1 State of Arkansas             As Engrossed: S4/7/25
2 95th General Assembly
                                     A Bill

3 Regular Session, 2025                                            SENATE BILL 492

4

5 By: Senator J. Bryant

6 By: Representative Lundstrum

7

8                               For An Act To Be Entitled

9      AN ACT TO AMEND THE LAW CONCERNING THE RELOCATION OF

10     UTILITY FACILITIES; TO AMEND THE LAW CONCERNING THE

11     ACQUISITION, CONDEMNATION, AND DISPOSITION OF REAL

12     PROPERTY BY THE STATE HIGHWAY COMMISSION; TO

13     ESTABLISH A PROCESS FOR THE RELOCATION OF A UTILITY

14     FACILITY LOCATED ON A PUBLIC RIGHT OF WAY; AND FOR

15     OTHER PURPOSES.

16

17

18                              Subtitle

19                       TO AMEND THE LAW CONCERNING THE

20                       RELOCATION OF UTILITY FACILITIES; AND TO

21                       AMEND THE LAW CONCERNING THE

22                       ACQUISITION, CONDEMNATION, AND

23                       DISPOSITION OF REAL PROPERTY BY THE

24                       STATE HIGHWAY COMMISSION.

25

26 BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF ARKANSAS:

27

28     SECTION 1. Arkansas Code Title 27, Chapter 67, Subchapter 3, is

29 amended to add additional sections to read as follows:

30     27-67-325. Relocation of utility facility -- Definitions.

31     (a) As used in this section and � 27-67-326:

32     (1) "Extraordinary event" means:

33                       (A) An event beyond the reasonable control of a utility;

34 or

35                       (B) A change of plans that causes a delay in the work of a

36 utility required under a relocation agreement;

    *ZRC016*                                                  04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                 SB492

1         (2)(A) "Municipal utility system" means a utility system owned

2 or operated by a municipality that provides or removes at least one (1) of

3 the following:

4                          (i) Electricity;

5                          (ii) Water;

6                          (iii) Wastewater;

7                          (iv) Gas;

8                          (v) Cable television; or

9                          (vi) Broadband service.

10                (B) "Municipal utility system" includes without limitation

11 a:

12                         (i) Consolidated waterworks system under the

13 Consolidated Waterworks Authorization Act, � 25-20-301 et seq.;

14                         (ii) Utility system managed or operated by a

15 nonprofit corporation under � 14-199-701 et seq.; and

16                         (iii) Utility system owned or operated by a

17 municipality or by a consolidated utility district under the General

18 Consolidated Public Utility System Improvement District Law, � 14-217-101 et

19 seq.;

20        (3)(A) "Public transportation facility" means a transportation

21 facility and a right-of-way that serves the public.

22                (B) "Public transportation facility" includes without

23 limitation a:

24                         (i) Highway, interstate, freeway, street, or other

25 road;

26                         (ii) Trail;

27                         (iii) Bicycle trail; and

28                         (iv) Sidewalk or other pedestrian facility;

29        (4)(A) "Relocation" means the adjustment, removal, or relocation

30 of a utility facility determined by the Arkansas Department of Transportation

31 to be necessary or appropriate in connection with the construction or

32 reconstruction of a public transportation facility.

33                (B) "Relocation" includes without limitation:

34                         (i) Removing and reinstalling a utility facility,

35 including a necessary temporary utility facility;

36                         (ii) Moving, rearranging, or changing the type of

                                      2                 04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                    SB492

1 existing utility facility;

2                          (iii) Taking necessary safety and protective

3 measures; and

4                          (iv) Constructing a replacement utility facility

5 that is functionally equivalent to an existing utility facility and necessary

6 for the continuous operation of the utility service, the project economy, or

7 the sequence of public transportation facility construction;

8               (5) "Relocation agreement" means a written agreement between the

9 department and a utility concerning a specific relocation;

10              (6) "Relocation proposal" means a formal written submission

11 prepared by a utility in response to a request from the department concerning

12 a specific relocation;

13              (7)(A) "Utility" means a private, public, or cooperative utility

14 that transmits or distributes communications, including without limitation

15 cable service and broadband service, electricity, gas, liquids, steam, or

16 sewerage by means of a utility facility.

17               (B) "Utility" does not include a railway or railroad

18 engaged in interstate commerce;

19              (8) "Utility accommodation rules" means the rules adopted by the

20 State Highway Commission and administered by the department that:

21               (A) Address the processes and procedures for a utility to

22 receive reimbursement for a relocation on public transportation facilities of

23 the commission; and

24               (B) Establish the process for permits for the placement of

25 utility facilities on public transportation facilities of the commission; and

26              (9) "Utility facility" means a line, facility, or system of a

27 utility that is used, is available for use, or was formerly used to transmit

28 or distribute communications, including without limitation cable service and

29 broadband service, electricity, gas, liquids, steam, water, or sewerage to

30 the public.

31  (b)(1) When a utility facility located on a public transportation

32 facility must be removed, relocated, or adjusted to accommodate a change to a

33 public transportation facility, the department and the utility shall

34 negotiate a relocation agreement establishing the reasonable schedule for

35 relocation and the duties of the department and the utility concerning the

36 relocation.

                                    3        04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                    SB492

1               (2) When negotiating the relocation agreement under subdivision

2 (b)(1) of this section, the:

3                   (A) Department shall:

4                          (i) Provide written notice to the utility of the

5 need for the relocation located on the public transportation facility that

6 shall include:

7                               (a) Plans that clearly identify all known

8 utilities that own a utility facility that is subject to relocation;

9                               (b) The area of the public transportation

10 facility the department or commission intends to acquire for the project; and

11                              (c) The proposed right-of-way acquisition and

12 timeline;

13                         (ii) Provide to the utility the construction plans

14 for the project that demonstrate the need for the relocation;

15                         (iii) Establish a reasonable date for the submission

16 of a relocation proposal;

17                         (iv) Coordinate a relocation agreement for the work

18 to be performed by the utility, including a schedule for the relocation; and

19                         (v) Issue a notice to proceed to the utility to

20 begin the relocation upon execution of a relocation agreement; and

21                  (B) Utility shall:

22                         (i) Submit to the department a relocation proposal

23 in accordance with the utility accommodation rules that includes without

24 limitation:

25                              (a) A plan for the relocation in accordance

26 with the construction plans for the project provided by the department as

27 required under subdivision (b)(2)(A)(ii);

28                              (b) A reasonable schedule for the completion

29 of the relocation;

30                              (c) Reasonable cost estimates for the

31 relocation; and

32                              (d) A final date all work will be complete for

33 the relocation;

34                         (ii) Begin and complete the relocation within the

35 time frame specified in the relocation agreement negotiated under subdivision

36 (b)(1) of this section; and

                                4             04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                    SB492

1                          (iii) Submit a progress report every two (2) months

2 to the department regarding the status of the relocation after a notice to

3 proceed is issued under subdivision (c)(1) of this section until the

4 relocation is complete.

5   (c)(1) After a relocation agreement is executed under this section,

6 the department shall issue a notice to proceed with the relocation to the

7 owner of the utility facility that is the subject of the relocation

8 agreement.

9              (2) A notice to proceed issued under subdivision (c)(1) of this

10 section serves as the formal authorization for the utility to commence work

11 on the relocation in accordance with terms of the relocation agreement.

12  (d)(1) If a utility other than a municipal utility system fails to

13 follow the process established in the utility accommodation rules or the

14 relocation agreement to complete the relocation within the time period stated

15 in the relocation agreement, the department may assess and collect a civil

16 penalty from a utility other than a municipal utility system after:

17                    (A) The department provides notice to the utility under

18 subdivision (e)(2)(A) of this section; and

19                    (B) The expiration of a thirty-day time period for the

20 utility to comply with the requirements stated in the utility accommodation

21 rules or the relocation agreement.

22             (2) The civil penalty authorized under subdivision (d)(1) of

23 this section shall be five hundred dollars ($500) for each business day the

24 utility fails to:

25                    (A) Respond to the written notice to the utility of the

26 need for the relocation located on the public transportation facility

27 provided under subdivision (b)(2)(A)(i) of this section;

28                    (B) Enter into negotiations for a relocation agreement

29 between the department and the utility; or

30                    (C)(i) Comply with a relocation agreement to which the

31 utility is a party, including completing the work according to the schedule

32 in the relocation agreement.

33                         (ii) A civil penalty shall not be assessed under

34 this subdivision (d)(2)(C) if the utility does not meet the agreed-upon

35 schedule but meets the final relocation completion date in the relocation

36 agreement.

                                       5       04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                  SB492

1                          (iii) A civil penalty may be assessed under this

2 subdivision (d)(2)(C) if a utility fails to:

3                           (a) Act in good faith to comply with the

4 relocation agreement; or

5                           (b) Request a reasonable modification of the

6 schedule.

7   (e)(1) A civil penalty shall not be assessed under subsection (d) for

8 a delay that is the result of:

9                    (A) An extraordinary event;

10                   (B) Excavation that damages an underground utility

11 facility for which:

12                         (i) The owner of the utility facility was not

13 provided notice of the intent to excavate; or

14                         (ii) The utility facility was not located and marked

15 properly under the Arkansas Underground Facilities Damage Prevention Act, �

16 14-271-101 et seq.; or

17                   (C) A delay in acquiring right-of-way after a good faith

18 effort by the utility to complete the acquisition of the right-of-way.

19           (2)(A) The department shall give a utility written notice of the

20 intent to assess a civil penalty under this subsection and an opportunity to

21 appeal the department's decision and show cause why the civil penalty should

22 not be assessed.

23                   (B) Upon a finding that a civil penalty should be assessed

24 under subsection (d) of this section, the department shall issue an

25 appropriate order to the utility.

26                   (C) If a civil penalty has not been paid in full within

27 ninety (90) days after the entry of an order under subdivision (e)(3)(B) of

28 this section, the civil penalty may be:

29                         (i) Deducted from the final reimbursement payment by

30 the department to the utility; or

31                         (ii) Subject to a collection action.

32           (3) An appeal of a decision to assess a civil penalty under this

33 subsection (e) shall be in accordance with the utility accommodation rules

34 and the Arkansas Administrative Procedure Act, � 25-15-201 et seq.

35           (4) Moneys collected as civil penalties under this subsection

36 (e) shall be paid into the State Highway and Transportation Department Fund

                                      6           04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                    SB492

1 and designated for use in a utility relocation grant and loan program to be

2 established by the department for the purpose of providing a grant or loan to

3 a small utility for a relocation that is nonreimbursable.

4   (f)(1) If a municipal utility system fails to follow the process

5 established in the utility accommodation rules or the relocation agreement to

6 complete a relocation within the time period stated in the relocation

7 agreement, the department may relocate the utility facility that is the

8 subject of the relocation agreement.

9               (2) If the department relocates a utility facility under

10 subdivision (f)(1) of this section, the department may enter into a contract

11 to complete the engineering, relocation, or other work required to relocate

12 the utility facility of a municipal utility system after providing written

13 notice to the municipal utility system.

14              (3)(A)(i) If within ten (10) days of the receipt of written

15 notice from the department under subdivision (f)(2) of this section, the

16 municipal utility system provides the department with a list of three (3) or

17 more approved engineers and three (3) or more approved contractors to perform

18 the relocation or design specifications for the utility facility that is to

19 be relocated, the department shall enter into a contract only with an

20 engineer or contractor contained in the list to perform the relocation.

21                         (ii) The department shall not enter into a contract

22 with an engineer or contractor who does not comply with the procurement

23 process of the department.

24              (B) If within ten (10) days of the receipt of written

25 notice from the department under subdivision (f)(2) of this section, the

26 municipal utility system provides the department with design specifications

27 for the utility facility that is to be relocated, then the department shall

28 require compliance with the design specifications in the contract for the

29 relocation.

30              (4) A contract entered into by the department to relocate a

31 utility facility of a municipal utility system under this subsection shall

32 identify the municipal utility system as the beneficiary of the contract.

33              (5) A municipal utility system that has entered into a contract

34 with the department to relocate a utility system of the municipal utility

35 system under this subsection may:

36              (A) Inspect the relocation of the utility facility;

                                      7     04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                   SB492

1                 (B) Inspect an underground utility facility before it is

2 covered; and

3                 (C) Pursue a claim against a person or entity other than

4 the department based on the relocation of the utility facility whether

5 provided under the contract with the department or by law.

6   (6) Within ninety (90) days of the receipt of a written invoice

7 from the department for the cost of a relocation under this subsection, a

8 municipal utility system shall:

9                 (A) Pay to the department the non-reimbursable portion of

10 the cost of the relocation that the municipal utility system does not

11 dispute; and

12                (B) Enter into a dispute resolution process with the

13 department for any disputed portion of the invoice.

14  (7) If a municipal utility system fails to comply with

15 subdivision (f)(6) of this section, the department may offset and collect the

16 amount owed by the municipal utility system from any funds administered by

17 the department for disbursement to the municipality, including without

18 limitation turnback and state aid street funds that may be lawfully applied

19 to the relocation costs.

20  (g) A municipal utility system may agree to the relocation of a

21 utility facility of the municipal utility system by the department using the

22 process provided in subsection (f) of this section.

23  (h)(1) The department shall not act under subsection (d) or subsection

24 (f) of this section if an extraordinary event prevents the completion of a

25 relocation within the time frame specified in the relocation agreement.

26  (2) If an extraordinary event occurs under subdivision (h)(1) of

27 this section, the utility shall provide the department with a:

28                (A) Written notice of the extraordinary event; and

29                (B) Revised relocation proposal and schedule under

30 subdivision (b)(2)(B)(i) of this section.

31  (3) Upon receipt of a written notice under subdivision (h)(2) of

32 this section, the department shall issue a modification to the relocation

33 agreement reflecting a new date for the completion of the relocation as

34 determined by the department.

35  (i) The department shall promulgate rules for the implementation of

36 this section.

                                   8                    04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                   SB492

1

2   27-67-326. Relocation of utility facility -- Rules.

3   (a)(1) Utility accommodation rules adopted by the State Highway

4 Commission concerning relocation under � 27-67-325 shall include without

5 limitation the relocation coordination process between the Arkansas

6 Department of Transportation and the utility.

7               (2) Rules concerning the relocation coordination process between

8 the department and the utility shall include without limitation that:

9               (A) The department shall schedule a meeting with the owner

10 of the utility facility at a time mutually convenient for both parties; and

11              (B) Before a meeting under subdivision (a)(2)(A) of this

12 section, the department shall provide the owner of the utility facility with

13 plans for a proposed relocation.

14              (3) The plans for a proposed relocation under subdivision

15 (a)(2)(B) of this section shall:

16              (A) Clearly indicate:

17                         (i) All identified existing utilities affected by

18 the relocation; and

19                         (ii) The right-of-way the department intends to

20 acquire for the relocation; and

21              (B) Use criteria that satisfy Subsurface Utility

22 Engineering Quality Level C or better.

23              (4) During a meeting under subdivision (a)(2)(A) of this

24 section, the department and the owner of the utility facility shall:

25              (A) Identify the scope of utility facilities that will be

26 subject to relocation;

27              (B) Discuss:

28                         (i) Proposed arrangements for the relocation,

29 including any right-of-way provided by the department for relocation;

30                         (ii) The expected cost of the relocation; and

31                         (iii) A deadline by which the owner of the utility

32 facility shall submit a relocation proposal to the department; and

33              (C) Agree upon the number of days required for the

34 relocation.

35              (5)(A) The department shall provide the utility with a written

36 report summarizing the decisions made and agreements reached during the

                                     9           04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                   SB492

1 meeting held under subdivision (a)(2)(A) of this section.

2               (B) The report provided under subdivision (a)(5)(A) of

3 this section shall serve as the basis for the relocation proposal.

4   (b)(1) The rules promulgated by the department concerning a relocation

5 under � 27-67-325 shall include without limitation:

6               (A) The process for the creation of a relocation proposal

7 and relocation agreement; and

8               (B) The procedure for the reimbursement of the costs of a

9 relocation.

10              (2) The rules for a relocation proposal shall include without

11 limitation that a relocation proposal:

12              (A) Be provided to each party in written form;

13              (B) Be signed by the authorized representatives of the

14 department and the utility; and

15              (C) Include:

16                         (i) The plan for the relocation;

17                         (ii) The schedule for the utility to complete the

18 relocation;

19                         (iii) A cost estimate for the relocation;

20                         (iv) Deadlines for the commencement and completion

21 of the relocation; and

22                         (v) The estimated cost of reimbursement by the

23 department for the relocation.

24              (3)(A) The rules for a relocation agreement shall include that a

25 relocation agreement may be modified if:

26                         (i) An extraordinary event occurs; and

27                         (ii) Either party requests a modification to the

28 relocation agreement.

29              (B) The modification of a relocation agreement shall:

30                         (i) Be documented in writing;

31                         (ii) Include updated timelines, costs, or other

32 relevant terms; and

33                         (iii) Be approved by both parties.

34              (4) Rules for the reimbursement of the costs for a relocation

35 shall include without limitation that the:

36              (A) Utility owner may submit an invoice for the

                                    10                 04-07-2025 20:00:57 ZRC016
    As Engrossed: S4/7/25                                                 SB492

1 reimbursement of costs to the department upon completion of the relocation;

2   (B) Invoice for the reimbursement of costs for the

3 relocation shall reflect all costs and expenses incurred by the utility for

4 the relocation; and

5   (C) Department shall pay a complete invoice submitted

6 under subdivision (b)(4)(A) of this section within ninety (90) days of

7 receipt of the complete invoice by the department.

8

9                          /s/J. Bryant

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

                           11                         04-07-2025 20:00:57 ZRC016
Every fact on this page links to its source, starting with the official bill record.