Approve the award of Change Order #1 to Contract 24-251, SPX Flow US LLC, SPX Flow Parts and Service, to Mills-Winfield Engineering for an amount not to exceed $50,000 and a total award of $149,000
Introduced
Moved
Reached a final decision
Became law
Derived from the official record below.
Officially: “Approve the award of Change Order #1 to Contract 24-251, SPX Flow US LLC, SPX Flow Parts and Service, to Mills-Winfield Engineering for an amount not to exceed $50,000 and a total award of $149,000” Read the full text
Official title from the city record, shown verbatim. Plain-language summary coming as coverage deepens. Not legal advice.
Procurement Change Order
Where it is
approved · Aug 18, 2026
The numbers
0
sponsors on the bill
Every fact on this page links to its source, starting with the official bill record. Last action: approved (Aug 18, 2026).