(CD 9) Authorize Execution of Change Order No. 5 in the Amount of $198,741.76 to a Contract with Winston Electric, Inc. dba ACME Electric Company, for the Westside Water Treatment Plant Generators...
Introduced
Moved
Reached a final decision
Became law
Derived from the official record below.
Officially: “(CD 9) Authorize Execution of Change Order No.” Read the full text
Official title from the city record, shown verbatim. Plain-language summary coming as coverage deepens. Not legal advice.
Award of Contract Consent
Where it is
Approved · May 12, 2026
CITY COUNCIL
The numbers
0
sponsors on the bill
Every fact on this page links to its source, starting with the official bill record. Last action: Approved (May 12, 2026).