govt.fyi
Back to HB 269
Delaware General Assembly· HB 269Signed

Interconnection Rules/Alignment/Procedures, the official text

Shown verbatim: the complete text as captured from the official PDF posted by the Delaware General Assembly, fetched 2026-09-25. Page and line markers are part of the official record; nothing is edited or removed. This is the current version. The official bill page.
SPONSOR: Rep. Burns & Rep. Heffernan & Sen. Hansen
                                                                                 Reps. Morrison, Romer, Phillips, Gorman

                          HOUSE OF REPRESENTATIVES
                            153rd GENERAL ASSEMBLY

                                                HOUSE BILL NO. 269

    AN ACT TO AMEND TITLE 26 OF THE DELAWARE CODE RELATING TO NET-METERING AND
    INTERCONNECTION RULES.

    BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF DELAWARE:

1        Section 1. Amend § 1014, Title 26 of the Delaware Code by making deletions as shown by strike through and

2 insertions as shown by underline as follows:

3        § 1014. Public purpose programs and consumer education [For application of this section, see 85 Del. Laws, c. 83,

4 § 2].

5        (e) The rules and regulations promulgated for net energy metering by the Commission, municipal electric

6 companies, and electric cooperatives during any period of exemption under § 223 of this title must consider the reliability,

7 safety, and capacity of the electric distribution system and:

8        (5) Require that all generating systems and grid-integrated electric vehicles used by eligible customers meet

9   all applicable safety and performance standards established by the National Electrical Code, and those of the Institute

10  of Electrical and Electronic Engineers, UL, or the Society of Automotive Engineers, to ensure that net metering

11  customers meet applicable safety and performance standards and comply with the electric supplier’s interconnection

12  tariffs and operating guidelines. An electric supplier’s interconnection rules must be developed by using as a guide

13  aligned with the most recent version of the Interstate Renewable Energy Council’s Model Interconnection Rules and

14  best practices identified by the U.S. Department of Energy. Municipal electric companies shall establish

15  interconnection rules no later than July 24, 2008. Procedures (Procedures) within 12 months of the Procedures’ latest

16  publishing date. An electric supplier may not require eligible net-metering customers who meet all applicable safety

17  and performance standards to install excessive controls, perform or pay for unnecessary tests, or purchase excessive

18  liability insurance.

                                                                        SYNOPSIS

              This Act requires that an electric supplier’s interconnection rules, for purposes of net-metering, align with the most
    recent version of the Interstate Renewable Energy Council’s Model Interconnection Procedures (Procedures) within 12
    months of the Procedures’ latest publishing date.

    HD : LTK : SCD                              Page 1 of 1          Released: 01/20/2026 12:10 PM