 Page 117 of 174
    HB NO. 2                                                            ENROLLED

1   50/MV2 WEST MONROE

2   (577517) Downtown Utilities Hardening and Improvements,

3             Phase 1, Planning and Construction

4             (Ouachita)

5             Payable from General Obligation Bonds

6             Priority 5                                             $  555,000

7             Payable from the Capital Outlay Savings Fund           $  300,000

8             Total                                                  $  855,000

9   (577518) Cotton Street Improvements and Sidewalks, Planning and

10            Construction

11            (Ouachita)

12            Payable from General Obligation Bonds

13            Priority 1                                             $  350,000

14            Priority 5                                             $  550,000

15            Total                                                  $  900,000

16  (577520) Jersey Street Improvements, Planning and Construction

17            (Ouachita)

18            Payable from General Obligation Bonds

19            Priority 1                                             $  350,000

20  (577712) Mid-City Drainage Improvements, Planning and

21            Construction

22            (Ouachita)

23            Payable from General Obligation Bonds

24            Priority 5                                             $ 3,300,000

25  50/MV3 WESTLAKE

26  (577615) Sewer Transport System Improvements, Planning and

27            Construction

28            (Calcasieu)

29            Payable from General Obligation Bonds

30            Priority 5                                             $ 3,300,000

31  (577618) City of Westlake Street Rehabilitation, Planning and

32            Construction

33            (Calcasieu)

34            Payable from General Obligation Bonds

35            Priority 5                                             $  960,000

36  50/MV4 WESTWEGO

37  (577255) Water Tower, Line and Improvements, Water Meter

38            Replacement, Planning and Construction

39            (Jefferson)

40            Payable from General Obligation Bonds

41            Priority 2                                             $ 1,000,000
                                                                     $ 1,000,000
42            Priority 5                                             $ 2,000,000

43            Total

44  (577319) Riverboat Landing Phase III, Planning and Construction

45            (Jefferson)

46            Payable from General Obligation Bonds

47            Priority 2                                             $  476,000

48            Priority 5                                             $ 4,000,000

49            Total                                                  $ 4,476,000

                            Page 118 of 174
    HB NO. 2                                                                 ENROLLED

1   (577320) Wastewater Treatment Plant Improvements, Planning and

2             Construction

3             (Jefferson)

4             Payable from General Obligation Bonds

5             Priority 2                                                  $ 1,000,000

6             Priority 5                                                  $ 4,503,500

7             Total                                                       $ 5,503,500

8   (577322) Park Land and Improvements, Including Improvements to

9             Existing Parks and Land Acquisition, Planning and

10            Construction

11            (Jefferson)

12            Payable from General Obligation Bonds

13            Priority 1                                                  $  336,038

14            Priority 5                                                  $ 1,000,000

15            Payable from the Balance of State General Fund (Direct)

16            Non-Recurring previously allocated under the authority

17            of Act 5 of 2024 for Fletcher Technical Community

18            College, Precision Agriculture Training Facility, Planning

19            and Construction

20            (Terrebonne)                                                $ 1,000,000

21            Total                                                       $ 2,336,038

22  (577324) Sala Avenue Street and Infrastructure Improvements

23            (Jefferson)

24            Payable from General Obligation Bonds

25            Priority 1                                                  $  184,400

26            Priority 5                                                  $  850,000

27            Total                                                       $ 1,034,400

28  (577325) The WHARF, Planning, Construction, and Site Preparation

29            (Jefferson)

30            Payable from General Obligation Bonds

31            Priority 1                                                  $ 2,502,867

32            Priority 5                                                  $ 2,200,000

33            Total                                                       $ 4,702,867

34  (577326) Emergency Preparedness Building, Planning and

35            Construction

36            (Jefferson)

37            Payable from General Obligation Bonds

38            Priority 1                                                  $  24,975

39  50/MV5 WHITE CASTLE

40  (577796) Street and Drainage Improvements, Planning and

41            Construction

42            (Iberville)

43            Payable from General Obligation Bonds

44            Priority 5                                                  $ 2,700,000

45  (578840) Training and Learning Center, Planning and Construction

46            (Iberville)

47            Payable from General Obligation Bonds

48            Priority 5                                                  $ 1,000,000

49            Payable from the Capital Outlay Savings Fund                $  500,000

50            Total                                                       $ 1,500,000

                                Page 119 of 174
    HB NO. 2                                                             ENROLLED

1   50/MV7 WINNFIELD

2   (578207) South Winnfield Drainage Improvements - Phase 1,

3             Planning and Construction

4             (Winn)

5             Payable from General Obligation Bonds

6             Priority 1                                              $  60,375

7             Priority 5                                              $  600,000

8             Total                                                   $  660,375

9   50/MV9 WISNER

10  (578437) Wastewater Treatment Plant Rehabilitation, Planning and

11            Construction

12            (Franklin)

13            Payable from General Obligation Bonds

14            Priority 1                                              $  200,000

15            Priority 5                                              $ 1,250,000

16            Total                                                   $ 1,450,000

17  50/MW2 YOUNGSVILLE

18  (577210) Langlinais Road Extension, Planning and Construction

19            (Lafayette)

20            Payable from General Obligation Bonds

21            Priority 5                                              $ 5,580,000

22  (577212) Fortune Road Extension, Planning and Construction

23            (Lafayette)

24            Payable from General Obligation Bonds

25            Priority 1                                              $ 2,811,038

26  (577213) Highway 89 Improvements, Planning and Construction

27            (Lafayette)

28            Payable from General Obligation Bonds

29            Priority 1                                              $ 5,978,531

30            Priority 5                                              $ 12,945,515

31            Total                                                   $ 18,924,046

32  (577214) Highway 92 Improvements, Planning and Construction

33            (Lafayette)

34            Payable from General Obligation Bonds

35            Priority 5                                              $ 5,405,000

36  (577215) Highway 92/Prescott Boulevard Roundabout, Design,

37            Planning, and Construction

38            (Lafayette)

39            Payable from General Obligation Bonds

40            Priority 5                                              $ 2,614,000

41  (577216) Wastewater System Improvements, Planning and

42            Construction

43            (Lafayette)

44            Payable from General Obligation Bonds

45            Priority 5                                              $ 4,500,000

46  (578841) New Fire Station, Planning and Construction

47            (Lafayette)

48            Payable from General Obligation Bonds

49            Priority 5                                              $ 3,250,000

                            Page 120 of 174
    HB NO. 2                                                             ENROLLED

1   50/MW3 ZACHARY

2   (577199) New Fire Station, Planning and Construction

3             (East Baton Rouge)

4             Payable from General Obligation Bonds

5             Priority 5                                              $ 1,600,000

6   50/MW6 ST. GABRIEL

7   (578846) City Council Chambers - New Construction

8             (Iberville)

9             Payable from General Obligation Bonds

10            Priority 1                                              $  496,214

11  50/MW8 CENTRAL

12  (577121) Wax Road, LA 3034, Extension, Planning and Construction

13            (East Baton Rouge)

14            Payable from General Obligation Bonds

15            Priority 2                                              $ 1,600,000

16            Priority 5                                              $ 1,600,000

17            Total                                                   $ 3,200,000

18  (578847) Administration Building

19            (East Baton Rouge)

20            Payable from General Obligation Bonds

21            Priority 1                                              $  16,943

22  50/N03 AUDUBON NATURE INSTITUTE, INC.

23  (577439) Audubon Facility Renovations and Improvements: Audubon

24            Zoo, Planning and Construction

25            (Orleans)

26            Payable from General Obligation Bonds

27            Priority 1                                              $ 19,000,000

28  (578811) Aububon Facility Renovations and Improvements

29            Riverfront for All, Planning and Construction

30            (Orleans)

31            Payable from General Obligation Bonds

32            Priority 5                                              $ 23,800,000

33  50/N04 NEW ORLEANS MUSEUM OF ART

34  (578204) Future NOMA, Planning and Construction

35            (Orleans)

36            Payable from General Obligation Bonds

37            Priority 1                                              $  500,000

38            Priority 5                                              $ 3,500,000

39            Total                                                   $ 4,000,000

40  50/N05 NEW ORLEANS EXHIBITION HALL AUTHORITY

41  (576996) Property Development Project

42            (Orleans)

43            Payable from General Obligation Bonds

44            Priority 1                                              $ 4,500,000
                                                                      $ 21,000,000
45            Priority 5                                              $ 25,500,000

46            Total

                                  Page 121 of 174
    HB NO. 2                                                           ENROLLED

1   50/N13 CHENNAULT INTERNATIONAL AIRPORT

2             AUTHORITY

3   (577856) Firewater Pumphouse #3 and Infrastructure, Planning and

4             Construction

5             (Calcasieu)

6             Payable from General Obligation Bonds

7             Priority 5                                               $ 6,000,000

8   50/N18 IBERIA PARISH AIRPORT AUTHORITY

9   (577557) Acadiana Regional Airport Improvements, Planning and

10            Construction

11            (Iberia)

12            Payable from General Obligation Bonds

13            Priority 1                                               $ 17,372,651

14            Priority 5                                               $ 23,000,000

15            Total                                                    $ 40,372,651

16  50/N19 PAUL S. MORTON SCHOLARSHIP FOUNDATION

17  (577434) Paul S. Morton Scholarship Foundation Greater Works

18            Family Life Center, Planning and Construction

19            (Orleans)

20            Payable from General Obligation Bonds

21            Priority 5                                               $ 6,200,000

22  50/N33 ENGLAND ECONOMIC & INDUSTRIAL

23            DEVELOPMENT DISTRICT

24  (578387) High Bay Aircraft Maintenance Hangar, Planning and

25            Construction

26            (Rapides)

27            Payable from General Obligation Bonds

28            Priority 1                                               $ 1,713,915

29            Priority 5                                               $ 15,425,000

30            Total                                                    $ 17,138,915

31  50/N34 ODYSSEY HOUSE LOUISIANA, INC.

32  (577686) Odyssey House Louisiana Gambling Treatment Center,

33            Acquisition and Renovation

34            (Orleans)

35            Payable from General Obligation Bonds

36            Priority 5                                               $ 7,000,000

37  (577859) Odyssey House Louisiana Renovation Project, Planning and

38            Construction

39            (Orleans)

40            Payable from General Obligation Bonds

41            Priority 1                                               $ 4,871,958

42            Priority 5                                               $ 2,000,000

43            Total                                                    $ 6,871,958

                            Page 122 of 174
    HB NO. 2                                                               ENROLLED

1   50/N40 LAFAYETTE ECONOMIC DEVELOPMENT

2             AUTHORITY

3   (577863) Lafayette Innovation Center, Planning and Construction

4             (Lafayette)

5             Payable from General Obligation Bonds

6             Priority 1                                                $ 3,661,342

7             Priority 5                                                $ 5,000,000

8             Total                                                     $ 8,661,342

9   50/N41 BATON ROUGE METROPOLITAN AIRPORT

10  (578023) Airport Aviation Business Park, Planning and Construction

11            (East Baton Rouge)

12            Payable from General Obligation Bonds

13            Priority 1                                                $ 1,686,902

14            Priority 5                                                $ 4,750,000

15            Total                                                     $ 6,436,902

16  (578024) Relocation of LA 67 at LA 408 due to Airport

17            Improvements

18            (East Baton Rouge)

19            Payable from General Obligation Bonds

20            Priority 5                                                $ 80,000,000

21  50/N52 LAFAYETTE PARISH SHERIFF'S OFFICE

22  (577332) Law Enforcement Center, Planning and Construction

23            (Lafayette)

24            Payable from General Obligation Bonds

25            Priority 5                                                $ 46,500,000

26  (577333) Range Upgrades, Planning and Construction

27            (Lafayette)

28            Payable from General Obligation Bonds

29            Priority 5                                                $ 8,363,000

30  (577334) Crime Scene and Evidence Storage/Fitness Center, Planning

31            and Construction

32            (Lafayette)

33            Payable from General Obligation Bonds

34            Priority 1                                                $ 2,010,000

35  50/N53 ORLEANS PARISH COMMUNICATIONS DISTRICT

36  (577221) Orleans Parish Communications District Expansion Project,

37            Planning and Construction

38            (Orleans)

39            Payable from General Obligation Bonds

40            Priority 5                                                $ 33,600,000

41  50/N71 NORTH LAFOURCHE CONSERVATION LEVEE AND

42            DRAINAGE DISTRICT

43  (578028) Jessee Dufrene/Homeplace FDA, Phase II,

44            Levee Improvements, Planning and Construction

45            (Lafourche)

46            Payable from General Obligation Bonds

47            Priority 5                                                $ 5,500,000

48            Payable from the Capital Outlay Savings Fund              $  200,000

49            Total                                                     $ 5,700,000

                                  Page 123 of 174
    HB NO. 2                                                                 ENROLLED

1   (578029) Raceland Prairie Levee Improvements,

2             Planning and Construction

3             (Lafourche)

4             Payable from General Obligation Bonds

5             Priority 5                                                  $ 4,975,000
                                                                          $ 1,000,000
6             Payable from the Capital Outlay Savings Fund                $ 5,975,000

7             Total

8   50/N72 RIVER ROAD AFRICAN AMERICAN MUSEUM

9   (578726) River Road African American Museum, Planning and

10            Construction

11            (Ascension)

12            Payable from General Obligation Bonds

13            Priority 5                                                  $ 1,500,000

14            Payable from the Capital Outlay Savings Fund                $  500,000

15            Total                                                       $ 2,000,000

16  50/N74 NATIONAL WORLD WAR II MUSEUM, INC.

17  (577514) Eight Projects under FP&C Management Plus Liberation

18            Pavilion: Bricks and Mortar, Exhibit Fabrication, Media

19            Production, Planning and Construction

20            (Orleans)

21            Payable from General Obligation Bonds

22            Priority 1                                                  $ 10,255,333

23            Priority 5                                                  $ 8,000,000

24            Total                                                       $ 18,255,333

25  50/N79 TANGIPAHOA PARISH FIRE DISTRICT 1

26  (578848) Bruce Cutrer Regional Fire Training Facility of Tangipahoa

27            Parish, Planning and Construction

28            (Tangipahoa)

29            Payable from General Obligation Bonds

30            Priority 1                                                  $ 2,122,710

31  50/N93 NORTHEAST LOUISIANA RAILROAD

32            DEVELOPMENT DISTRICT

33  (576693) Northeast Louisiana Railroad Development District,

34            Planning and Construction

35            (Tensas)

36            Payable from General Obligation Bonds

37            Priority 1                                                  $ 1,000,000
                                                                          $ 9,000,000
38            Priority 5                                                  $ 10,000,000

39            Total

40  50/N99 AMITE RIVER BASIN COMMISSION

41  (577935) Upper Amite River Flood Risk Reduction and Restoration,

42            Planning and Construction

43            (East Baton Rouge, East Feliciana, Livingston, St. Helena)

44            Payable from General Obligation Bonds

45            Priority 1                                                  $ 4,000,000

46            Priority 5                                                  $ 63,000,000

47            Total                                                       $ 67,000,000

                            Page 124 of 174
    HB NO. 2                                                             ENROLLED

1   50/NA3 AVOYELLES PARISH AIRPORT AUTHORITY

2   (578670) Runway Extension Marksville Municipal Airport, Planning

3             and Construction

4             (Avoyelles)

5             Payable from General Obligation Bonds

6             Priority 5                                              $ 2,200,000

7             Payable from State General Fund (Direct) Non-Recurring

8             Revenues                                                $  240,000

9             Total                                                   $ 2,440,000

10  50/NAA POINTE COUPEE COUNCIL ON AGING

11  (577222) Senior Center, Planning and Construction

12            (Pointe Coupee)

13            Payable from General Obligation Bonds

14            Priority 1                                              $ 2,153,013

15            Priority 5                                              $ 1,000,000

16            Payable from State General Fund (Direct) Non-Recurring

17            Revenues                                                $  130,000

18            Total                                                   $ 3,283,013

19  50/NAD MU ZETA FOUNDATION, INC.

20  (578849) Expansion Project, Planning and Construction

21            (East Baton Rouge)

22            Payable from General Obligation Bonds

23            Priority 1                                              $  175,769

24  50/NAJ EFFORTS OF GRACE, INC.

25  (578850) Ashe Too, Planning and Construction

26            (Orleans)

27            Payable from General Obligation Bonds

28            Priority 1                                              $  45,000

29  50/NAV MADE IN AMERICA, INC.

30  (578803) Construction of a Small Business Incubator, Community

31            Health Clinic, and Workforce Training Center, Planning

32            and Construction

33            (Caddo)

34            Payable from General Obligation Bonds

35            Priority 1                                              $  999,595

36            Priority 5                                              $ 9,000,000

37            Total                                                   $ 9,999,595

38  50/NAY OGDEN MUSUEM OF SOUTHERN ART

39  (578676) Ogden Museum of Southern Art Renovation, Planning

40            and Construction

41            (Orleans)

42            Payable from General Obligation Bonds

43            Priority 5                                              $ 21,315,000

44            Payable from State General Fund (Direct) Non-Recurring

45            Revenues                                                $ 1,461,000

46            Total                                                   $ 22,776,000

                                  Page 125 of 174
    HB NO. 2                                                              ENROLLED

1   50/NAZ HOSPICE OF ACADIANA FOUNDATION, INC.

2   (578851) Calcutta House, Planning and Construction

3             (Lafayette)

4             Payable from General Obligation Bonds

5             Priority 5                                               $  600,000

6   50/NB1 CENTER FOR INNOVATIVE TRAINING OF YOUTH

7   (578763) STEM NOLA's Innovation Hub, Planning and Construction

8             (Orleans)

9             Payable from General Obligation Bonds

10            Priority 1                                               $  500,000

11            Priority 5                                               $ 7,300,000

12            Total                                                    $ 7,800,000

13  50/NB3 MCKINLEY HIGH SCHOOL ALUMNI ASSOCIATION

14  (578620) McKinley Alumni Center in Baton Rouge- Major safety

15            repairs, system replacements, facility upgrades and

16            renovations, Planning and Construction

17            (East Baton Rouge)

18            Payable from the Capital Outlay Savings Fund             $  362,000

19  50/NB8 LEWISBURG BELLEVUE WATER SYSTEM

20  (577577) Community Water Distribution and Safety Infrastructure

21            Improvements Project, Planning and Construction

22            (St. Landry)

23            Payable from General Obligation Bonds

24            Priority 5                                               $ 1,680,000

25  (578852) Water System Meters Water Tower Refurbishment

26            Infrastructure, Planning and Construction

27            (St. Landry)

28            Payable from General Obligation Bonds

29            Priority 1                                               $  950,000

30  50/NBF COMMUNITY RECEIVING HOME, INC.

31  (578853) Rapides Parish Juvenile Justice Complex, Planning and

32            Construction

33            (Rapides)

34            Payable from General Obligation Bonds

35            Priority 5                                               $ 25,300,000

36  50/NBJ JONESVILLE FIRE DISTRICT

37  (578715) New Fire Station at U.S. Hwy 84 and 3rd Street, Planning

38            and Construction

39            (Catahoula)

40            Payable from General Obligation Bonds

41            Priority 1                                               $  800,000

                                  Page 126 of 174
    HB NO. 2                                                                ENROLLED

1   50/NC2 BATON ROUGE RECREATION AND PARKS

2             COMMISSION

3   (577107) Baton Rouge Gallery, Contemporary Art Center at City

4             Park, Planning and Construction

5             (East Baton Rouge)

6             Payable from General Obligation Bonds

7             Priority 5                                                 $ 10,000,000

8   50/NC3 ST. TAMMANY PARISH SHERIFF

9   (578585) Training Facility, Planning and Construction

10            (St. Tammany)

11            Payable from General Obligation Bonds

12            Priority 5                                                 $ 18,000,000

13  50/NC4 BERWICK/BAYOU VISTA WATERWORKS

14  (579031) Renovations to Berwick/Bayou Vista Joint Water

15            Treatment Facility, Planning and Construction

16            (St. Mary)

17            Payable from General Obligation Bonds

18            Priority 2                                                 $  30,000

19            Priority 5                                                 $  270,000

20            Payable from the Capital Outlay Saving Fund                $  100,000

21            Total                                                      $  400,000

22  50/NCF TECHE ACTION BOARD, INC.

23  (578475) Construction and Completion of New Health Center

24            Facility for Teche Action Clinic at Gramercy in Gramercy,

25            LA, Planning and Construction

26            (St. James)

27            Payable from General Obligation Bonds

28            Priority 5                                                 $ 3,700,000

29  50/NCM FIFTH WARD RECREATION DISTRICT OF ST.

30            HELENA PARISH

31  (578256) Recreation District Baseball Fields, Planning and

32            Construction

33            (St. Helena)

34            Payable from General Obligation Bonds

35            Priority 1                                                 $  950,417

36            Priority 5                                                 $ 1,000,000

37            Total                                                      $ 1,950,417

38  50/NCR LAFAYETTE PARISH WATERWORKS DISTRICT-

39            NORTH

40  (577463) Water Filtration Plant Construction

41            (Lafayette)

42            Payable from General Obligation Bonds

43            Priority 5                                                 $ 6,475,000

                                  Page 127 of 174
    HB NO. 2                                                               ENROLLED

1   50/ND3 ORLEANS PARISH SHERIFF'S OFFICE

2   (578806) OJC Plumbing Replacement, Planning and

3             Construction

4             (Orleans)

5             Payable from General Obligation Bonds

6             Priority 2                                                $  500,000

7   50/ND5 LAFOURCHE PARISH WATER DISTRICT

8   (578941) Kraemer Water Line Upgrades, Planning and Construction

9             (Lafourche)

10            Payable from General Obligation Bonds

11            Priority 5                                                $ 1,500,000

12  50/ND8 BOSSIER PARISH SHERIFF

13  (578738) Regional Response Vehicle Driving Track,

14            Planning and Construction

15            (Bossier)

16            Payable from General Obligation Bonds

17            Priority 2                                                $  594,500

18            Priority 5                                                $ 2,805,500

19            Total                                                     $ 3,400,000

20  50/ND9 NORTHEAST LOUISIANA CHILDREN'S MUSEUM

21  (578118) Northeast Louisiana Children's Museum Relocation,

22            Land Acquisition, Real Estate, Planning and Construction

23            (Ouachita)

24            Payable from General Obligation Bonds

25            Priority 5                                                $ 2,500,000

26  (578910) Northeast Louisiana Children's Museum, Planning and

27            Construction

28            (Ouachita)

29            Payable from General Obligation Bonds

30            Priority 5                                                $ 7,500,000

31            Payable from the Capital Outlay Savings Fund              $  500,000

32            Total                                                     $ 8,000,000

33  50/NDN OPPORTUNITIES INDUSTRIALIZATION CENTER

34            INCORPORATED OF OUACHITA

35  (578861) New Education Building, Planning and Construction

36            (Ouachita)

37            Payable from General Obligation Bonds

38            Priority 1                                                $ 1,231,775

39  50/NDQ TANGIPAHOA AFRICAN AMERICAN HERITAGE

40            MUSEUM AND VETERANS' ARCHIVES

41  (578862) Tangipahoa African American Heritage Museum Roof

42            Replacement, Planning and Construction

43            (Tangipahoa)

44            Payable from General Obligation Bonds

45            Priority 5                                                $  540,000

                            Page 128 of 174
    HB NO. 2                                                                ENROLLED

1   50/NDX NEW ORLEANS COUNCIL ON AGING, INC.

2   (576701) New Orleans Council on Aging Office and Senior

3             Community Center, Planning, Purchase, and Renovation

4             of a Building and/or Acquire Land and Construct a New

5             Building

6             (Orleans)

7             Payable from General Obligation Bonds

8             Priority 1                                                 $ 2,850,000

9             Payable from the Capital Outlay Savings Fund               $  500,000

10            Total                                                      $ 3,350,000

11  50/NDY JEFFERSON DAVIS WATER AND SEWER

12            DISTRICT COMMISSION #1

13  (577815) Water System Improvements, Planning and Construction

14            (Jefferson Davis)

15            Payable from General Obligation Bonds

16            Priority 1                                                 $ 2,000,000

17            Priority 5                                                 $ 4,200,000

18            Total                                                      $ 6,200,000

19  50/NE4 JEFFERSON PARISH CORONER'S OFFICE

20  (578612) Advanced Forensic Center Project, Planning and

21            Construction

22            (Jefferson)

23            Payable from General Obligation Bonds

24            Priority 5                                                 $ 6,000,000

25  50/NEE BIOMEDICAL RESEARCH AND INNOVATION PARK

26  (577506) Biomedical Research and Innovation Park Building, Planning

27            and Construction

28            (Ouachita)

29            Payable from General Obligation Bonds

30            Priority 1                                                 $ 8,290,798

31            Priority 2                                                 $ 7,000,000

32            Priority 5                                                 $ 9,900,000

33            Total                                                      $ 25,190,798

34  50/NER ST. HELENA PARISH HOSPITAL SERVICE

35            DISTRICT NO. 1

36  (577776) Hospital Renovation, Expansion, and Equipment

37            Replacement, Planning and Construction

38            (St. Helena)

39            Payable from General Obligation Bonds

40            Priority 1                                                 $ 3,647,583

41  50/NEV HOSPITAL SERVICE DISTRICT 1 TERREBONNE

42            PARISH

43  (578942) Emergency Power System Replacement and Upgrade,

44            Planning and Construction

45            (Terrebonne)

46            Payable from General Obligation Bonds

47            Priority 5                                                 $ 15,000,000

48            Payable from the Capital Outlay Savings Fund               $  800,000

49            Total                                                      $ 15,800,000

                                 Page 129 of 174
    HB NO. 2                                                                  ENROLLED

1   50/NEY ORLEANS PARISH HOSPITAL SERVICE

2             DISTRICT A

3   (578550) Parish Hospital Service District for the Parish of Orleans -

4             District A - Behavioral Health Service Line Expansion,

5             Planning and Construction

6             (Orleans)

7             Payable from General Obligation Bonds

8             Priority 1                                                   $ 3,200,000

9   50/NF6 ST. MARTIN PARISH SHERIFF

10  (578699) Training Barracks and Records Retention Facility,

11            Planning and Construction

12            (St. Martin)

13            Payable from General Obligation Bonds

14            Priority 5                                                   $ 3,300,000

15  50/NF7 ST. MARTIN SEWER AND WATER

16  (579032) Belle River Wastewater Treatment Plant,

17            Planning and Construction

18            (St. Martin)

19            Payable from General Obligation Bonds

20            Priority 2                                                   $  50,000

21            Priority 5                                                   $  450,000

22            Payable from the Capital Outlay Savings Fund                 $  400,000

23            Total                                                        $  900,000

24  50/NFE CAJUNDOME

25  (577522) Cajundome and Convention Center Indoor Air Quality

26            Improvements, Planning and Construction

27            (Lafayette)

28            Payable from General Obligation Bonds

29            Priority 1                                                   $ 6,364,182

30  Provided, however, that $500,000 of the Priority 1 appropriation shall be used to fund the

31  Louisiana Basketball Coaches Association historical memorabilia project at the Cajundome.

32  50/NFJ H/A ALLIANCE

33  (579024) Open Health Care Clinic, Renovations to Airline

34            Hwy. Clinic Location, Planning and Construction

35            (East Baton Rouge)

36            Payable from General Obligation Bonds

37            Priority 2                                                   $  250,000

38            Priority 5                                                   $ 2,750,000

39            Total                                                        $ 3,000,000

40  50/NFQ ALGIERS DEVELOPMENT DISTRICT

41  ()        West Bank Park Improvements Including New Soccer
              and Recreational Facilities, Planning and Construction
42            (Orleans)
              Payable from General Obligation Bonds
43
                  Priority 1
44                Priority 5
              Total
45                                                                         $ 2,678,389
                                                                           $ 11,225,400
46                                                                         $ 13,903,789

47

48  Pending submittal and approval of a capital outlay budget request pursuant to the provisions

49  of R.S. 39:112.

                                  Page 130 of 174
    HB NO. 2                                                           ENROLLED

1   50/NFX THE O.W. DILLON TRAINING AND COMMUNITY

2             DEVELOPMENT CENTER, INC.

3   (577949) The O.W. Dillon Training and Community Development

4             Center Building, Planning and Construction

5             (Tangipahoa)

6             Payable from General Obligation Bonds

7             Priority 1                                            $ 1,179,207

8             Priority 5                                            $ 4,500,000

9             Total                                                 $ 5,679,207

10  50/NFZ OUR LADY OF LOURDES REGIONAL MEDICAL

11            CENTER

12  (578687) Our Lady of Lourdes Regional Medical Center, Planning

13            and Construction

14            (Lafayette)

15            Payable from General Obligation Bonds

16            Priority 1                                            $ 4,500,000

17            Priority 5                                            $ 8,500,000

18            Total                                                 $ 13,000,000

19  50/NGG YWCA OF GREATER NEW ORLEANS

20  (579017) Construction Project, Planning and Construction

21            (Orleans)

22            Payable from General Obligation Bonds

23            Priority 5                                            $ 6,750,000

24  50/NGM NEW ORLEANS AFRICAN AMERICAN MUSEUM

25            OF ART, CULTURE AND HISTORY

26  (578943) New Orleans African American Museum of Art, Culture

27            and History: Renovation and New Construction

28            (Orleans)

29            Payable from General Obligation Bonds

30            Priority 1                                            $  343,299

31            Priority 5                                            $ 4,000,000

32            Total                                                 $ 4,343,299

33  50/NGN LOUISIANA CHAMBER OF COMMERCE

34            FOUNDATION, INC.

35  (578972) Louisiana Chamber of Commerce's Business Innovation

36            Center, Planning and Construction

37            (Calcasieu)

38            Payable from General Obligation Bonds

39            Priority 1                                            $ 1,644,795

40  50/NGO MARY BIRD PERKINS CANCER CENTER

41  (578989) Securing the Future of Cancer Center in Ascension

42            Parish, Planning and Construction

43            (Ascension)

44            Payable from General Obligation Bonds

45            Priority 2                                            $  500,000

46            Priority 5                                            $ 3,000,000

47            Total                                                 $ 3,500,000

                                Page 131 of 174
    HB NO. 2                                                               ENROLLED

1   50/NGQ THE STRAND THEATRE OF SHREVEPORT

2             CORPORATION

3   (577246) Repair and Renovation to the Strand Theatre of Shreveport

4             (Caddo)

5             Payable from General Obligation Bonds

6             Priority 5                                                $  984,000

7   50/NH7 CEMETERY MAINTENANCE ZACHARY

8   (578864) Public Cemetery Maintenance, Planning and Construction

9             (East Baton Rouge)

10            Payable from General Obligation Bonds

11            Priority 5                                                $ 3,750,000

12  50/NHE ST. JAMES PARISH HOSPITAL

13  (578579) West Bank Health Clinic, Planning and Construction

14            (St. James)

15            Payable from General Obligation Bonds

16            Priority 1                                                $ 2,789,295
                                                                        $ 7,900,000
17            Priority 5                                                $ 10,689,295

18            Total

19  50/NHG LAFAYETTE CENTRE DEVELOPMENT DISTRICT

20  (578525) Downtown Lafayette Public Infrastructure Improvements and

21            Upgrades, Planning and Construction

22            (Lafayette)

23            Payable from General Obligation Bonds

24            Priority 1                                                $  400,099

25  50/NI7 HOSPITAL SERVICE DISTRICT 1 IBERIA PARISH

26            DBA IBERIA MEDICAL CENTER

27  (578757) Addition of Medical, Surgical, and Psychiatric Inpatient

28            Rooms, Planning, Construction, and Equipment

29            (Iberia)

30            Payable from General Obligation Bonds

31            Priority 1                                                $ 7,149,828

32  50/NI9 ASCENSION-ST. JAMES AIRPORT AND

33            TRANSPORTATION AUTHORITY

34  (578031) Commercial Hangar Complex - Louisiana Regional

35            Airport, Gonzales, LA, Planning and Construction

36            (Ascension)

37            Payable from General Obligation Bonds

38            Priority 5                                                $ 1,000,000

39  (578865) Drinking Water, Fire Suppression, and ADA Compliance -

40            Louisiana Regional Airport, Gonzales, LA, Planning and

41            Construction

42            (Ascension)

43            Payable from General Obligation Bonds

44            Priority 1                                                $  131,378

                                  Page 132 of 174
    HB NO. 2                                                             ENROLLED

1   50/NJ1 NEW ORLEANS MILITARY AND MARITIME

2             ACADEMY

3   (576513) Campus Expansion Phase I - Development, Planning and

4             Construction

5             (Orleans)

6             Payable from General Obligation Bonds

7             Priority 5                                              $ 22,400,000

8   50/NJ6 WIL REACH ONE FOUNDATION

9   (578866) Center for High-Quality Early Learning in New Orleans,

10            Planning and Construction

11            (Orleans)

12            Payable from General Obligation Bonds

13            Priority 5                                              $ 1,000,000

14            Payable from the Capital Outlay Savings Fund            $  750,000

15            Total                                                   $ 1,750,000

16  50/NJL BASTION COMMUNITY OF RESILIENCE

17  (578869) Veterans Wellness Facility in New Orleans, Planning and

18            Construction

19            (Orleans)

20            Payable from General Obligation Bonds

21            Priority 1                                              $  263,257

22  50/NKA ABBEVILLE GENERAL HOSPITAL

23  (578132) Expansion and Modernization of the Ambulatory Surgery

24            and Obstetrics/Delivery Departments, Planning and

25            Construction

26            (Vermilion)

27            Payable from General Obligation Bonds

28            Priority 1                                              $ 3,200,000

29  50/NKQ THIBODAUX REGIONAL HEALTH SYSTEM

30  (577225) Emergency Power System Replacement and Upgrade,

31            Planning and Construction

32            (Lafourche)

33            Payable from General Obligation Bonds

34            Priority 2                                              $ 4,300,000

35            Priority 5                                              $ 15,800,000

36            Total                                                   $ 20,100,000

37  50/NL1 BEAUREGARD PARISH WATER WORKS

38            DISTRICT #2

39  (577267) Booster Station Upgrades, Planning and Construction

40            (Beauregard)

41            Payable from General Obligation Bonds

42            Priority 1                                              $  250,000

43            Priority 5                                              $  830,000

44            Total                                                   $ 1,080,000

                            Page 133 of 174
    HB NO. 2                                                               ENROLLED

1   50/NLO OUR LADY OF THE ANGELS HOSPITAL

2   (577119) Medical Office Building, Planning and Construction

3             (Washington)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 4,400,000

6   50/NLT ST. TAMMANY PARISH HOSPITAL SERVICE DISTRICT

7             NO. 1 DBA ST. TAMMANY HEALTH SYSTEM

8   (577734) Parking Garage and Helipad, Planning and Construction

9             (St. Tammany)

10            Payable from General Obligation Bonds

11            Priority 5                                                $ 10,000,000

12  (578090) Exterior Hospital Building Hardening, Planning and

13            Construction

14            (St. Tammany)

15            Payable from General Obligation Bonds

16            Priority 5                                                $  210,000

17  (578091) Roof and HVAC Replacements, Planning and

18            Construction

19            (St. Tammany)

20            Payable from General Obligation Bonds

21            Priority 5                                                $  320,000

22  50/NLX LAKE CHARLES MEMORIAL HOSPITAL

23  (578700) Main Campus Mechanical Upgrades,

24            Planning and Construction

25            (Calcasieu)

26            Payable from General Obligation Bonds

27            Priority 2                                                $  250,000

28            Priority 5                                                $  750,000

29            Total                                                     $ 1,000,000

30  50/NM9 ANTIOCH BAPTIST CHURCH

31  (578284) Historic Restoration Project, Planning and Construction

32            (Caddo)

33            Payable from General Obligation Bonds

34            Priority 5                                                $ 2,000,000

35  50/NMB CALCASIEU PARISH WATER WORKS DISTRICT 1

36  (577287) Water Wells for Plants A and B, Planning and Construction

37            (Calcasieu)

38            Payable from General Obligation Bonds

39            Priority 5                                                $ 2,500,000

40  50/NMW BEAUREGARD PARISH SHERIFF

41  (577261) Emergency Operations Center, Planning and Construction

42            (Beauregard)

43            Payable from the Capital Outlay Savings Fund              $  600,000

                             Page 134 of 174
    HB NO. 2                                                               ENROLLED

1   50/NNK PIERRE PART BELLE RIVER MUSEUM

2   (577062) Pierre Part Belle River Museum, Planning and Construction

3             (Assumption)

4             Payable from General Obligation Bonds

5             Priority 5                                                $ 2,000,000

6             Payable from the Capital Outlay Savings Fund              $  250,000

7             Total                                                     $ 2,250,000

8   50/NNN CONSOLIDATED GRAVITY DRAINAGE DISTRICT NO. 1

9   (577284) Lateral W-3 Improvements, Planning and Construction

10            (Calcasieu)

11            Payable from General Obligation Bonds

12            Priority 5                                                $ 2,250,000

13  50/NNW BEAUREGARD PARISH WATERWORKS DISTRICT 3

14  (577270) Texas Eastern Road Water Line Replacement,

15            Planning and Construction

16            (Beauregard)

17            Payable from General Obligation Bonds

18            Priority 5                                                $ 1,060,000

19            Payable from the Capital Outlay Savings Fund              $  200,000

20            Total                                                     $ 1,260,000

21  50/NNX PLAQUEMINES PARISH SHERIFFS OFFICE

22  (579013) Detention Center Security Upgrade,

23            Planning and Construction

24            (Plaquemines)

25            Payable from the Capital Outlay Savings Fund              $ 1,750,000

26  Pending submittal of a capital outlay budget request pursuant to the provisions of R.S.

27  39:112.

28  50/NP1 ACADIANA CRIMINALISTICS LABORATORY

29            DISTRICT

30  (577611) New Crime Laboratory, Planning, Design, Construction,

31            and Equipment

32            (Iberia)

33            Payable from General Obligation Bonds

34            Priority 1                                                $  75,371

35  50/NPB FRIENDS OF CROWVILLE

36  (576997) Community Center Improvements, Planning and

37            Construction

38            (Franklin)

39            Payable from General Obligation Bonds

40            Priority 5                                                $  565,000

41            Payable from State General Fund (Direct) Non-Recurring

42            Revenues                                                  $  100,000

43            Payable from the Capital Outlay Savings Fund              $ 1,235,000

44            Total                                                     $ 1,900,000

                             Page 135 of 174
    HB NO. 2                                                           ENROLLED

1   50/NPD IBERIA ECONOMIC DEVELOPMENT AUTHORITY

2   (577447) Progress Point Business Park and Airport Gateway, Land

3             Acquisition, Planning and Construction

4             (Iberia)

5             Payable from General Obligation Bonds

6             Priority 1                                               $ 5,003,402

7             Priority 2                                               $ 1,200,000

8             Priority 5                                               $ 1,600,000

9             Total                                                    $ 7,803,402

10  50/NPE THE LOUISIANA MUSIC AND HERITAGE

11            EXPERIENCE, INC.

12  (578441) The Louisiana Music and Heritage Experience, Inc.,

13            Planning and Construction

14            (Orleans)

15            Payable from General Obligation Bonds

16            Priority 5                                               $ 25,000,000

17  50/NQ2 GRAVITY DRAINAGE DISTRICT 6 CALCASIEU

18            PARISH

19  (577285) Buxton Creek Drainage Improvements, Planning and

20            Construction

21            (Calcasieu)

22            Payable from General Obligation Bonds

23            Priority 1                                               $ 4,100,000
                                                                       $ 2,000,000
24            Priority 5                                               $ 6,100,000

25            Total

26  50/NQG LAFAYETTE METROPOLITAN EXPRESSWAY

27            COMMISSION

28  (576584) Lafayette Loop Project, Planning and Construction

29            (Lafayette)

30            Payable from General Obligation Bonds

31            Priority 5                                               $ 2,500,000

32  50/NQN LSU REAL ESTATE AND FACILITIES FOUNDATION

33  (578734) University Lakes Restoration Project to Address Flood

34            Control, Environmental, Safety, Health and Other Issues

35            (Matching Funds)

36            (East Baton Rouge)

37            Payable from General Obligation Bonds

38            Priority 1                                               $ 18,292,437

39            Priority 5                                               $ 5,000,000

40            Payable from State General Fund (Direct) Non-Recurring

41            Revenues                                                 $ 2,000,000

42            Total                                                    $ 25,292,437

43  50/NQV BEAUREGARD WATERWORKS DISTRICT #6

44  (577282) Water System Improvements, Planning and Construction

45            (Beauregard)

46            Payable from General Obligation Bonds

47            Priority 5                                               $ 1,000,000

                                  Page 136 of 174
    HB NO. 2                                                                ENROLLED

1   50/NR7 COMMCARE CORPORATION

2   (577093) Wynhoven Health Care Expansion, including St. Andrew's

3             Village, Planning and Construction

4             (Jefferson)

5             Payable from General Obligation Bonds

6             Priority 1                                                 $ 5,427,716

7             Priority 5                                                 $ 3,999,500

8             Total                                                      $ 9,427,216

9   50/NRD SOUTH BEAUREGARD RECREATION DISTRICT NO. 2 OF WARDS

10  4 AND 6

11  (577790) Multi-Purpose Recreation Facilities Improvements,

12            Planning and Construction

13            (Beauregard)

14            Payable from General Obligation Bonds

15            Priority 5                                                 $ 1,800,000

16  50/NRU EAST BATON ROUGE COUNCIL ON AGING

17  (578527) Lotus Village at the Lakes Senior Community, Planning,

18            Development and Construction

19            (East Baton Rouge)

20            Payable from General Obligation Bonds

21            Priority 2                                                 $ 1,000,000

22            Priority 5                                                 $ 7,684,000

23            Total                                                      $ 8,684,000

24  (578643) Lotus Village Phase II (Acquisition, Planning,

25            Rehabilitation, and Construction)

26            (East Baton Rouge)

27            Payable from General Obligation Bonds

28            Priority 2                                                 $ 1,550,000
                                                                         $ 1,550,000
29            Priority 5                                                 $ 3,100,000

30            Total

31  50/NS7 HABITAT NOLA

32  (578686) Rising Oaks - Infrastructure for Housing Phase II and III,

33            Planning and Construction

34            (Jefferson)

35            Payable from General Obligation Bonds

36            Priority 2                                                 $  500,000

37            Priority 5                                                 $ 2,500,000

38            Total                                                      $ 3,000,000

39  50/NSP EDEN HOUSE

40  (577102) Emergency Housing and Services for Human Trafficking

41            Survivors

42            (Orleans)

43            Payable from General Obligation Bonds

44            Priority 5                                                 $ 11,000,000

45            Payable from State General Fund (Direct) Non-Recurring

46            Revenues                                                   $ 3,000,000

47            Total                                                      $ 14,000,000

                                  Page 137 of 174
    HB NO. 2                                                                ENROLLED

1   (578870) New Orleans Emergency Shelter, Planning and Construction

2             (Orleans)

3             Payable from General Obligation Bonds

4             Priority 1                                                 $  850,000

5   50/NST DOWNTOWN DEVELOPMENT DISTRICT NEW

6             ORLEANS

7   (578945) Harmony Circle, Planning and Construction

8             (Orleans)

9             Payable from General Obligation Bonds

10            Priority 5                                                 $ 4,000,000

11  50/NT7 CITIZENS MEDICAL CENTER

12  (577294) Expansion of Emergency Department, ICU, and Imaging,

13            Planning, Design, and Construction

14            (Caldwell)

15            Payable from General Obligation Bonds

16            Priority 1                                                 $ 2,500,000

17            Priority 2                                                 $ 2,000,000

18            Priority 5                                                 $ 11,900,000

19            Payable from the Capital Outlay Savings Fund               $ 2,000,000

20            Total                                                      $ 18,400,000

21  50/NTA EAST CARROLL PARISH SHERIFF'S OFFICE

22  (578128) Training and Recreation Center, Planning and Construction

23            (East Carroll)

24            Payable from General Obligation Bonds

25            Priority 1                                                 $ 3,000,000

26            Priority 5                                                 $ 9,000,000

27            Total                                                      $ 12,000,000

28  50/NU2 LOUISIANA ENDOWMENT FOR THE HUMANITIES

29  (577733) Critical Repairs and Restoration of Historic Turners Hall,

30            Planning and Construction

31            (Orleans)

32            Payable from General Obligation Bonds

33            Priority 5                                                 $ 2,000,000

34  50/NU9 9TH WARD STADIUM, INC.

35  (578871) Multi-Sport Venue in Eastern New Orleans and Lower

36            Ninth Ward, Planning and Construction

37            (Orleans)

38            Payable from General Obligation Bonds

39            Priority 1                                                 $ 3,314,617

40            Priority 2                                                 $  700,000

41            Total                                                      $ 4,014,617

42  50/NUQ LOUISIANA HIBERNIAN CHARITY

43  (578872) Four Acre Irish Heritage Park in the Lakeview

44            Neighborhood, Planning and Construction

45            (Orleans)

46            Payable from General Obligation Bonds

47            Priority 1                                                 $  183,522

                              Page 138 of 174
    HB NO. 2                                                               ENROLLED

1   50/NV1 POLLOCK AREA WATER SYSTEM, INC.

2   (578467) Water Production System Improvements, Planning

3             and Construction

4             (Grant)

5             Payable from General Obligation Bonds

6             Priority 5                                                $  510,000

7             Payable from the balance of the Capital Outlay Savings

8             Fund previously allocated under the authority of Act 465

9             of 2023 for South Grant Water Corporation, Water

10            Production System Improvements, East Well #2,

11            Planning and Construction (Grant)                         $  390,000

12            Total                                                     $  900,000

13  50/NVK UNION GENERAL HOSPITAL

14  (577631) CT Scanner Replacement and Diagnostic Image

15            Enhancement Project, Planning and Construction

16            (Union)

17            Payable from the Capital Outlay Savings Fund              $  500,000

18  50/NVY WASHINGTON PARISH HOSPITAL SERVICE

19            DISTRICT NO. 1

20  (577755) Emergency Upgrades including Power Generation System

21            Upgrade, Mechanical Systems, and Roofing, Planning and

22            Construction

23            (Washington)

24            Payable from General Obligation Bonds

25            Priority 1                                                $  347,498

26            Priority 5                                                $ 3,100,000

27            Payable from the Capital Outlay Savings Fund              $  500,000

28            Total                                                     $ 3,947,498

29  50/NWG CHILDREN'S ADVOCACY NETWORK, INC.

30  (578388) Children's Advocacy Network Campus, Planning and

31            Construction

32            (Rapides)

33            Payable from General Obligation Bonds

34            Priority 5                                                $ 2,000,000

35  50/NWO AIRPORT DISTRICT 1 OF CALCASIEU PARISH

36  (578414) Airport Entrance and Access Road Improvements and

37            Marquee, Planning and Construction

38            (Calcasieu)

39            Payable from General Obligation Bonds

40            Priority 1                                                $ 1,000,000

41  50/NWR LOUISIANA SWAMP BASE, INC.

42  (577226) Camp Atchafalaya Swamp Base, Planning, Design, and

43            Construction

44            (St. Martin)

45            Payable from General Obligation Bonds

46            Priority 1                                                $  470,858

47            Priority 5                                                $ 9,000,000

48            Total                                                     $ 9,470,858

                                Page 139 of 174
    HB NO. 2                                                             ENROLLED

1   50/NWS LAFAYETTE CENTRAL PARK, INC.

2   (577227) Lafayette Central Park Improvements, Planning and

3             Construction

4             (Lafayette)

5             Payable from General Obligation Bonds

6             Priority 1                                              $  500,000

7             Priority 5                                              $ 5,137,000

8             Total                                                   $ 5,637,000

9   50/NWT CENTRAL ST. LANDRY ECONOMIC DEVELOPMENT

10            DISTRICT

11  (577836) Harry Guilbeau Road (LA 3233) Wastewater Improvements-

12            Central St. Landry Economic Development District

13            (CSLEDD), Planning and Construction

14            (St. Landry)

15            Payable from General Obligation Bonds

16            Priority 5                                              $ 9,000,000

17  50/NXI HEBERT WATER SYSTEM, INC.

18  (577621) Water System Improvements, Planning and Construction

19            (Caldwell)

20            Payable from General Obligation Bonds

21            Priority 1                                              $ 1,213,583

22            Priority 5                                              $ 1,500,000

23            Payable from State General Fund (Direct) Non-Recurring

24            Revenues                                                $ 1,000,000

25            Total                                                   $ 3,713,583

26  50/NXS BATON ROUGE GENERAL MEDICAL CENTER

27  (577538) EmPATH Unit Implementation at Baton Rouge General

28            Mid City, Planning and Construction

29            (East Baton Rouge)

30            Payable from General Obligation Bonds

31            Priority 5                                              $ 1,200,000

32            Payable from the Capital Outlay Savings Fund            $ 1,000,000

33            Total                                                   $ 2,200,000

34  50/NXT THE 18TH WARD

35  (578596) Hollygrove Community Center Renovation, Planning and

36            Construction

37            (Orleans)

38            Payable from State General Fund (Direct) Non-Recurring

39            Revenues                                                $  65,000
                                                                         30,000
40            Payable from the Capital Outlay Savings Fund            $  95,000

41            Total                                                   $

42  50/NYJ ALLEN PARISH HOSPITAL

43  (578498) Allen Parish Hospital - Phase 1 Build Out, Planning

44            and Construction

45            (Allen)

46            Payable from General Obligation Bonds

47            Priority 5                                              $ 5,200,000

48            Payable from the Capital Outlay Savings Fund            $  200,000

49            Total                                                   $ 5,400,000

                                  Page 140 of 174
    HB NO. 2                                                              ENROLLED

1   50/NYP SECOND HARVEST FOOD BANK OF GREATER

2             NEW ORLEANS AND ACADIANA

3   (578873) Roof Replacement and HVAC Installation, Planning and

4             Construction

5             (Jefferson)

6             Payable from General Obligation Bonds

7             Priority 1                                               $  352,888

8   50/NYS HOLY ROSARY REDEVELOPMENT

9   (578664) Holy Rosary Institute, Planning, Construction, and

10            Restoration

11            (Lafayette)

12            Payable from General Obligation Bonds

13            Priority 1                                               $ 3,518,859
                                                                       $ 1,000,000
14            Priority 2                                               $ 4,200,000
                                                                       $ 8,718,859
15            Priority 5

16            Total

17  50/NZ3 BEAUREGARD MEMORIAL HOSPITAL

18  (578874) Emergency Department Addition and Renovation and

19            Women's Center Renovation, Planning and Construction

20            (Beauregard)

21            Payable from General Obligation Bonds

22            Priority 5                                               $ 2,700,000

23  50/NZB LIVINGSTON PARISH AIRPORT DISTRICT

24  (578448) Livingston Executive Airport, Planning and Construction

25            (Livingston)

26            Payable from General Obligation Bonds

27            Priority 1                                               $ 5,678,820

28            Priority 5                                               $ 4,650,000

29            Total                                                    $ 10,328,820

30  50/NZX WEST CALCASIEU CAMERON HOSPITAL

31  (578768) West Calcasieu Cameron Hospital Medical Office Building,

32            Planning and Construction

33            (Calcasieu)

34            Payable from General Obligation Bonds

35            Priority 1                                               $  264,063

36            Priority 5                                               $ 4,022,000

37            Total                                                    $ 4,286,063

38  50/R05 INDUSTRIAL DEVELOPMENT BOARD OF

39            LAFOURCHE

40  (577880) Lockport Marine Manufacturing Electrical Utility

41            Modernization Project, Planning and Construction

42            (Lafourche)

43            Payable from General Obligation Bonds

44            Priority 1                                               $ 13,000,000

                            Page 141 of 174
    HB NO. 2                                                               ENROLLED

1   50/R11 TANGIPAHOA PARISH SHERIFF

2   (578722) Multipurpose Facility, Planning and Construction

3             (Tangipahoa)

4             Payable from the balance of General

5             Obligation Bond Proceeds previously allocated

6             under the authority of Act 465 of 2023 for

7             St. James Parish, Storm Damage Repair to Dock

8             on Blind River, Planning and Construction

9             (St. James)                                               $  248,989

10            Payable from the balance of General

11            Obligation Bond Proceeds previously allocated

12            under the authority of Act 2 of 2020 for

13            Cajundome HVAC Pneumatic Systems,

14            Renovations and Replacements

15            (Lafayette)                                               $  52,733

16            Payable from the Capital Outlay

17            Savings Fund                                              $ 1,000,000

18            Total                                                     $ 1,301,722

19  50/R12 WATSON MEMORIAL SPIRIT TEMPLE

20  (578630) Watt Algiers Memorial Spirit Temple,

21            Planning and Construction

22            (Orleans)

23            Payable from General Obligation Bonds

24            Priority 5                                                $ 5,850,000

25            Payable from the Capital Outlay Savings Fund              $  650,000

26            Total                                                     $ 6,500,000

27  50/R21 SMILEY XTREME MEASURES, INC.

28  (578485) Reconstruction of a Building for Mixed Use,

29            Commercial and Housing Rental, Planning and Construction

30            (Caddo)

31            Payable from the Capital Outlay Savings Fund              $  217,000

32  50/R26 HIGHLAND CENTER CORPORATION

33  (578706) Community Center Accessibility, Planning and Construction

34            (Caddo)

35            Payable from the Capital Outlay Savings Fund              $  100,000

36  50/R27 KEMPER AND LEILA WILLIAMS FOUNDATION

37  (578420) The Historic New Orleans Collection Emergency

38            Readiness and Facility Repairs, Planning

39            and Construction

40            (Orleans)

41            Payable from General Obligation Bonds

42            Priority 2                                                $  250,000

43            Priority 5                                                $ 4,250,000

44            Total                                                     $ 4,500,000

                                Page 142 of 174
    HB NO. 2                                                              ENROLLED

1   50/R28 AVOYELLES PARISH WATERWORKS DISTRICT 1

2   (577737) Water Distribution System, Planning and Construction

3             (Avoyelles)

4             Payable from General Obligation Bonds

5             Priority 5                                               $ 1,750,000

6             Payable from State General Fund (Direct)                 $  400,000

7             Total                                                    $ 2,150,000

8   50/R31 NORTHSHORE CHARTER SCHOOLS

9   (578377) New School Campus Project, Planning and Construction

10            (Washington)

11            Payable from General Obligation Bonds

12            Priority 5                                               $ 12,500,000

13            Payable from the Capital Outlay Savings Fund             $  500,000

14            Total                                                    $ 13,000,000

15  50/R36 JEFFERSON DAVIS WATER DISTRICT 4

16  (577903) Potable Water Supply Improvements, Planning and

17            Construction

18            (Jefferson Davis)

19            Payable from General Obligation Bonds

20            Priority 5                                               $ 1,640,000

21            Payable from the Capital Outlay Savings Fund             $  100,000

22            Total                                                    $ 1,740,000

23  50/R37 PEOPLE'S HOUSING + INC.

24  (578751) LaSalle Street Resilience Hub, Planning and Construction

25            (Orleans)

26            Payable from General Obligation Bonds

27            Priority 2                                               $  100,000

28            Priority 5                                               $  900,000

29            Total                                                    $ 1,000,000

30  50/R49 A GOOD DEED FOUNDATION

31  (577881) North Baton Rouge Food Access and Community

32            Development, Planning and Construction

33            (East Baton Rouge)

34            Payable from General Obligation Bonds

35            Priority 2                                               $ 1,000,000

36            Priority 5                                               $ 16,200,000

37            Payable from the Capital Outlay Savings Fund             $  800,000

38            Total                                                    $ 18,000,000

39  50/R54 HOSPITAL SERVICE DISTRICT NO. 1 EAST BATON ROUGE

40  (578597) Da Vinci 5 Surgical Robot System,

41            Planning and Construction

42            (East Baton Rouge)

43            Payable from General Obligation Bonds

44            Priority 2                                               $  625,000

45            Priority 5                                               $ 1,875,000

46            Total                                                    $ 2,500,000

                                  Page 143 of 174
    HB NO. 2                                                     ENROLLED

1   (578599) Behavioral Health Outpatient Clinic,

2             Planning and Construction

3             (East Baton Rouge)

4             Payable from General Obligation Bonds

5             Priority 2                                      $  250,000

6             Priority 5                                      $  750,000

7             Total                                           $ 1,000,000

8   (578601) Obstetrics - Gynecology Clinic Major Renovation

9             and Expansion, Planning and Construction

10            (East Baton Rouge)

11            Payable from General Obligation Bonds

12            Priority 2                                      $  170,000

13            Priority 5                                      $ 1,530,000

14            Total                                           $ 1,700,000

15  50/R56 WASHINGTON PARISH SHERIFF'S OFFICE

16  (578666) Emergency Operations Center and Jail,

17            Planning and Construction

18            (Washington)

19            Payable from General Obligation Bonds

20            Priority 5                                      $ 27,000,000

21            Payable from the Capital Outlay Savings Fund    $  500,000

22            Total                                           $ 27,500,000

23  50/R57 ULL ECONOMIC DEVELOPMENT

24  (577528) LA Hub Complex Development, Planning

25            and Construction

26            (Lafayette)

27            Payable from General Obligation Bonds

28            Priority 5                                      $ 10,000,000

29  50/R58 HARBOR CENTER DISTRICT

30  (578468) Replacement of HVAC Duct Work and Exterior

31            Doors/Frame Extensive Repair to Exterior EIFS

32            Wall and Framing, and Purchase of Chairs for

33            Newly Built Meeting/Event Space,

34            Planning and Construction

35            (St. Tammany)

36            Payable from the Capital Outlay Savings Fund    $  500,000

37  50/R66 GIVING HOPE, INC.

38  (578364) Food Pantry and Resource Center

39            of Jefferson Parish, Planning and Construction

40            (Jefferson)

41            Payable from General Obligation Bonds

42            Priority 5                                      $ 3,775,000

43            Payable from the Capital Outlay Savings Fund    $  425,000

44            Total                                           $ 4,200,000

                                  Page 144 of 174
    HB NO. 2                                                    ENROLLED

1   50/R72 NATCHITOCHES PARISH HOSPITAL SERVICE DISTRICT 1

2   (578644) Healthcare Infrastructure Investment: NRMC

3             Ambulatory Tower, Planning and Construction

4             (Natchitoches)

5             Payable from General Obligation Bonds

6             Priority 5                                     $ 16,600,000
                                                             $ 1,000,000
7             Payable from State General Fund (Direct)       $ 2,000,000
                                                             $ 19,600,000
8             Payable from the Capital Outlay Savings Fund

9             Total

10  50/R75 CAMERON GRAVITY DRAINAGE DISTRICT #9

11  (578111) Schoolhouse Marsh Control Structure,

12            Planning and Construction

13            (Cameron)

14            Payable from General Obligation Bonds

15            Priority 2                                     $  250,000

16            Priority 5                                     $ 1,615,160

17            Payable from the Capital Outlay Savings Fund   $  50,000

18            Total                                          $ 1,915,160

19  50/R78 PROJECT 70805, INC

20  (578765) Ghost Kitchen Redevelopment at Former Ace

21            Cleaners (2504 Scenic Highway) including

22            Planning, Land Acquisition, Brownfield

23            Remediation, Design Development, Permitting,

24            Construction and Equipment

25            (East Baton Rouge)

26            Payable from General Obligation Bonds

27            Priority 5                                     $ 2,000,000

28  50/R80 COMMUNITY POWER SOUTH

29  (578355) Williams Memorial CME Temple - Resilience Hub,

30            Planning and Construction

31            (Caddo)

32            Payable from the Capital Outlay Savings Fund   $  225,000

33  (578356) Cedar Grove Friendship House - Resilience Hub,

34            Planning and Construction

35            (Caddo)

36            Payable from the Capital Outlay Savings Fund   $  250,000

37  (578360) Mt. Olive Baptist Church Resilience Hub,

38            Planning and Construction

39            (Calcasieu)

40            Payable from Capital Outlay Savings Fund       $  200,000

41  50/R87 LAFAYETTE PARISH WATERWORKS DISTRICT SOUTH

42  (578608) Water System Improvements, Planning and

43            Construction

44            (Lafayette)

45            Payable from General Obligation Bonds

46            Priority 5                                     $ 1,100,000

47            Payable from the Capital Outlay Savings Fund   $  500,000

48            Total                                          $ 1,600,000

                                  Page 145 of 174
    HB NO. 2                                                              ENROLLED

1   50/R92 START CORPORATION

2   (578731) Community Health Center French Quarter Parking,

3             Planning and Construction

4             (Orleans)

5             Payable from General Obligation Bonds

6             Priority 5                                               $ 3,000,000

7             Payable from the Capital Outlay Savings Fund             $  500,000

8             Total                                                    $ 3,500,000

9   50/RA7 MAGNOLIA COMMUNITY SERVICES

10  (578974) Whitehall Renovation and Upgrades - Magnolia

11            Community Services, Planning and Construction

12            (Jefferson)

13            Payable from the Capital Outlay Savings Fund             $ 2,390,000

14  Pending submittal and approval of a capital outlay budget request pursuant to the provisions

15  of R.S. 39:112.

16  50/RA9 WATT VILLAS

17  (578994) Watt Villas, Planning and Construction

18            (Orleans)

19            Payable from General Obligation Bonds

20            Priority 1                                               $  300,000

21            Priority 5                                               $ 2,700,000

22            Total                                                    $ 3,000,000

23  50/RB1 VOLUNTEERS OF AMERICA OF SOUTHEAST LOUISIANA

24  (579019) Integrated Health Care Hub Adjacent to

25            BioDistrict New Orleans, Planning and Construction

26            (Orleans)

27            Payable from General Obligation Bonds

28            Priority 2                                               $  550,000

29            Priority 5                                               $ 6,000,000

30            Total                                                    $ 6,550,000

31  50/S10 CALCASIEU PARISH SCHOOL BOARD

32  (578372) Moss Bluff Elementary - Student Carpool Improvements-

33            Calcasieu Parish School Board, Planning and

34            Construction

35            (Calcasieu)

36            Payable from the Capital Outlay Savings Fund             $  900,000

37  (578761) Renovations to Lake Charles Boston Stadium, Planning and

38            Construction

39            (Calcasieu)

40            Payable from General Obligation Bonds

41            Priority 1                                               $  167,000

42            Priority 5                                               $  823,000

43            Total                                                    $  990,000

                            Page 146 of 174
    HB NO. 2                                                               ENROLLED

1   50/S16 DESOTO PARISH SCHOOL BOARD

2   (578714) DeSoto Parish School Board - North DeSoto Turning Lane,

3             Planning and Construction

4             (DeSoto)

5             Payable from State General Fund (Direct) Non-Recurring

6             Revenues                                                  $  113,000

7             Payable from the Capital Outlay Savings Fund              $  900,000

8             Total                                                     $ 1,013,000

9   50/S26 JEFFERSON PARISH SCHOOL BOARD

10  (578528) Bridge/Crossing to Access Airline Highway (Bunche

11            Elementary Airline Crossing), Planning and Construction

12            (Jefferson)

13            Payable from the Capital Outlay Savings Fund              $  200,000

14  50/S32 LIVINGSTON PARISH SCHOOL BOARD

15  (578678) Arts and Multipurpose Facility, Planning and Construction

16            (Livingston)

17            Payable from General Obligation Bonds

18            Priority 2                                                $  735,000

19  50/S39 POINTE COUPEE PARISH SCHOOL BOARD

20  (578875) Pointe Coupee Parish School Board Office Relocation,

21            to be Located at 8777 Morganza Highway, Formerly

22            Labarre Elementary School Site, Due to Flooding Caused

23            by Hurricane Gustav, Planning and Construction

24            (Pointe Coupee)

25            Payable from General Obligation Bonds

26            Priority 1                                                $ 4,153,560

27            Priority 5                                                $ 2,000,000

28            Total                                                     $ 6,153,560

29  50/S59 WASHINGTON PARISH SCHOOL BOARD

30  (577539) Thomas Elementary School Cafeteria Expansion and

31            Classroom Building, Planning and Construction

32            (Washington)

33            Payable from General Obligation Bonds

34            Priority 5                                                $ 6,000,000

35            Payable from the Capital Outlay Savings Fund              $  500,000

36            Total                                                     $ 6,500,000

37  50/S63 WEST FELICIANA PARISH SCHOOL BOARD

38  (578876) Julius Freyhan Cultural/Conference Center, Planning and

39            Construction

40            (West Feliciana)

41            Payable from General Obligation Bonds

42            Priority 1                                                $  20,139

                                Page 147 of 174
    HB NO. 2                                                        ENROLLED

1   50/S67 CENTRAL COMMUNITY SCHOOL SYSTEM

2   (578049) Central City Community Sports Complex Infrastructure,

3             and School Board Administration Building and Meeting

4             Room, Planning and Construction

5             (East Baton Rouge)

6             Payable from General Obligation Bonds

7             Priority 5                                            $ 2,000,000

8   ()        Central Community School System Multi-Use
              Activity Center, Recreational Facility, Planning
9             and Construction
              (East Baton Rouge)
10            Payable from General Obligation Bonds

11                Priority 2
                  Priority 5
12            Payable from the Capital Outlay Savings Fund
              Total
13                                                                  $ 3,600,000
                                                                    $ 9,800,000
14                                                                  $ 1,200,000
                                                                    $ 14,600,000
15

16

17  Pending submittal of a capital outlay budget request pursuant to the provisions of R.S.

18  39:112.

19            (B) Notwithstanding the provisions of R.S. 39:101, 102, and 112(C), projects

20  included in Section 1(A) of this Act which did not submit a capital outlay application by

21  November 1, 2025, in compliance with the provisions of R.S. 39:101 and 102 and which

22  have not received late approval as required by R.S. 39:112(C) are hereby deemed to have

23  until June 5, 2026, to submit a capital outlay budget request application pursuant to R.S.

24  39:101(A), and if the application is submitted by that date, the project is deemed to have

25  complied with the late approval requirements of R.S. 39:112(C). Additionally, the capital

26  outlay budget requests together with supporting information and documents for these

27  projects shall constitute the feasibility study required by Article VII, Section 11(C) of the

28  Constitution of Louisiana.

29            (C) Appropriated Debt Projects. The projects in this Section are to be funded

30  through the sale of bonds and secured by or payable from state appropriation.

31  01/107 DIVISION OF ADMINISTRATION

32  (578324) Purchase and Renovation of Buildings Statewide

33            (Statewide)

34            Payable from Revenue Bonds                            $ 125,000,000

35            Notwithstanding anything contained in this Capital Outlay Act, or any previous

36  Capital Outlay Act to the contrary, or any other provision of law, the Division of

37  Administration may finance the design, construction, furnishing and equipping of facilities

38  through the issuance of revenue bonds by the Office Facilities Corporation to be secured by

                                  Page 148 of 174
    HB NO. 2                                                 ENROLLED

1   and payable from State appropriations. The issuance of such revenue bonds shall require the

2   approval of the State Bond Commission.

3             Section 2. The expenditure of funds appropriated in this Act shall be in

4   conformity to all existing statutes relative to public bidding, contractual review, and R.S.

5   39:101 through 128 and any other statutes affecting the capital outlay program for state

6   government, state institutions, and political entities.

7             Section 3. Payment for projects specified in this Act must be made by warrant

8   submitted to the division of administration, Department of Transportation and Development,

9   the state treasurer or other administering agency as provided in Section 8, whichever is

10  appropriate, only to the extent of funds required for immediate payment. Copies of invoices

11  or other supporting documentation shall be submitted with warrants. In the event that any

12  equipment included in this Act, is procured pursuant to the provisions of the State Lease-

13  Purchase Act, R.S. 39:1761 et seq., the amounts included in this Act for each such piece of

14  equipment shall not be appropriated. The provisions of R.S. 39:1771 which require

15  equipment to be leased under the State Lease-Purchase Act to be included in the executive

16  budget and approved by the legislature through inclusion in the General Appropriation Act

17  shall be considered waived upon the inclusion of such equipment in this Act. Projects

18  contained in this Act may, at the direction of the division of administration and with the

19  approval of the State Bond Commission, alternatively be funded through financing programs

20  heretofore or hereafter provided by a public trust and public corporation duly organized

21  pursuant to R.S. 9:2341 et seq., having for its beneficiary the state and the Louisiana Local

22  Government Environmental Facilities and Community Development Authority, pursuant to

23  R.S. 33:4548.1 et seq.

24            Section 4. If at any time during the Fiscal Year 2026-2027, the governor should

25  find, or the Joint Legislative Committee on the Budget or the commissioner of

26  administration should report to the governor, that the receipts of the treasury are falling short

27  or appear likely to fall short of the revenue estimates for the fiscal year and that a cash

28  deficit is likely to be incurred, the governor shall take such steps as deemed necessary to

29  prevent the occurrence of a cash deficit. In the event that a capital outlay project funded in

30  this Act falls under an agency which is abolished or for which funds are not appropriated in

31  the 2026-2027 General Appropriation Act, then the funds appropriated in this Act for such

                            Page 149 of 174
    HB NO. 2                                                                ENROLLED

1   capital outlay projects shall not be expended unless deemed necessary by the governor to

2   protect life or property. In the event that legislation is enacted which transfers facilities or

3   programs for which projects are funded in this Act, on behalf of one agency, institution,

4   department, or management board to another agency, institution, department, or management

5   board, then the projects in this Act shall be deemed transferred also.

6             Section 5. All monies appropriated by this Act and any applicable funds of a

7   prior capital outlay budget act adopted by the legislature shall be deposited by the state

8   treasurer in the Comprehensive Capital Outlay Escrow Account, established by this Section,

9   in the state treasury. In accordance with R.S. 36:764, no later than sixty days following the

10  end of each quarter, the state treasurer shall report to the Joint Legislative Committee on the

11  Budget and the commissioner of administration, all funds contained in the Miscellaneous

12  Fund of the Comprehensive Capital Outlay Escrow Account. Notwithstanding any

13  provisions contained herein or other law to the contrary, any original issue premium or

14  accrued interest proceeds received pursuant to the sale of general obligation bonds shall

15  remain on deposit to the credit of the Bond Security and Redemption Fund until such time

16  as they may be utilized in accordance with U.S. Department of the Treasury Regulations

17  promulgated pursuant to the Internal Revenue Code of 1986. All such monies shall be

18  administered according to the particular act pertaining to the fiscal year in which such

19  monies were appropriated. If it is determined by the director of the Office of Facility

20  Planning and Control, Division of Administration, that the funds appropriated by this Act

21  or any prior capital outlay budget Act are not sufficient to complete the projects contained

22  in any capital outlay budget Act, through unavoidable deficiencies in appropriation,

23  including administrative and legal requirements, the commissioner of administration, subject

24  to approval of the Joint Legislative Committee on the Budget, may direct the use of interest

25  earned from the investment of general obligation bond or note proceeds in the

26  Comprehensive Capital Outlay Escrow Account, not to exceed an aggregate of five million

27  dollars in any one fiscal year, for the purpose of completing the projects contained in any

28  capital outlay budget Act and such money shall be deemed appropriated in specific amounts

29  necessary for such purpose. All appropriations in this Act which are made as additions to

30  funds for previously authorized projects shall be included, for accounting purposes, in the

31  account of the previously authorized projects. If it is determined by the director of the Office

              Page 150 of 174
    HB NO. 2                                              ENROLLED

1   of Facility Planning and Control, Division of Administration, that it is cost effective and

2   practical to combine individual appropriations, the commissioner of administration, subject

3   to the approval of the Joint Legislative Committee on the Budget, may direct that two or

4   more appropriations or parts thereof may be combined into a single project for accounting

5   and audit purposes. The commissioner of administration may direct that funding in the

6   various statewide and/or multiple parish projects for improvements for state facilities may

7   be transferred to any project, in this Act or any previFus Capital Outlay Act, which require

8   supplemental funding for improvements for state facilities which qualify for funding through

9   the various statewide and/or multiple parish projects for improvements for state facilities.

10  The Office of Facility Planning and Control, Division of Administration is authorized to

11  receive settlements and vendor rebates and to add a portion or all of these receipts to the

12  existing project funds relating to the settlement and/or vendor rebates and appropriated in

13  this Act or any previous Capital Outlay Act including those previously appropriated funds

14  that become unavailable. Approval of the Joint Legislative Committee on the Budget will

15  be obtained if the settlement and/or vendor rebates will be added to any projects in this Act

16  or any previous Capital Outlay Act which are unrelated to the project from which the

17  settlement and/or vendor rebates were received. The Office of Facility Planning and Control,

18  Division of Administration is authorized to receive insurance payments and are hereby

19  authorized to immediately repair facilities that suffer insurance losses without those projects

20  being included in the Act and shall report to the Joint Legislative Committee on the Budget

21  any expenditures from insurance funds received pursuant to this section. A portion, as

22  determined by the commissioner of administration and not to exceed one percent (1%), of

23  the funding for projects which qualify for the Percent for Art Program and not to exceed

24  $450,000 for an individual, qualifying project, may be transferred from the qualifying

25  project budgets, to the Department of Culture, Recreation and Tourism for costs of acquiring

26  art and administering the program. For all Percent for Art Program projects in this or any

27  previous capital outlay, up to ten percent (10%) of the aforementioned one percent (1%) may

28  be used for the costs of administering the projects.

29            Section 6. No later than February 1, 2027, agencies administering capital outlay

30  projects will submit reports identifying completed projects and cash balances to the Joint

              Page 151 of 174
    HB NO. 2                                                                       ENROLLED

1   Legislative Committee on Capital Outlay pursuant to the reporting requirements of R.S.

2   39:105 and R.S. 39:116.

3             Section 7. The commissioner of administration, with the approval of the Joint

4   Legislative Committee on the Budget, is authorized to supplement or substitute the

5   appropriations specified in this or previous capital outlay acts with any federal or other funds

6   which are or may become available and such funds shall be deemed appropriated in specific

7   amounts necessary for the purposes of this Act. Any funds received by the State Bond

8   Commission as a result of a prepayment of reimbursement contracts as authorized by law

9   and the policy and procedure for reimbursement contracts of the Department of Treasury,

10  office of State Bond Commission, shall be deposited as set forth in such policy and

11  procedure and shall be deemed available and appropriated in specific amounts necessary for

12  the purposes of this Act pursuant to the procedure set forth in this section.

13            Section 8.(A) All projects herein authorized and funded shall be subject to the

14  provisions of R.S. 39:101 through 128. With the exception of appropriations made to the

15  Department of Military Affairs, the Legislature, the Louisiana Stadium and Exposition

16  District, the Department of Economic Development, the Coastal Protection and Restoration

17  Authority, the Division of Administration for Supplemental State Funds for Local

18  Government Assistance Program, the Division of Administration for the Community Water

19  Enrichment Program, the Department of Transportation and Development, or the Office of

20  Louisiana Highway Construction, all funds herein appropriated shall be considered as having

21  been appropriated directly to the Office of Facility Planning and Control, Division of

22  Administration. All cooperative endeavor agreements for non-state entities shall be prepared

23  by the appropriate administering agency and submitted to the office of State Procurement

24  for review and approval. As part of its review, the office of State Procurement shall consult

25  with bond counsel to the State relative to any federal tax issues.

26            (1) Notwithstanding anything contained in this act to the contrary or any other

27  provision of law, the appropriations made for the Louisiana Stadium and Exposition District

28  shall be appropriated directly to the Louisiana Stadium and Exposition District, and are

29  public purposes pursuant to the provisions of Article VII, Section 14 of the Constitution of

30  Louisiana primarily for economic development, including the generation of tax revenue,

31  creation of jobs, and the generation of tourism, and may be used to reimburse any

                             Page 152 of 174
    HB NO. 2                                                                   ENROLLED

1   expenditure made prior to the granting of a line of credit or the sale of bonds by the State

2   Bond Commission, determination by the State Treasurer that cash funding has been

3   deposited in the Comprehensive Capital Outlay Escrow Account for the project.

4             (2) Further, with respect to appropriations to the Louisiana Stadium and

5   Exposition District for the TPC Louisiana, Planning and Construction project, the Louisiana

6   Stadium and Exposition District shall be permitted to use alternative competitive

7   procurement and delivery methods for the award of any contracts to be funded through such

8   appropriation.

9             (3) The Louisiana Stadium and Exposition District shall have the authority to

10  directly appoint a design professional from a list of a minimum of three architectural firms

11  or joint ventures with professional sports facility design experience acceptable to the

12  Commissioner of Administration and shall be exempt from other state requirements for

13  selection of designers. The design professional fee shall be in accordance with state

14  guidelines administered by the Office of Facility Planning and Control, Division of

15  Administration.

16            (B)(1)(a) Funds appropriated in the Capital Outlay Act under the name of non-

17  state entities shall be administered by the Office of Facility Planning and Control, Division

18  of Administration under cooperative endeavor agreements; however, projects involving state

19  or federal highways may be administered by the Department of Transportation and

20  Development, if appropriate. Except as provided in Section 8(A), cooperative endeavor

21  agreements entered into pursuant to appropriations in this Act shall not be required to be

22  submitted to the Division of Administration, Office of State Procurement.

23            (b) Further, for all projects in the Capital Outlay Act or a previous Capital

24  Outlay Act which are appropriated to the Office of Facility Planning and Control, Division

25  of Administration, including those administered by cooperative endeavor agreements, up to

26  six percent of each line-item may be used for costs of administering the projects.

27            (c) For all projects in Capital Outlay Act or a previous Capital Outlay Act

28  appropriated to the Department of Transportation and Development, up to six percent of

29  each line-item may be used for costs of administering the projects, or for field

30  engineering/construction supervision.

                     Page 153 of 174
    HB NO. 2                                                       ENROLLED

1             (d) For all projects in Capital Outlay Act or a previous Capital Outlay Act

2   appropriated to the Office of Louisiana Highway Construction, up to six percent of each

3   line-item may be used for costs of administering the projects, or for field

4   engineering/construction supervision.

5             (2) Notwithstanding anything in this Act, or a previous Capital Outlay Act, the

6   Office of Facility Planning and Control may enter into a cooperative endeavor agreement

7   with the Archdiocese of New Orleans and Jefferson Parish for the Preservation and

8   Restoration of Historic Structure for Hope Haven/Madonna Manor Campus, Planning and

9   Construction project.

10            (C) Line-item general obligation bond projects appropriated to the Department

11  of Transportation and Development in the Capital Outlay Act or a previous Capital Outlay

12  Act shall be authorized to draw Transportation Trust Funds from the Highway Program

13  appropriation, for supplemental funding on overruns in excess of the original estimated

14  project cost as determined by the Department of Transportation and Development, provided

15  however that said projects are in the state or federal highway system and in the priority

16  program, and the overrun is less than $50,000. Any such overrun of $50,000 or more must

17  be approved by the Joint Legislative Committee on the Budget.

18            (D) All ports, levee districts and other non-state entities must follow the

19  provisions of R.S. 39:122.

20            (E) Pursuant to R.S. 39:122(B)(2), funds to be reimbursed by the state which a

21  non-state entity attempts to obligate prior to the receipt of funding shall not be eligible for

22  reimbursement or payment by the state; however,

23            (1) Notwithstanding anything in this Act or any previous Capital Outlay Acts

24  to the contrary, contracts may be entered into for the Lafayette Economic Development

25  Authority, Lafayette Innovation Center (Lafayette) prior to the receipt of funding and the

26  State is authorized to financially participate in obligations created by such contracts.

27            (2) Notwithstanding anything contained in this Act or any other provision of law,

28  Lafayette Parish is authorized to execute contracts for all of Phase 1 and Phase 2 work that

29  includes the contract for Pre-Construction Services and Amendment No. 1 through

30  Amendment No. 9 for WBS Number F.50000897 for the Bayou Vermilion Flood Control

31  project prior to execution of a cooperative endeavor agreement, the granting of a line of

                                Page 154 of 174
    HB NO. 2                                                            ENROLLED

1   credit or the sale of bonds. Phase 1 and Phase 2 work that includes the contract for

2   Pre-Construction Services and Amendment No. 1 through Amendment No. 9 for WBS

3   Number F.50000897 for the Bayou Vermilion Flood Control project shall be exempt from

4   the requirements of R.S. 39:126. The appropriation for this project may be used to pay any

5   obligation incurred or to reimburse any expenditure made pursuant to such contracts unless

6   the Commissioner of Administration is advised by bond counsel to the state that such may

7   violate federal tax law. The office of facility planning and control shall consult with bond

8   counsel to the State relative to any federal tax issues.

9             (3) Notwithstanding anything contained in this Act or any other provision of law,

10  Lafayette Parish is authorized to execute contracts for the Parish Government Complex,

11  Parish Courthouse project prior to execution of a cooperative endeavor agreement, the

12  granting of a line of credit, or the sale of bonds. The appropriation for this project may be

13  used to pay any obligation incurred or to reimburse any expenditure made pursuant to such

14  contracts unless the Commissioner of Administration is advised by bond counsel to the state

15  that such may violate federal tax law. The office of facility planning and control shall consult

16  with bond counsel to the State relative to any federal tax issues.

17            (4) Notwithstanding anything contained in this Act or any previous Capital

18  Outlay Act or any provision of law to the contrary, contracts may be entered into for the

19  Acadia Parish, Street Improvements of Hains Road project prior to receipt of concurrence

20  by the Office of Facility Planning and Control and are excepted from bid opening extensions

21  associated with addenda to bidding documents and the state is authorized to financially

22  participate in obligations created for such project.

23            (5) Notwithstanding anything contained in this Act or any other provision of law,

24  the Port of Lake Charles is authorized to execute contracts for the Berths 4, 5, and 6 Wharf

25  and Shed Reconstruction at City Docks project prior to the granting of a line of credit or the

26  sale of bonds. The appropriation for this project may be used to pay any obligation incurred

27  or to reimburse any expenditure made pursuant to such contracts unless the Commissioner

28  of Administration is advised by bond counsel to the state that such may violate federal tax

29  law. The office of facility planning and control shall consult with bond counsel to the State

30  relative to any federal tax issues.

                                         Page 155 of 174
    HB NO. 2                                                              ENROLLED

1             (6) Notwithstanding anything contained in this Act or any previous Capital

2   Outlay Act or any provision of law to the contrary, contracts may be entered into for the City

3   of Slidell, Sewer Lift Station Upgrades at Grafton Dr. (PS 312), Breckenridge (PS 252), and

4   LaQuinta/Cracker Barrel (PS 202) project prior to receipt of concurrence by the Office of

5   Facility Planning and Control and are excepted from bid opening extensions associated with

6   addenda to bidding documents and the state is authorized to financially participate in

7   obligations created for such project.

8             (7) Notwithstanding anything contained in this Act or any previous Capital

9   Outlay Act or any provision of law to the contrary, contracts may be entered into for the

10  YMCA of Northwest Louisiana, Youth Sports Construction project prior to receipt of

11  concurrence by the Office of Facility Planning and Control and the state is authorized to

12  financially participate in obligations created for such project.

13            (F) Pursuant to R.S. 39:112(E)(2), non-state entity projects shall require a match

14  for each appropriation in this act; however,

15            (1) Notwithstanding anything contained in this Act, any prior Capital Outlay

16  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the projects for the

17  City of Opelousas for the Water Meter Replacement and Upgrades and for the Bridge

18  Replacement and Upgrades shall be exempt for all match requirements.

19            (2) Notwithstanding anything contained in this Act, any prior Capital Outlay

20  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for

21  Tensas Parish for the Recreation Facility shall be exempt from all match requirements.

22            (3) Notwithstanding anything contained in this Act, any prior Capital Outlay

23  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for the

24  East Carroll Parish Sheriff's Office for the Training and Recreation Center shall be exempt

25  from all match requirements.

26            (4) Notwithstanding anything contained in this Act, any prior Capital Outlay

27  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for

28  Oberlin for the Street Improvements, Phase I shall be exempt from all match requirements.

29            (5) Notwithstanding anything contained in this Act, any prior Capital Outlay

30  Acts, any other provisions of law, or the provisions of R.S. 39:112(E)(2), the project for the

                                  Page 156 of 174
    HB NO. 2                                                  ENROLLED

1   Fifth Ward Recreation District of St. Helena Parish for Recreation District Baseball Fields

2   shall be exempt from all match requirements.

3             (6) Notwithstanding anything contained in this Act, any prior Capital Outlay

4   Acts, any other provisions of law, or the provisions of R.S. 39:112(E)(2), the project for

5   Eunice for Renovations to City Hall/Police Department shall be exempt from all match

6   requirements

7             (7) Notwithstanding anything contained in this Act, any prior Capital Outlay

8   Acts, any other provisions of law, or the provisions of R.S. 39:112(E)(2), the project for East

9   Carroll Parish for Courthouse Improvements shall be exempt from all match requirements.

10            (8) Notwithstanding anything contained in this Act, any prior Capital Outlay

11  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for the

12  Amite River Basin Commission for the Upper Amite River Flood Risk Reduction and

13  Restoration shall be exempt from all match requirements.

14            (9) Notwithstanding anything contained in this Act, any prior Capital Outlay

15  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for

16  Opportunities Industrialization Center Incorporated of Ouachita for the New Education

17  Building shall be exempt from all match requirements.

18            (10) Notwithstanding anything contained in this Act, any prior Capital Outlay

19  Acts, any other provision of law, or the provisions of R.S. 39:112(E)(2), the project for

20  Gretna Government Complex Parking Lot, Planning and Construction shall be exempt from

21  all match requirements.

22            (G) Notwithstanding anything contained in this Act or the Capital Outlay Act

23  to the contrary or any other Act or provision of law, the appropriations made for the

24  Executive Department for facilities which promote economic development included in the

25  Repair, Restoration, and Replacement for Declared Disasters, Planning, Construction,

26  Renovation, and Acquisition project, and the Department of Economic Development projects

27  are for public purposes pursuant to the provisions of Article VII, Section 14 of the

28  Constitution of Louisiana primarily for economic development, including the generation of

29  tax revenues, creation of jobs, promotion of tourism, and creation of facilities for charitable,

30  cultural, artistic, educational, social, civic, research, service, economic development

31  activities, or provide facilities for professional golf events, pursuant to the terms of

                             Page 157 of 174
    HB NO. 2                            ENROLLED

1   cooperative endeavor agreements, including leases and all expenditures of these

2   appropriations and may be exempted, by the Commissioner of Administration, from all

3   statutes relative to public bidding, contractual review and the provisions of R.S.

4   33:9029.2(D) and in lieu thereof be allowed to use alternative competitive contracting

5   arrangements where the appropriate administering entity submits documentation to the

6   Commissioner of Administration substantiating that it is in the best interest of the citizens

7   of the state, due to economic and/or operational benefits, and the necessity to complete the

8   projects in a timely manner; and, the appropriate administering entity shall have the

9   authority to directly appoint the design professional from a list of a minimum of three design

10  firms or joint ventures with the appropriate specialized facility design experience submitted

11  to and acceptable to the Commissioner of Administration and shall be exempt from other

12  state requirements for selection of designers, and may include expenditures for computers,

13  fixtures, furniture, and other equipment as such is deemed to be capital outlay in nature, and

14  unless the Commissi(ner of Administration is advised by bond counsel to the State that such

15  may violate federal tax law, may be used to reimburse any expenditure made prior to the

16  granting of a line of credit or the sale of bonds by the State Bond Commission, determination

17  by the State Treasurer that cash funding has been deposited in the Comprehensive Capital

18  Outlay Escrow Account for the project or the execution of a cooperative endeavor agreement

19  from the Office of Facility Planning and Control, and may be used to acquire land or real

20  property, the title to which is held in the name of an entity exempt from taxation under the

21  provisions of 26 U.S.C. 501(c)(3).

22            (H) Notwithstanding any other provision of this Act or the Capital Outlay Act

23  or any other provision of law to the contrary, all of the funds herein appropriated to the

24  Department of Economic Development in connection with projects or programs for which

25  the Department of Economic Development utilizes a cooperative endeavor agreement to

26  further economic development as permitted under Article VII, Section 14 of the Louisiana

27  Constitution, including the generation of tax revenues and creation of jobs, shall be

28  considered as having been appropriated to the Department of Economic Development, may

29  be used to reimburse any expenditure made prior to the granting of a line of credit and made

30  prior to the execution of a cooperative endeavor agreement and shall be administered solely

31  by the Department of Economic Development pursuant to, in compliance with, and on the

              Page 158 of 174
    HB NO. 2                                                  ENROLLED

1   terms contained in such cooperative endeavor agreements without compliance with any other

2   law, including, but not limited to, the provisions of R.S. 39:101 through 128. Additionally,

3   all expenditures of these appropriations may be exempted by the Commissioner of

4   Administration, from all statutes relative to public bidding, contractual review and the

5   provisions of R.S. 33:9029.2(D).

6                 (I)(1) Notwithstanding any other provision of this Act or the Capital Outlay Act

7   or any other provision of law to the contrary, funds appropriated for the Economic

8   Development Award Program project for the Office of Business Development are to be used

9   solely for capital and infrastructure improvements subject to verification by the Division of

10  Administration, Office of Facility Planning and Control.

11                (2) Eligible expenses for Economic Development Award Program funds may

12  include documented project expenses beginning on the date of LEDC Board approval of the

13  project and may be reimbursed upon execution of the cooperative endeavor agreement for

14  the project.

15                (J)(1) Due to the state's current investment in TPC Louisiana and the financial

16  support it provides to the PGA TOUR event currently played at said facility, said PGA

17  TOUR event shall not be played at New Orleans City Park Golf Complex without the prior

18  agreement of the Commissioner of Administration and the Chairman of the Jefferson Parish

19  Council.

20                (2) Notwithstanding the foregoing, the City Park Golf Complex may host any

21  other golf tournament or event, including but not limited to any other PGA-affiliated or

22  sponsored tournament or event.

23                (K)(1) For all projects administered by the Office of Facility Planning and

24  Control and payable from proceeds of self-generated revenues, funds shall be remitted to the

25  Office of Facility Planning and Control for deposit in the state treasury at such time as may

26  be deemed necessary by the Office of Facility Planning and Control in order to cover the

27  amount of contracts or other project expenses.

28                (2) Notwithstanding any provisions contained herein or any other law to the

29  contrary, for projects with other means of financing provided to the administering agency

30  by interagency transfer, the authority to draw these funds shall remain with the user agency.

                                      Page 159 of 174
    HB NO. 2                                                            ENROLLED

1             (3) Any revenue bonds appropriated in Section 1 (A) or Section 1 (B) of the

2   Capital Outlay Act shall not be secured by the full faith and credit of the state.

3             (4) The State Treasurer shall refund to the appropriate source any surplus self-

4   generated funds, advanced insurance funds received by the Office of Facility Planning and

5   Control as Interagency Transfer from Office of Risk Management associated with hurricane

6   damage recovery, and interest earned on these funds, provided the Treasurer's Office is

7   notified, when these funds are deposited in the state treasury, that the user agency or Office

8   of Risk Management intends to request a refund of this interest.

9             (L) Notwithstanding any provisions contained in this Act, the Capital Outlay

10  Act, or any other provision of law to the contrary, any funds expended by the parish of St.

11  Mary for the purpose of securing a federal grant, for the Infrastructure Improvements and

12  Construction of a Welding Training Center Facility at the Charenton Canal Industrial Park,

13  shall be eligible for reimbursement from any cash line of credit approved for the project.

14            (M) Notwithstanding anything contained in this Act to the contrary or any other

15  provision of law, the resolution adopted by the Joint Legislative Committee on the Budget

16  (the committee) on March 19, 2019 approving State of Louisiana Grant Anticipation

17  Revenue Bonds, in one or more series, not exceeding $650,000,000, and approving the

18  related projects and providing for other matters in connection therewith, contains the

19  following approvals:

20            (1) The first series of bonds in the original principal amount of not exceeding

21  $185,000,000 in order to fund the following projects in the following estimated amounts:

22  Barksdale Project ($61,600,000) and portions of the Loyola Project ($77,600,000) and the

23  I-10 Project ($30,601,000) with the understanding that the Department has the ability to

24  manage the actual application of bond proceeds in order to appropriately fund the Projects

25  and meet expenditure requirements of the Internal Revenue Service.

26            (2) The second series of bonds for the express purpose of granting the required

27  contracts in the principal amount of approximately $142,000,000 in order to fund the

28  following projects in the following estimated amounts: the balance of the Barksdale Project

29  ($16,518,000), the balance of the Loyola Project ($87,500,000), portions of the I-10 Project

30  ($37,982,000) and the Belle Chasse Project ($12,500,000) with the understanding that the

31  Department has the ability to manage the actual application of Bond proceeds in order to

                          Page 160 of 174
    HB NO. 2                                                         ENROLLED

1   appropriately fund the Projects and meet expenditure requirements of the Internal Revenue

2   Service provided, however, the Department of Transportation and Development seeks

3   approval from the Committee for the issuance of the second series of bonds and all

4   subsequent series of bonds.

5             (N) Notwithstanding anything contained in this Act to the contrary or any other

6   provision of law, the Research Vessel (R/V) Pelican Replacement is deemed to be a capital

7   asset and the appropriation to Louisiana Universities Marine Consortium (LUMCON) to

8   replace the R/V Pelican is for a public purpose and has a significant economic impact

9   providing a variety of oceanographic research missions. Further, LUMCON shall be

10  permitted to use an alternative delivery method to award contracts for design of the proposed

11  replacement vessel. LUMCON shall have the authority to select the design professional from

12  a list of a minimum of two engineering firms or joint ventures with ship design experience

13  acceptable to the Commissioner of Administration and the selection shall be exempt from

14  other state requirements for the selection of designers. The design professional fee shall be

15  in accordance with state guidelines administered by the Office of Facility Planning and

16  Control, Division of Administration. LUMCON shall further be permitted to use an

17  alternative delivery method to award contracts for the construction of the proposed

18  replacement vessel. LUMCON shall have the authority to select the contractor from a list

19  of a minimum of three highly qualified ship builders/shipyards with relevant vessel

20  construction experience acceptable to the Commissioner of Administration and the selection

21  shall be exempt from other state requirements for the selection of contractors. The

22  construction contract shall be administered by the Office of Facility Planning and Control,

23  Division of Administration in accordance with state guidelines.

24            (O) Notwithstanding anything contained in this Act to the contrary or any other

25  provision of law, the appropriations for Major Repairs for Higher Education Facilities –

26  Infrastructure, and Buildings Based on Statewide Condition Assessment, Planning and

27  Construction, in Act 7 of the 2008 Second Extraordinary Session identifying specific

28  projects for higher education is deemed to be complete, and any remaining residual funds

29  are hereby authorized to be combined and accumulated to accomplish additional major repair

30  projects within the higher education systems, as deemed necessary and approved by the

31  Board of Regents and Facility Planning and Control. At the completion of the program,

                                 Page 161 of 174
    HB NO. 2                                                    ENROLLED

1   Facility Planning and Control shall submit a report to the Joint Legislative Committee on the

2   Budget concerning the use of the remaining residual funds.

3             (P) Notwithstanding anything contained in this Act or any other provision of

4   law, LSU Real Estate and Facilities Foundation (LRFF) is authorized to execute contracts

5   for the University Lakes Restoration Project to Address Flood Control, Environmental,

6   Safety, Health and Other Issues project prior to execution of a cooperative endeavor

7   agreement, the granting of a line of credit or the sale of bonds. The appropriation for this

8   project may be used to pay any obligation incurred or to reimburse any expenditure made

9   pursuant to such contracts unless the Commissioner of Administration is advised by bond

10  counsel to the state that such may violate federal tax law, after execution of a cooperative

11  endeavor agreement. The Office of Facility Planning and Control shall consult with bond

12  counsel to the State relative to any federal tax issues. Further, LRFF may use alternative

13  competitive contracting arrangements with the prior approval of the Commissioner of

14  Administration.

15            (Q) Notwithstanding anything contained in this Act to the contrary or any other

16  provision of law, the USS KIDD DD-661, a World War II era Fletcher class destroyer and

17  National Historic Landmark, is deemed to be a capital asset and the appropriation to the

18  Louisiana Naval War Memorial Commission for Hull Repair & Reinforcement,

19  Superstructure Repair, Interior Restoration & Painting and Docking Cradle Repairs &

20  Upgrade is for a public purpose and will allow the vessel to continue to serve the citizens of

21  Louisiana as a proven highly successful tourist attraction, educational institution, military

22  memorial, patriotic ceremonial platform and documentary/theatrical film set. Further, the

23  USS KIDD DD-661 the only surviving Fletcher class destroyer in her original WW2

24  configuration and the restoration project requires special consideration in the selection of a

25  restoration contractor and in the location and complete identification of the repairs to be

26  performed. Therefore, the Louisiana Naval War Memorial Commission, through the Office

27  of Culture, Recreation & Tourism, shall be permitted to use an alternative delivery method

28  to award construction contract(s) for the proposed repairs and renovations to the USS KIDD

29  and its cradle. The Louisiana Naval War Memorial Commission, through the Office of

30  Culture, Recreation & Tourism, shall have the authority to select the contractor(s) from a list

31  of a minimum of three highly qualified ship builders/shipyards with relevant restoration

                     Page 162 of 174
    HB NO. 2                                          ENROLLED

1   experience acceptable to the Commissioner of Administration and the selection shall be

2   exempt from other state requirements for the selection of contractors. The construction

3   contract(s) shall be administered by the Office of Facility Planning and Control, Division

4   of Administration in accordance with state guidelines and all restoration and repairs shall

5   adhere to the U.S. Department of Interiors’ Standards for Historic Ship Preservation

6   Projects.

7              (R) Pursuant to R.S. 39:102, each capital outlay budget request submitted as

8   required by R.S. 39:101 shall include a detailed project description and justification for each

9   new project requested; however,

10             (1) Notwithstanding anything contained in this Act or the Capital Outlay Act to

11  the contrary or any other provision of law, the scope of the appropriations made in this or

12  any other Capital Outlay Act for the Pointe Coupee Parish School Board Office Relocation,

13  Due to Flooding Caused by Hurricane Gustav, Planning and Construction project shall be

14  deemed to include that the School Board Office is to be Located at 8777 Morganza

15  Highway.

16             (2) Notwithstanding anything in this Act, any previous capital outlay act, or

17  other provision of law to the contrary, the scope of the appropriation for the Port of South

18  Louisiana Globalplex Terminal Building #71 Upgrade project shall be deemed to also

19  include similar upgrades for other Globalplex Terminal Buildings and a Heavy Load

20  Capacity Foundation or Floor.

21             (3) Notwithstanding anything in this Act, any previous capital outlay act, or

22  other provision of law to the contrary, monies appropriated herein for the Port of South

23  Louisiana Globalplex Terminal Building #71 and Other Globalplex Terminal Building

24  Upgrades, Planning and Construction may be expended for design fees related to the

25  conveyor system and ancillary equipment that exceed the customary ten percent limitation

26  on design fee costs.

27             (4) Notwithstanding anything in this Act, any previous capital outlay act, or

28  other provision of law to the contrary, the scope of the appropriation for the Port of South

29  Louisiana Globalplex Dock Access Bridge and Equipment Replacement/Repair project shall

30  be deemed to also include an Access Road.

                                     Page 163 of 174
    HB NO. 2                                                                  ENROLLED

1             (5) Notwithstanding anything in this Act, any previous capital outlay act, or

2   other provision of law to the contrary, the scope of the appropriation for the Port of South

3   Louisiana Globalplex Rail Siding project shall be deemed to also include a Rail Spur.

4             (6) Notwithstanding anything contained in this Act or the Capital Outlay Act to

5   the contrary or any other provision of law, the scope of the appropriations made in this or

6   any other Capital Outlay Act for the Pontchartrain Levee District Lake Pontchartrain West

7   Shore Hurricane Protection, Planning and Construction project shall be deemed to include

8   Ascension Parish.

9             (7) Notwithstanding anything contained in this Act or the Capital Act to the

10  contrary or any other provision of law, the scope of the appropriation made in this or any

11  other Capital Outlay Act for the Statewide Roofing Asset Management Program and

12  Waterproofing, Related Repairs and Equipment Replacement Program project shall be

13  deemed to include Peltier Hall at Nicholls State University.

14            (8) Notwithstanding anything contained in this Act or the Capital Act to the

15  contrary or any other provision of law, the scope of the appropriation made in this or any

16  other Capital Outlay Act for the Longview Road Improvements, Beauregard Parish Police

17  Jury project shall be deemed to include Longville Road Improvements for the Beauregard

18  Parish Police Jury.

19            (9) Notwithstanding anything contained in this Act or the Capital Act to the

20  contrary or any other provision of law, the scope of the appropriation made in this or any

21  other Capital Outlay Act for the JESTC Training Facility Improvements project shall be

22  deemed to include facilities at JESTC to accommodate a less than lethal training program

23  utilizing mobile virtual training.

24            (10) Notwithstanding anything contained in this Act, any previous capital outlay

25  act to the contrary, or any other provision of law, the scope of the appropriations made in

26  this or any other capital outlay act for the Industrial Park Development project for New

27  Roads shall be deemed to include underground electrical system upgrades.

28            (11) Notwithstanding anything contained in this Act, any previous capital outlay

29  act to the contrary, or any other provision of law, the scope of the appropriations made in

30  this or any other capital outlay act for the Lincoln Manner Subdivision Drainage project for

                                        Page 164 of 174
    HB NO. 2                                                                   ENROLLED

1   Kenner shall be deemed to include 30th Street Roadway and Drainage Improvements from

2   Loyola Drive to Ohio Street.

3             (12) Notwithstanding anything contained in this Act or the Capital Outlay Act

4   to the contrary or any other provision of law, the scope of the appropriations made in this

5   or any other Capital Outlay Act for the Tensas Parish Recreational Facility project shall be

6   deemed to include Recreational Facilities at Newellton, St. Joseph, and Waterproof.

7             (13) Notwithstanding anything contained in this Act, any previous capital outlay

8   act to the contrary, or any other provision of law, the scope of the appropriations made in

9   this or any other capital outlay act for the LA 93 Roadway Improvements - I-10 Ramp to

10  Renaud Drive, Planning and Construction project for Scott shall be deemed to include the

11  planning and design of the Roundabout at Exit 97 Westbound, Planning, Construction, and

12  Land Acquisition project for Scott and the planning and design of the Roundabout at LA 93

13  and Renaud Drive, Planning, Construction, and Land Acquisition for Scott.

14            (14) Notwithstanding anything contained in this Act, any previous capital outlay

15  act to the contrary, or any other provision of law, the scope of the appropriations made in

16  this or any other capital outlay act for the Water and Sewer Line Installation along Apollo

17  Road Extension, Planning and Construction project for Scott shall be deemed to include the

18  placement of water and sewer line utilities along the roadway.

19            (15) Notwithstanding anything contained in this Act, any previous capital outlay

20  act to the contrary, or any other provision of law, the scope of the appropriations made in

21  this or any other capital outlay act for the Young's Bayou Enhancement of Channel Capacity,

22  Planning and Construction project for Monroe shall be deemed to include streams and

23  contributing tributaries flowing into the Young's Bayou Watershed.

24            (16) Notwithstanding anything contained in this Act, any previous capital outlay

25  act to the contrary, or any other provision of law, the scope of the appropriations made in

26  this or any other capital outlay act for the Central Louisiana State Hospital Relocation to

27  Pinecrest project for the Office of Behavioral Health shall be deemed to include new

28  construction and renovations of buildings.

29            (17) Notwithstanding anything contained in this Act, any previous capital outlay

30  act to the contrary, or any other provision of law, the scope of the appropriations made in

31  this or any other capital outlay act for the New Education Building project for the

                                  Page 165 of 174
    HB NO. 2                                                           ENROLLED

1   Opportunities Industrialization Center Incorporated of Ouachita shall be deemed to include

2   new construction and renovations of buildings.

3             (18) Notwithstanding anything contained in this Act, any previous capital outlay

4   act to the contrary, or any other provision of law, the scope of the appropriations made in

5   this or any other capital outlay act for the New Orleans Emergency Shelter project for Eden

6   House shall be deemed to include acquisitions, renovations, and new construction of other

7   Eden House facilities statewide.

8             (19) The following revisions are hereby made to Act 465 of the 2023 Regular

9   Legislative Session of the Louisiana Legislature for the purpose of transferring the projects

10  listed below to the appropriate agency:

11            (a) Notwithstanding any provisions of law to the contrary, including the

12  provisions of the Capital Outlay Act, the appropriation to 50/NC2 BATON ROUGE

13  RECREATION AND PARKS COMMISSION for The Inspiration Center – Howell

14  Community Park (East Baton Rouge) project is hereby amended and reenacted to 50/R01

15  BATON ROUGE LAW ENFORCEMENT AND CRIMINAL JUSTICE FOUNDATION.

16            (20) Notwithstanding anything contained in this Act, any previous capital outlay

17  act, or any other provision of law to the contrary, the scope of work for the Parish Jail

18  Improvements for Iberia Parish shall be prioritized with coordination between the Parish of

19  Iberia and the Iberia Parish Sheriff.

20            (21) Notwithstanding anything contained in this Act, any previous capital outlay

21  act to the contrary, or any other provision of law, the scope of the appropriations made in

22  this or any other capital outlay act for the Lake Pontchartrain West Shore Hurricane

23  Protection project for the Pontchartrain Levee District shall be deemed to include levee

24  improvements around the Port of South Louisiana's airport runway.

25            (22) Notwithstanding anything contained in this Act, any previous capital outlay

26  act to the contrary, or any other provision of law, the scope of the appropriations made in

27  this or any other capital outlay act for the Water Treatment Facility, Booster Pump Station,

28  and Distribution System Improvements project for the City of Franklin shall be deemed to

29  include necessary improvements at the water treatment plant including the transfer pump.

30            (23) Notwithstanding anything contained in this Act, any previous capital outlay

31  act to the contrary, or any other provision of law, the scope of the appropriations made in

                                      Page 166 of 174
    HB NO. 2                                                    ENROLLED

1   this or any other capital outlay act for the Commerce Street Improvements and Utilities

2   Relocation for the town of St. Francisville shall be deemed to include additional

3   infrastructure improvements and appurtenances to streets and other areas with connectivity

4   to Commerce Street.

5             (24) Notwithstanding anything contained in this Act, any previous capital outlay

6   act to the contrary, or any other provision of the law, the scope of the appropriations made

7   in this or any other capital outlay act for the Louis Collier Hall Science Building Renovation

8   project for Southern University Shreveport shall be deemed to include replacement of the

9   existing building.

10            (25) Notwithstanding anything contained in this Act, any previous capital outlay

11  act to the contrary, or any other provision of the law, the scope of the appropriations made

12  in this or any other capital outlay act for the Roadway Reconstruction, Eugene Garrett Road

13  for Winn Parish shall be deemed to include the entirety of Eugene Garrett Road.

14            (26) Notwithstanding anything in this Act, any previous capital outlay act, or

15  other provision of law to the contrary, the scope of the appropriation for the Port of South

16  Louisiana Globalplex Roadway Improvements: Parking Area near Building 60 project shall

17  be deemed to also include a W. 10th Street Access Roadway.

18            (27) Notwithstanding anything in this Act, any previous Capital Outlay Act, or

19  other provision of law to the contrary, the scope of the appropriation for the Port of South

20  Louisiana Globalplex Terminal Building #71 and Other Globalplex Terminal Building

21  Upgrades project shall be deemed to also include Improvements to the Port of South

22  Louisiana Executive Regional Airport.

23            (28) Notwithstanding anything contained in this Act, any previous Capital

24  Outlay Act, or any other provision of law to the contrary, the scope of the appropriations

25  made in this or any other Capital Outlay Act for the C.C. Antoine Park, Planning and

26  Construction project and the C.C. Antoine Museum and Arts Center, Planning and

27  Construction project for Shreveport shall be deemed to include the planning, design, site

28  work, construction, reconstruction, or replacement of a replica or replacement structure for

29  the C.C. Antoine House within C.C. Antoine Park, including construction at a location

30  different from the original C.C. Antoine House site.

                         Page 167 of 174
    HB NO. 2                                                          ENROLLED

1             (S) Notwithstanding anything contained in this Act to the contrary or any other

2   provision of law, all non-state projects that include water systems in the scope of work shall

3   also be required to include a rate study as part of the project.

4             (T) Notwithstanding anything contained in this Act or any other provision of

5   law, the appropriations included herein identified as "Payable from State General Fund

6   (Direct) Non-Recurring Revenues" are appropriated for the purpose of making supplemental

7   capital outlay appropriations for Fiscal Year 2025-2026.

8             (U) Notwithstanding anything contained in this Act to the contrary or any other

9   provision of the law, the appropriations included herein identified as "Payable from Interest

10  Earnings" are appropriated for the purpose of making supplemental capital outlay

11  appropriations for Fiscal Year 2025-2026.

12            (V) Notwithstanding anything contained in this Act to the contrary or any other

13  provision of law, any water/sewer project that submitted by August 31, 2022 for the Water

14  Sector Program shall be deemed to be submitted timely provided a capital outlay request is

15  submitted and is otherwise compliant with the provisions of R.S. 39:101 and R.S. 39:102.

16  Such request together with supporting information and documents shall constitute the

17  feasibility study required by Article VI, Section 11(C) of the Constitution of Louisiana.

18            (W) Notwithstanding anything contained in this Act or any other provision of

19  law, the Port of New Orleans is authorized to execute contracts for the Louisiana

20  International Terminal Roadway and Rail Improvements, Planning and Construction and the

21  Louisiana International Terminal, Drainage, Site Preparation and Mitigation, Planning and

22  Construction prior to execution of a cooperative endeavor agreement, the granting of a line

23  of credit, or the sale of bonds. The appropriation for this project may be used to pay any

24  obligation incurred or to reimburse any expenditure made pursuant to such contracts unless

25  the commissioner of administration is advised by bond counsel to the state that such may

26  violate federal tax law. The office of facility planning and control shall consult with bond

27  counsel to the state relative to any federal tax issues.

28            (X) Notwithstanding anything contained in this Act or any other provision of

29  law, the Board of Commissioners for the Port of New Orleans is authorized to execute

30  contracts for the Louisiana International Terminal Roadway and Rail Improvements,

31  Planning and Construction and the Louisiana International Terminal, Drainage, Site

              Page 168 of 174
    HB NO. 2                                    ENROLLED

1   Preparation and Mitigation, Planning and Construction project prior to execution of a

2   cooperative endeavor agreement, the granting of a line of credit, or the sale of bonds. The

3   appropriation for this project may be used to pay any obligation incurred or to reimburse any

4   expenditure made pursuant to such contracts unless the commissioner of administration is

5   advised by bond counsel to the state that such may violate federal tax law. The office of

6   facility planning and control shall consult with bond counsel to the state relative to any

7   federal tax issues.

8             (Y) Notwithstanding anything contained in this Act or any previous Capital

9   Outlay Act or any provision of law to the contrary, capital outlay expenditures by the Local

10  Government Assistance Program (LGAP) shall comply with the definition contained in La.

11  R.S. 39:2(9) exclusively.

12            (Z) Notwithstanding anything contained in this Act or any other provision of law

13  to the contrary, the Louisiana State University Research Well No. 3 at LSU's Petroleum

14  Engineering Research Training and Testing Laboratory (PERTT Lab) is deemed to be a

15  capital asset and the funds made available to the Board of Supervisors of Louisiana State

16  University and Agricultural and Mechanical College (LSU) for Planning and Construction

17  of the Louisiana State University Research Well No. 3 at LSU's Petroleum Engineering

18  Research Training and Testing Laboratory (PERTT Lab) are for a public purpose and will

19  further LSU's educational mission through the support of research, education, testing and

20  training related to carbon capture and sequestration, oil and gas production, geothermal

21  energy, and other subsurface engineering technologies. Further, the complexities of the

22  research well project and the consortium of partners to LSU involved in the design, supply,

23  and construction of the research well project require special consideration in the selection

24  of designers, contractors, a general contractor, and/or construction manager. LSU shall be

25  permitted to use alternative delivery methods to award one or more contracts for the design,

26  construction, and/or construction management of the research well project. As necessary,

27  LSU shall have the authority to select and contract with designers, each will be selected from

28  a list of a minimum of three (3) entities or joint ventures with well design expertise

29  acceptable to the Commissioner of Administration and the selections shall be exempt from

30  state requirements for selection of designers. Where applicable, any fee related to design

31  shall be in accordance with state guidelines administered by the Office of Facility Planning

                               Page 169 of 174
    HB NO. 2                                               ENROLLED

1   and Control, Division of Administration. LSU shall further be permitted to use alternative

2   delivery methods to award one or more contracts for the construction and/or construction

3   management of the research well project. LSU shall have the authority to select co(tractors,

4   a general contractor, and/or construction manager, each will be selected from a list of a

5   minimum of three (3) highly qualified contractors, general contractors, and/or construction

6   managers with relevant construction and/or construction management experience acceptable

7   to the Commissioner of Administration and the selections shall be exempt from other state

8   requirements for the selection of contractors, general contractors, and/or construction

9   managers. The contracts related to construction and/or construction management shall be

10  administered by LSU through a delegation of authority by the Director of the Office of

11  Facility Planning and Control, Division of Administration, pursuant to a cooperative

12  endeavor agreement with LSU. The administration of the contracts related to construction

13  and/or construction management shall be in accordance with state laws and guidelines

14  applicable to public contracts, with the exception that La. R.S. 38:2212(L) shall not apply.

15  The Project shall be designed in accordance with industry standards and in compliance with

16  the requirements of the Louisiana Department of Energy and Natural Resources for well

17  construction.

18            (AA) Notwithstanding anything contained in this Act or any other provision of

19  law to the contrary, the Louisiana Optical Network Infrastructure (LONI) is deemed to be

20  a capital asset and the funds made available to the Louisiana Board of Regents for Planning

21  and Construction of the System-Wide Telecommunications Wiring and Equipment are for

22  a public purpose and will further the state of Louisiana’s educational mission through the

23  support of research, education, and economic development by providing access to advanced

24  computing and data services. Further, the specialization and complexities of the

25  telecommunications wiring and equipment project and the consortium of partners to LONI

26  involved in the locations of the project require special consideration in the selection of

27  designers, contractors, and/or construction managers.

28            The Board of Regents and LONI, through the Board of Supervisors of Louisiana

29  State University and Agricultural and Mechanical College (LSU), who serve as the fiduciary

30  agent for LONI, shall be permitted to use alternative delivery methods to award one or more

31  contracts for the design, construction, and/or construction management of the

                   Page 170 of 174
    HB NO. 2                    ENROLLED

1   telecommunications project. As necessary, LONI shall have the authority to select and

2   contract with a designer, selected from a list of a minimum of three (3) (if available)

3   applicants or joint ventures with telecommunications wiring and equipment expertise

4   acceptable to the Commissioner of Administration and the selections shall be exempt from

5   state requirements for the selection of designers. Where applicable, any fee related to design

6   shall be in accordance with guidelines administered by the Office of Facility Planning and

7   Control, Division of Administration. LONI shall further be permitted to use alternative

8   delivery methods to award one or more contracts for the construction and/or construction

9   management of the telecommunications project. LONI shall have the authority to select

10  contractors and/or construction managers from a list of a minimum of three (3) (if available)

11  highly qualified contractors and/or construction managers with relevant construction

12  experience acceptable to the Commissioner of Administration and the selection shall be

13  exempt from state requirements for the selection of contractors and/or construction

14  managers.

15             The contracts related to construction shall be administered by LSU through a

16  delegation of authority by the Director of the Office of Facility Planning and Control,

17  Division of Administration, pursuant to a cooperative endeavor agreement with LSU. The

18  Board of Regents shall also have the authority to approve the scope of the project. The

19  administration of the contracts related to construction shall be in accordance with state laws

20  and guidelines applicable to public contracts, with the exception that La R.S. 38:2212(L)

21  shall not apply. The Project shall be designed in accordance with industry standards.

22             Notwithstanding anything in this Act or any previous Capital Outlay Acts to the

23  contrary, the Department of Transportation and Development may enter into contracts for

24  Southern University – Baton Rouge, Ravine, Bluff and Riverbank Stabilization Project (East

25  Baton Rouge) prior to the receipt of funding including contracts previously entered into for

26  planning, environmental, engineering, and other preconstruction services, and the State is

27  authorized to financially participate in and reimburse the Department of Transportation and

28  Development for obligations created by and eligible costs incurred under such contracts.

29             Section 9. Notwithstanding any provisions contained herein or any other law to

30  the contrary, the provisions of Chapter 17 of Title 39 of the Louisiana Revised Statutes of

31  1950 as amended, shall not apply to architectural and engineering contracts, administered

               Page 171 of 174
    HB NO. 2                                           ENROLLED

1   by the Office of Facility Planning and Control, Division of Administration pursuant to this

2   or any other capital outlay act.

3             Section 10. All funds appropriated herein to agencies administering capital

4   outlay projects, on behalf of non-state entities, by cooperative endeavor agreements pursuant

5   to this Act shall be expended within two (2) years from the date of the issuance of the bonds.

6   Agencies administering capital outlay projects pursuant to a cooperative endeavor agreement

7   shall notify the non-state entity of the date the bonds are issued within three (3) months from

8   the issuance thereof. If the funds appropriated herein and administered under cooperative

9   endeavor agreements pursuant to this Act are not totally expended within two (2) years from

10  the issuance of the bonds, the administering agency can close the project and recommend

11  that the reallocation of any unexpended proceeds to any project contained in this Act or any

12  previous Capital Outlay Acts.

13            Section 11. Notwithstanding any provisions contained herein or law to the

14  contrary, the proceeds of revenue bonds to be utilized to fund certain projects authorized in

15  Section 1 (A) and Section 1 (B) hereof may, in accordance with Article VII, Section 9 of the

16  Louisiana Constitution of 1974, be deposited in special accounts held outside the state

17  treasury in accordance with the provisions of any bond resolution, indenture, reimbursement

18  contract, or other bond or financing covenant which provides for the pledge of such funds

19  in connection with the issuance of revenue bonds. For all projects administered by the Office

20  of Facility Planning and Control, Division of Administration, authorized in Section 1 (A)

21  And Section 1 (B) hereof which are payable from the proceeds of revenue bonds, only the

22  Office of Facility Planning and Control, Division of Administration, will be authorized to

23  requisition funds from the special accounts described immediately above, at such time or

24  times as may be deemed necessary by the Office of Facility Planning and Control, Division

25  of Administration, in order to cover contract amounts or other project expenses.

26            Section 12. The governor shall have the power to veto any line-item in this Act.

27            Section 13. Except as otherwise provided herein, no funds shall be expended on

28  any highway projects on highways within the state highway system as established in R.S.

29  48:191 under the jurisdiction of the Department of Transportation and Development unless

30  and until such project is in the Highway Program, R.S. 48:228 through 232, approved by the

31  Joint Legislative Committee on Transportation, Highways and Public Works. Pursuant to

                                      Page 172 of 174
    HB NO. 2                                                                      ENROLLED

1   R.S. 49:214.6.2(B), no integrated coastal protection construction project shall be undertaken

2   with funds included in this bill except those included in an annual plan finally approved by

3   the legislature in accordance with the provisions of R.S. 49:214.5.3. No funds appropriated

4   to the Coastal Protection and Restoration Authority in this Act as a contribution for a project

5   cost-share or otherwise, for the national economic development and national ecosystem

6   restoration components of the Southwest Coastal Louisiana Study shall be used or provided

7   for the expropriation of property or use of eminent domain, except where such funds are to

8   be used to obtain property voluntarily offered for project purposes, where at least seventy-

9   five percent of the owners have voluntarily offered the property, or where the record or

10  apparent owners have voluntarily offered the property but do not have clear title.

11            Section 14. The word "statewide" used in place of the specific parish designation

12  for projects contained in this Act indicates that the project or program is applicable to all

13  sixty- four parishes in the state. The description of any project in this Act shall be deemed

14  to include planning, design, master planning, studies, permits, surveys, testing, construction,

15  land and/or building/improvement acquisition, reconstruction, renovation, repair, right-of-

16  way and utilities, site and other improvements, miscellaneous/contingencies, lease hold

17  improvements ultimately owned by the state or a political subdivision of the state, equipment

18  and other acquisitions, and any other component of the project if such are included or

19  indicated in the capital outlay request for such projects required by R. S. 39:101 subject to

20  the provisions of Title 39 of the Louisiana Revised Statutes of 1950. For new construction

21  or renovation projects, equipment or other acquisitions, which can reasonably be considered

22  necessary for the facility to be functional, may be deemed to be included in the project, even

23  if such equipment or other acquisitions are not included or indicated in the project name or

24  the capital outlay request. When local or federal match is referenced in a project title, but

25  only a portion of the state appropriation is granted a line of credit or otherwise funded, then

26  the amount of local or federal match, required to be made available, may be prorated relative

27  to the amount of state appropriation made available through lines of credit.

28            Section 15. The provisions, items, and projects contained in this Act are

29  severable and if any provision, item, or project contained herein, or the application of any

30  such provision, item, or project, is held invalid, such invalidity shall not affect other

              Page 173 of 174
    HB NO. 2                                                                ENROLLED

1   provisions, items, projects, or applications of the Act which can be given effect without the

2   invalid provision, project, item, or application.

3             Section 16. Notwithstanding any other provisions of law to the contrary, the state

4   shall not grant cash lines of credit, or authorize or issue general obligation bonds in a

5   principal amount in excess of $1,994,431,681 for Fiscal Year 2026-2027

6             Section 17. As of December 31, 2025 the total outstanding net state tax

7   supported debt, as defined in La. R.S. 39:1367, was $ 8,502,629,398 ($6,214,189,000

8   principal and $2,288,440,398 interest). The estimated debt service costs associated with the

9   $ 574,000,000 of new general obligation bond cash line of credit capacity for Fiscal Year

10  2026-2027 is $ 42,100,000 annually beginning in Fiscal Year 2027-2028 through Fiscal Year

11  2046-2047.

12            Section 18. Notwithstanding any contrary provision of this Act or any contrary

13  provision of law, no funds appropriated by this Act shall be released or provided to any

14  recipient of an appropriation made in this Act if, when, and for as long as, the recipient fails

15  or refuses to comply with the provisions of R.S. 24:513. No recipient shall be considered to

16  fail or refuse to comply with the provisions of R.S. 24:513 pursuant to this Section during

17  any extension of time granted by the legislative auditor to the recipient to comply.

18            Section 19. This Act shall become effective upon signature by the governor or,

19  if not signed by the governor, upon expiration of the time for bills to become law without

20  signature by the governor, as provided in Article III, Section 18 of the Constitution of

21  Louisiana. If vetoed by the governor and subsequently approved by the legislature, this Act

22  shall become effective on the day following such approval.

    APPROVED:   SPEAKER OF THE HOUSE OF REPRESENTATIVES
                PRESIDENT OF THE SENATE
                GOVERNOR OF THE STATE OF LOUISIANA